A06_Specifications_Final_1.docx
DOCX document 32 KB Posted
- Attached to
- PRECAST CONCRETE VAULT TOILETS Federal contract opportunity
- Solicitation number
- 140P6222Q0027
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A14_Market_Research_Sources_Sought_Announcement_1.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications
All product/materials contained in the below sections are subject FAR Clause 52.211-6 Brand Name or Equal.
Despite a manufacturer and product being listed, it is a suggested product, but all products/materials are brand name or “or equal”.
Brand name or equivalent product must use manufacturer’s instructions and recommendations for product installation/application.
A. Precast Concrete Vault Toilet – Single User CXT- Rocky Mountains Style Single or NPS approved equivalent:
1. (2) Single Concrete Vault: 1,000 gallon, Single User Concrete Building, both sites will be Right Hand Floor Plan (to protect door and entrance walls during flooding), Exterior Finish: Barnwood, Exterior Roof Finish: Cedar Shake. Exterior Siding Paint: Color Match to Sand Beige – Roof Covering Paint, Color Match Java Brown. Fully accessible to (Architectural Barriers Act – ABA and American with Disabilities Act – ADA) standards. Single Toilet Riser (ABA/ADA), Grab Bars (ABA/ADA), Single Waste Clean Out Hatch, Single Urinal.
a. Final color must be approved by the COR.
b. Exterior must have horizontal or vertical textured panel or plank walls.
2. Vault Minimum Dimensions:
a. Height: 4 feet, 4 inches
b. Width: 6 feet, 6 inches
c. Length: 14 feet, 7.5 inches
3. Building Minimum Dimensions:
a. Floor Dimensions: 5 inch height, 6 feet 6 inches width, 14 feet 7.5 inches length
b. Total Building: 11 feet 6 inches height (not including stack) (15 feet with Stack), 8 feet 6 inches width, 14 feet 7.5 inches length.
4. Marine Environment Corrosion Protection
5. Accessories include:
a. Double Toilet paper Holder
b. Solar Light Kit
c. Solar exhaust Fan Kit
d. Owl Guard
6. Specifications are based off of CXT’s ROCKY MOUNTAIN BUILDING STYLE single user model.
SPECIFICATIONS
ROCKY MOUNTAIN BUILDING STYLE
1.0 SCOPE
This specification covers the construction and placing of precast Rocky Mountain toilet buildings as produced by CXT® Incorporated. All products and materials are brand name “or equal”.
2.0 SPECIFICATIONS
ASTM C33 Concrete Aggregates ASTM C39 Method of Test for Compressive Strength of Cylindrical Concrete Specimens ASTM C94 Standard Specification for Ready-Mixed Concrete ASTM C143 Method of Test for Slump of Concrete ASTM C150 Standard Specification for Portland Cement ASTM C172 Standard Practice for Sampling Freshly Mixed Concrete ASTM A185 Standard Specification for Steel Welded Wire Reinforcement, Plain, or Concrete ASTM C192 Method of Making and Curing Test Specimens in the Laboratory ASTM C231 Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method ASTM C309 Standard Specifications for Liquid Membrane-Forming Compounds for Curing Concrete ASTM C494 Standard Specification for Chemical Admixtures for Concrete ASTM A615 Standard Specification for Deformed and Plain Carbon-Steel bars for Concrete Reinforcement ASTM C618 Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete ASTM C979 Standard Specification for Pigments for Integrally Colored Concrete ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort ACI 211.1 Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete ACI 306 Cold Weather Concreting ACI 318 Building Code Requirements Structural Concrete and Commentary (includes Errata) PCI MNL 116 Quality Control for Plants and Production of Precast Prestressed Concrete Products
3.0 MANUFACTURER CRITERIA
The manufacturer supplying the requested precast concrete vault facility must meet the following:
A. Manufacturer must be ISO 9001 certified at the time of bid.
B. Manufacturing plant must be PCI certified at the time of bid.
C. Manufacturer must not have defaulted on any contract within the last five (5) years.
D. Manufacturer must provide stamped, engineered drawings prior to acceptance.
E. Manufacturer must be pre-approved prior to bidding.
F. Manufacturer must show four (4) examples of designed precast concrete vault toilet facilities produced, installed, and in use as an example of their ability to perform on this contract.
G. Manufacturer shall provide a one (1) year warranty.
H. UL 752 Bullet Resistance on 4” thick concrete samples.
4.0 DESIGN CRITERIA
Vault buildings have been designed to individually meet the following criteria. Calculations and engineer’s stamped drawings are available, for standard buildings, upon request by the customer and are for their sole and specific use only. The design criteria are to ensure that they not only will withstand the forces of nature listed below but will provide protection from vandalism and other unforeseen hazards. Building will be manufactured using precast concrete including the roof.
Building’s structural and foundation design will be relevant to the region and properties associated with its final placement. Design will also meet all applicable accessibility and building code requirements. Vault buildings also to meet various structural loads such as below, but not limited to/or restricted by them.
A. Roof Snow Load
1. Vault buildings are designed to withstand a 350 pounds per square foot snow load.
B. Floor Load
1. Vault buildings are designed to withstand 400 pounds per square foot floor load.
C. Wind Load
1. Vault buildings will withstand the effects of 150 miles per hour (3-second gust) wind Exposure.
D. Earthquake
1. Vault buildings will withstand the effects of a seismic design category E earthquake.
E. Sweet Smelling Technology (SST)
1. Vault buildings incorporate design aspects of SST as outlined by Briar Cook for the U.S.
Forest Service.
2. All wall to floor interior surface seams shall have a minimum 1” radius coving made of high strength grout.
3. The vault shall have a bottom slope of 1” per foot from under the toilet riser out to the outside cleanout area.
4. The vault shall have a 24” diameter (minimum) lightweight manhole cover installed to the rear or side of the building.
a. The manhole cover should be raised, with the surrounding concrete sloped away using a minimum slope of ½” per foot.
5. The depth of the vault shall be no deeper than 4½’ to 5’.
6. A 12” diameter round pipe will be installed to vent the vault and the pipe shall be raised a minimum of 3’ above the highest point of the roof.
a. Vent pipe shall be straight up from the vault.
7. There shall be only one vent opening in the building and it shall be placed only on one side of the building (the side that the wind blows against).
F. Additional Design Standards
1. Single vault buildings are an all concrete design with a minimum 7/12 roof pitch.
2. Vault buildings shall have a minimum 4” wall, 4½” roof, and 5” floor thickness.
3. Vault buildings have a one-piece floor unit to prevent panels that migrate in different directions during periods of freeze/thaw stress.
4. Vault buildings have a one-piece full length and width vault unit to support the building, screen area, and snow loads evenly.
5.0 MATERIALS
A. Concrete – General
1. The concrete mix design is designed to ACI 211.1 to produce concrete of good workability.
2. Concrete will contain a minimum of 675 pounds of cementitious material per yard. Cement is a low alkali type I/II or III conforming to ASTM C-150.
3. Coarse aggregates used in the concrete mix design will conform to ASTM C33 with the designated size of coarse aggregate #67.
4. Maximum water/cement ratio will not exceed .45.
5. Air-entraining admixtures will conform to ASTM C260. Water reducing admixtures will conform to ASTM C494, Type A.
6. If Self Compacting Concrete (SCC) is used, it must conform to ASTM C1611.
B. Concrete – Cold Weather
1. Cold weather concrete placement is in accordance with ACI 306.
2. Concrete will not be placed if ambient temperature is expected to be below 35ºF during the curing period unless heat is readily available to maintain the temperature of the concrete at least 50ºF.
3. Materials containing frost or lumps of frozen materials will not be used.
C. Concrete – Hot Weather
1. The temperature of the concrete will not exceed 90ºF at the time of placement. When the ambient reaches 90ºF the concrete is protected with moist covering.
D. Concrete Reinforcement
1. All reinforcing steel will conform to ASTM A615. All welded wire fabric will conform to
ASTM A185.
2. All reinforcement is new, free of dirt, oil, paint, grease, loose mill scale and loose or thick rust when placed.
3. Details not shown on drawings or specified are to ACI318.
4. Steel reinforcement is centered in the cross-sectional area of the walls and will have at least 1¼” of cover on the under surface of the floor.
5. The maximum allowable variation for center-center spacing of reinforcing steel is ½”.
6. Full lengths of reinforcing steel are used when possible. When splices are necessary on long runs, splices are alternated from opposite sides of the components for adjacent steel bars.
a. Lap bars under #4 a minimum of 12” bar diameters.
b. Lap bars larger than #4 a minimum of 24” bar diameters.
7. Reinforcing bars are bent cold. No bars partially embedded in concrete are field bent unless approved by the customer.
E. Caulking, Grout, Adhesive and Sealer
1. Caulking service temperatures from -40ºF to +194ºF.
2. Interior and exterior joints are caulked with a paintable polyurethane sealant.
3. Grout is a non-shrink type and are painted to match the color of surrounding concrete as nearly as possible.
4. Cement base coating is formulated with a very fine aggregate system and is a built-in bonding agent.
F. Lockset
1. Lockset will meet ANSI A156.2 Series 4000, Grade 1 cylindrical lockset for exterior door.
MUST USE BEST CORE LOCK SYSTEM
2. Heavy duty tamper resistant.
3. 2¾” backset.
4. U.S. 26D finish.
G. FRP Doors and Jams
1. Doors will be flush FRP,
2. Door frames FRP. Three (3) rubber door silencers will be provided on latch side of frame.
H. Door Hinges
1. Door hinges will be three (3) per door with dull chrome plating 4½” x 4½”, adjustable tension, and automatic closing for each door.
2. Three (3) rubber door silencers are provided on latch side of frame.
I. Doorstop
1. Dome style stop meeting ANSI 156.16.
J. Door Sweep
1. Provided at the bottom of door with an adjustable brush.
K. Double Coat Hook
1. 16-gauge (1.5mm), type 304 stainless steel.
2. Formed construction with a satin finish and have ³̷₁₆” x ⅞” nail in anchor.
3. Upper hook extends at least 2½” from the wall.
4. Lower hook will extend at least 1¼” from the wall.
L. Grab Bars
1. 18-gauge, type 304 stainless steel with 1½” clearance.
2. Able to withstand 300-pound top loading.
M. Lockset
1. Meets ANSI A156.2 Series 4000, Grade 1 cylindrical lockset for exterior door.
2. Lever handle both inside and out.
3. Either handle operates latch unless outside handle is locked by inside push-button.
4. Push-button will automatically release when inside lever handle is turned or door is closed.
5. Emergency slot on exterior so door can be unlocked from the outside with a coin, screwdriver, etc.
6. Inside lever always active.
7. U.S. 26D finish.
N. Paint
1. All paints and materials will conform to all federal specifications or be similar “top-of-theline-components.”
2. Paints will not contain more than .06% by weight of lead.
3. Type of paints for toilets.
a. Inside concrete surfaces.
i. Interior floors – chemical resistant urethane. The color is gray.
ii. Interior walls and ceilings – modified acrylic, water repellent penetrating stain. The color is white followed by a clear acrylic anti-graffiti sealer.
b. Exterior concrete surfaces.
i. Exterior slab – clear sealer.
ii. Exterior walls and roof – . Paint – MUST USE JAVA BROWN FOR ROOF AND DOORs and SAND BEIGE EXTERIOR WALLS - water repellent penetrating stain in the same color as the walls or roof followed by a clear acrylic anti-graffiti sealer.
c. Metal surfaces (both inside and out).
i. DTM ALKYD.
O. Riser
1. Meets ADA standards.
2. Molded one-piece HDPE polyethylene.
3. Smooth surface and have high impact resistance at extremely cold temperatures.
P. Sealers and Curing Compounds
1. Curing compounds, if used, are colorless, complying with ASTM C309, type I or 1-D.
2. Weatherproofing sealer for exterior of building are a clear water repellent penetrating sealer.
Q. Signs
1. Signs to have raised pictograms, letters, and braille to meet ADA.
2. Interior to have “No Trash in Vault” sign.
3. All signs inset a minimum of ¾” into wall with 45-degree bevel.
4. All signs to be anchored into concrete with ¼” x ¾” concrete anchor nails.
R. Toilet Paper Dispenser
1. Constructed of ¼” thick, type 304 stainless steel.
2. Holds three (3) standard rolls of toilet paper.
3. Fastening system able to withstand 300-pound top loading.
S. Polyethylene Vault Liner
1. Made of a Roto molded 8460 polyethylene.
2. Holds up to 1,000 gallons of waste or 15,000 uses per vault.
3. Minimum thickness .100.
4. Molded dovetail embeds to attach the liner to concrete walls of the vault.
5. Welded (2) C-channels to attach the liner to the bottom of the vault.
T. Vent Stack
1. Minimum 12” in diameter and a minimum 3’ higher than the roof peak.
U. Wall Vent
1. Vent cover is 14-gauge, type 304 stainless steel painted with DTM and anchored into the concrete wall with high strength anti-rust tap con fasteners.
2. Vent louver frame and louvers are non-vision, .1” extruded, aluminum jet coat finish.
3. Vent comes with insect screen.
4. Cover to be recessed a minimum ¾” on exterior walls with a 45-degree bevel. Interior to be flush mounted. Wall vent will not protrude from the wall.
V. Windows and Vault Cleanout Cover
1. Windows and cleanout cover frames are constructed from steel.
2. Window glazing is ³̷₁₆” thick translucent pebble finished mar-resistant Lexan.
3. Plate for vault cleanout cover is ¼” thick diamond plate steel.
4. Lid is hinged and configured so that it can be locked with a padlock. A gasket is provided around the entire perimeter of the lid to provide an airtight seal.
5. Windows to have ¾” recess with 45-degree bevel.
6. Windows frames to have vandal resistant fasteners.
7. Window to be constructed of a minimum 4 x4 x ¼ square tube.
W. Optional Roof Insulation
1. Ceiling anchored ½” plywood + fiberglass laminate + 2” polyurethane foam.
Approximately R-19.
6.0 MANUFACTURE
A. Mixing and Delivery of Concrete
1. Mixing and delivery of concrete are in accordance with ASTM C94, Section 12.6 through 12.9.
B. Placing and consolidating concrete.
1. Except for SCC, concrete is consolidated by the use of mechanical vibrators. Vibration are sufficient to accomplish compaction but not to the point that segregation occurs.
C. Finishing Concrete
1. Interior floor and exterior slabs are floated and troweled.
2. All exterior building walls and exterior screen walls are any one of the available textures.
3. All exterior surfaces of the roof panels are cast to simulate any one of the available textures.
The underside of the overhang will have a smooth finish.
D. Cracks and Patching
1. Cracks in concrete components which are judged to affect the structural integrity of the building are rejected.
2. Small holes, depressions, and air voids are patched with a suitable material. The patch will match the finish and texture of the surrounding surface.
3. Patching will not be allowed on defective areas if the structural integrity of the building is affected.
E. Curing and Hardening Concrete
1. Concrete surfaces will not be allowed to dry out from exposure to hot, dry weather during initial curing period.
7.0 FINISHING AND FABRICATION
A. Structural Joints
1. Wall components are joined together with two (2) welded plate pairs at each joint.
2. Each weld plate is 6” long and located one (1) pair in the top quarter and one (1) pair in the bottom quarter of the seam.
3. Weld plates are anchored into the concrete panel and welded together with a continuous weld.
4. Inside seams are a paintable caulk.
5. Outside seams will use a caulk in a coordinating building color or clear.
6. Walls and roof are joined with weld plates, 3" x 6" at each building corner.
7. The joint between the floor slab and walls are joined with a grout mixture on the inside, a matching colored caulk on the outside and two (2) weld plates 6” long per wall.
B. Painting/Staining
1. An appropriate curing time is allowed before paint is applied to concrete.
2. Some applications may require acid etching. A 30% solution of hydrochloric acid are used, flushed with water, and allowed to thoroughly air dry.
3. Painting will not be done outside in cold, frosty, or damp weather.
4. Painting will not be done outside in winter unless the temperature is 50ºF or higher.
5. Painting will not be done in dusty areas.
6. All surface voids are filled prior to painting
7. Schedule of finishes.
a. Inside concrete surfaces.
i. Inside floors – one (1) coat of 1-part water based chemical resistant urethane.
ii. Interior walls and ceilings – two (2) coats of a modified acrylic, water repellent penetrating stain, followed by one (1) coat of clear sealer.
b. Exterior concrete surfaces.
i. Exterior walls – two (2) coats of water repellent penetrating stain in the same color as the walls or roof followed by one (1) coat of clear acrylic anti-graffiti sealer.
c. Metal surfaces (both inside and out).
i. Two (2) coats of DTM ALKYD.
8.0 TESTING
A. Testing will only be performed by qualified individuals who have been certified ACI Technician Grade 1.
B. Sampling is in accordance with ASTM C172.
C. The following tests are performed on concrete used in the manufacture of toilets. All testing is performed in the CXT (PCI certified) laboratories.
1. Air content – checked per ASTM C231 on the first batch of concrete. The air content is in the range of 5.0% +/- 1.5%.
2. Compressive strength of the cylinders – tested to ASTM C39.
a. Two (2) are tested at release (minimum strength of 2500 psi).
b. One (1) is tested at seven (7) days (minimum strength of 4500 psi).
c. Two (2) are tested at 28 days (minimum strength of 5000 psi).
D. A copy of all test reports are available to the customer as soon as 28-day test results are available.
9.0 INSTALLATION
A. Scope of Work
1. Work specified under this section includes excavation, backfill and placement of precast concrete vault toilet.
B. Materials
1. Bedding material to be sand or ⅜” minus crushed or screened aggregate.
2. Caulking between vault and toilet floor to be 1” x 1” Butyl tape designed specifically to bond precast concrete to precast concrete.
C. Location – It is the responsibility of the customer to:
1. Provide exact location by stakes or other approved method.
2. Provide clear and level site free of overhead and/or underground obstructions.
3. Provide access to the site for truck delivery and sufficient area for the crane to install and the equipment to perform the contract requirements.
D. Access to Site
1. Delivery to site made on normal highway trucks and trailers.
H. Exhaust Pipe Installation
1. After exhaust pipe is installed, seal around pipe at top and underside of roof with polyurethane caulk. Seal around pipe at top of slab are accomplished by using polyurethane caulk.
10.0 WARRANTY—PRECAST
Must provide a one (1) year warranty.