A06-Specifications.pdf
PDF 331 KB Posted
- Attached to
- JORDAN RIVER NFH-RACEWAY REHAB PROJ
- Solicitation number
- 140F0221R0013
About this file
This document package includes specifications for a concrete project at the Jordan River National Fish Hatchery in Antrim County, Michigan. The Fish and Wildlife Service is soliciting proposals to perform joint and crack sealing of two existing concrete raceways within the 57/58 building and to construct concrete pavement for remaining non-paved areas. Additional improvements shown in the attached drawings are also included. Work will include removal of existing concrete and asphalt, excavation, grading, importing fill, adjusting existing structures, installing reinforced concrete, routing and removing existing concrete joint sealants, installing new sealant, and final cleaning. Special notes require the contractor to stage construction to keep existing raceways operational and protect them from debris, with water flow shutoff only between October 15th and November 15th for sealing one raceway. The solicitation number provided is 140F0221R0013 for the Jordan River NFH Raceway Rehab Project with the Department of the Interior Fish and Wildlife Service listed as the agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NoticetoOfferors_0001.pdf | ||
| PPQ_0001.docx | DOCX document | |
| Sol_140F0221R0013_Amd_0001.pdf | ||
| NoticetoOfferors.pdf | ||
| B03-DOL Wage Determination.pdf | ||
| A14-BID-SCHED.xls | XLS spreadsheet | |
| A06-Drawings.pdf | ||
| CPARS Notice.pdf | ||
| BidBond Form SF24.pdf | ||
| PPQ.docx | DOCX document | |
| Sol_140F0221R0013.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES DEPARTMENT
OF THE INTERIOR
FISH AND WILDLIFE SERVICE
(Region 3)
SPECIFICATIONS
for the
57/58 RACEWAY BUILDING CONCRETE PROJECT
at the
JORDAN RIVER NATIONAL FISH HATCHERY
ANTRIM COUNTY, MICHIGAN
Prepared by the
U.S. Fish & Wildlife Service Infrastructure Management Division
5600 American Blvd. West, Suite 900 Bloomington, Minnesota 55437
Page J - 1
PART III, SECTION J
LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
INDEX
TECHNICAL PROVISIONS/SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01100 SUMMARY OF THE WORK
SECTION 01310 PROJECT COORDINATION
SECTION 01330 SUBMITTALS
SECTION 01420 DEFINITIONS AND STANDARDS
SECTION 01770 PROJECT CLOSEOUT
DIVISION 2 – SITE CONSTRUCTION
SECTION 02071 SELECTIVE DEMOLITION & STAGING
SECTION 02200 EXCAVATION, TRENCHING, AND BACKFILL
DIVISION 3 - CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
SECTION 07900 JOINT SEALANTS
ATTACHMENTS:
PRECONSTRUCTION SAFETY CHECKLIST
SUBMITTAL REGISTER
DIVISION 1 SECTION 01100
GENERAL REQUIREMENTS SUMMARY OF THE WORK
01100-1
PART 1 – GENERAL
1.1 Project Title: 57/58 Raceway Building Concrete
Project at the Jordan River National Fish Hatchery.
1.2 Work Under These Specifications: The Fish & Wildlife
Service is requesting proposals to perform joint and crack sealing of the Two existing concrete raceways that are located within the 57/58 Building and to also construct concrete pavement for the remaining non-paved areas of the 57/58 building. At the same time, the FWS would like to make additional improvements as shown on the attached drawings. Contractor shall furnish materials, labor, and equipment for the work described below.
Work includes but is not limited to:
1. Removal of existing concrete and asphalt.
2. Excavation, grading, importing fill material, and compacting fill materials.
3. Adjusting existing manholes, valves and other items to be incorporated into the new pavement.
4. Installing new reinforced concrete pavements.
5. Route and remove existing concrete joints sealants in the raceway walls and floors.
6. Install new concrete joint sealant.
7. Final Cleaning of disturbed areas..
and other associated work at the Jordan River National Fish Hatchery.
Special Notes:
This facility must remain operational during construction of the project.
1. The contractor shall be required to stage the construction in order to keep the existing facilty functional. The shorter raceways within the building must remain operational and shall be protected from debris during construction.
The water flow to the raceways which are to be crack sealed may only be shut down between October 15, 2021 thru November 15, 2021. The sealing of the new raceways must be completed and flow restored before Nov. 15, 2021. The
01100-2 contractor shall coordinate the shut down time with the Hatchery. The other concrete work can be completed at any time during the period of performance.
2. Construction methods shall be reviewed with the
COR and Fisheries staff before starting construction.
3. The contractor shall be required to make every effort to prevent contamination of the water supply to the hatchery from construction related pollution.
This work shall not be measured for payment and shall be paid for on a lump sum basis, complete.
1.3 Location And Inspection Of Site
A. The work site is located at the Jordan River
National Fish Hatchery near Elmira, Michigan as shown on the included drawings. The mailing address is shown on the Solicitation, Offer, and Award (Standard Forms 1442 or, 18 block 9) as attached to this Invitation.
B. All prospective bidders/quoters, contractors, subcontractors, and related persons are encouraged to visit the site(s) of the proposed work and to assess the location(s) and extent of the work prior to submitting bids/quotes. Persons may inspect the work site by contacting the Hatchery Manager. All questions regarding the scope of work shall be presented in writing to the Contract Officer.
1.4 Specifications and Drawings for Construction
A. The successful bidder will be provided, upon request, up to 5 sets of additional half size prints of the contract drawings as necessary for execution of this contract. These drawings will be provided at no additional cost to the successful bidder/quoter.
01100-3
B. Exact location of all affected utilities will be the responsibility of the contractor. Drawings do not completely show existing utilities. Site verification is required in addition to contacting any local authorities and utility companies to determine exact locations of utilities.
C. In case of difference between drawings and specifications, the specifications shall govern.
1.5 Work Not Included In This Contract
A. All items indicated "NIC" on drawings or in specifications are items not included in this contract.
B. Work in place is generally shown as "Existing" on the Contract Drawings.
C. Work to be performed under other contracts and not included as part of this contract is generally shown as "By Others" on the Contract Drawings.
1.6 Items Provided By The Government
A. Work to be accomplished by the Government or manufactured items to be provided by the Government are generally shown as "By Government" on the Contract Drawings.
1. Unless specifically provided herein, no materials or equipment shall be furnished by the Government under this Contract.
1.7 Temporary Facilities
A. Maintain and restore all Government roads, service areas and utilities used to pre-construction condition.
B. Temporary Toilet facilities will be required for workers throughout the project.
C. Temporary electric/power supply for construction will be the responsibility of the contractor.
01100-4
D. The hatchery will not provide phone/fax services and will not accept deliveries or unload deliveries.
E. The hatchery will not provide tools, parts, or other equipment to the contractor for use during
1.8 Site Access, Staking and Right of Way
A. The construction access limits on Government property will be established by the Government and the Contractor shall be responsible for complying with these limits and governing all work accordingly. All temporary access roads shall be removed following work completion unless directed otherwise by the Contracting Officer.
B. Construction staking will not be provided by the
Government, the contractor shall include all costs to stakeout, mark, survey, or otherwise layout the work to be accomplished as part of this contract.
C. Maintain traffic and public safety in a safe manner with signs, barricades, lights, and watchmen as required. Follow Manual of Uniform Traffic Control Devices (MUTCD). Load limits and other restrictions shall be obeyed. All bidders are reminded that they are responsible for contacting the local entity such as township, county, or state having jurisdiction in the project vicinity to insure bidders/quoters are aware of any requirements of the local entity.
These requirements are between the entity and the bidder. If the Contractor proposes to cross private property, permission must be obtained from the owner to use private property or roads in the conduct of the Work.
D. Work scheduled on Saturdays, Sundays, Federal
Holidays or other than normal working hours shall be approved in advance by the COR, Hatchery Manager, and Contracting Officer.
01100-5
1.9 Safety - In addition to FAR 52.236-13 Accident
Prevention
A. The contractor shall designate a safety officer to ensure a safe work site. The safety officer shall perform daily work site inspections to assure compliance with all safety regulations and standards.
B. The Contractor’s Safety Plan shall be available on-site. The Contractor shall provide Safety Data Sheets (SDS) for all hazardous materials brought on-site. SDS shall be made available in a conspicuous location.
C. The Contractor shall provide a Pre-construction
Safety Checklist during the preconstruction conference.
D. All equipment and work activities shall comply with OSHA Regulations and all accidents incidental to work performed under this contract shall be reported in accordance with OSHA reporting requirements. Additionally, a copy of the accident report shall be provided to the Contracting Officer.
E. The contractor shall provide and install safety barricades, signs, or other warning devices to delineate & warn the public of the construction area.
F. Provide at least one non-freezing-type fire extinguisher in each workshop and shed used for storage of materials on the premises. Place in location readily accessible to workers.
G. Provide at least one non-freezing-type fire extinguisher of the appropriate class for each group of workers performing flammable procedures.
H. Provide and maintain a basic first aid kit for use of workers.
(a) Provide first aid supply commensurate with size of project with items necessary for first aid treatment of all injuries. The
01100-6 first aid supply shall include items identified on SDS (see paragraph B of this section) in applicable locations.
(b) Advise all workers of the location of first aid supplies.
(c) Post telephone numbers of nearest hospital or ambulance service and fire station in conspicuous location. Advise all workers of location of telephone numbers.
I. Provide necessary Personnel Protective Equipment
(PPE) as identified by SDS and OSHA regulations.
Provide documentation, workers have been trained in use of PPE prior to individual use.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
(END OF SECTION 01100)
DIVISION 1 SECTION 01310
GENERAL REQUIREMENTS PROJECT COORDINATION
01310-1
PART 1 - GENERAL
1.1 Jobsite Administration - Superintendence, Subcontract
administration and Quality Control, is the responsibility of the Contractor.
A. Final decisions relative to items in conflict shall be made by the Contracting Officer.
B. The Government shall have the authority to temporarily suspend the Work for such time as necessary because of the failure on the part of the Contractor to perform any of the provisions of the Contract. No extension of contract performance time will be permitted until the Government determines that the deficiencies in performance, which caused the temporary suspension, have been corrected.
C. The Contractor shall have responsible superintendence on site during all project operations. Contractor shall notify Government of any changes of superintendents.
D. The Contractor shall notify the COR at least ten (10) days prior to the anticipated date of completion of all Work specified herein. Upon completion of the Work, the COR shall proceed with the final inspection which shall be completed as promptly as practicable.
The time required for such inspection and for performing any corrective Work shall be included in the contract performance time.
F. The contractor shall notify the COR and Inspector five
(5) days prior to any concrete pours, paving and back filling so that the Inspector can be on-site to perform inspections.
1.2 Modification/Change Order procedures
A. In the event of the need for a Change Order, the Contractor will receive a letter requesting a price quote for proposed changes to the Contract.
01310-2
B. For evaluation purposes, the Contractor's quote shall be broken down to show the costs of labor and materials for each proposed category of Work included with the change, along with the total cost for Contractor's overhead, profit, and bond for the proposed changes.
C. All Contract time extensions required as a result of a proposed change must be justified and supported in detail at the time of the proposal.
1.3 Preconstruction Conference
A. Soon after award of the Contract and prior to commencing construction, the Contractor and any subcontractors shall attend a preconstruction conference with representatives of the Government.
Timely notification of the meeting will be given to the Contractor. Time, date, and place of the conference will be determined by the Contracting Officer. Requirements pertaining to Contract administration, construction operations and the project schedule will be discussed. The project schedule shall be in accordance with Section 01330.
The Preconstruction Safety Checklist shall be submitted for review during this conference. Please pay special attention to Question #15 of the “Preconstruction Safety Checklist”.
1.4 Progress Meetings
A. Periodic general project meetings will be conducted with a representative of the Contractor at the project site or by telephone by the Government's representative for the purpose of coordinating, expediting, and assessing the work progress.
B. The Contractor shall provide reports of progress on the project, discuss the work schedule for the coming period and present all conflicts, discrepancies or other difficulties for resolution. A record of
01310-3 discussions and decisions will be prepared by the Government and distributed to those attending and others affected.
PART 3 - EXECUTION (not Applicable)
(END OF SECTION 01310)
DIVISION 1 SECTION 01330
GENERAL REQUIREMENTS SUBMITTALS
01330-1
1.1 General:
A. Refer to submittal register or technical specifications for all submittals required.
B. When specifically requested by the Contracting Officer
(CO), Contractor’s Officer’s Representative (COR) or the Government’s Construction Inspector, the Contractor shall provide copies of manufacturer's written installation instructions and/or recommendations for review and approval prior to accomplishing equipment installation.
1.2 Submittal Register:
A. A submittal register, listing items requiring submittals under this solicitation, is provided as an attachment to this document. Additional submittals may be required by the specifications that are not listed in the register. The Contractor shall provide all required submittals to the COR within 30 days of award except for items noted otherwise on the submittal register.
B. Furnish a minimum of four copies of all required submittals. Three copies will be retained by the Government. The remaining copies will be returned to the Contractor.
C. The approval of submittals shall not relieve the
Contractor to comply with the terms and conditions of the Contract Drawings and Specifications. The Contractor shall be responsible to determine correct dimension, design, connection, detail and satisfactory construction of all Work.
1.3 Project Schedule: Contractor shall provide as required by
Federal Acquisition Regulation (FAR) clauses. *
DIVISION 1 SECTION 01330
GENERAL REQUIREMENTS SUBMITTALS
01330-2
1.4 Price Breakdown - Lump Sum Items: Contractor shall provide as required by FAR clauses. *
1.5 Subcontractor's List
A. Submit a list of subcontractors who will be working on the project.
1.6 Submittal of Progress Payment Certificate: Contractor shall provide as required by FAR clauses. *
1.7 Guarantees, Warranties And Certificates: Refer to Section
01770
1.8 Operating And Maintenance Instruction: Refer to Section
01770
1.9 Delivery Tickets
A. The Contractor shall submit to the Government's on site representative, one legible copy of each delivery ticket for all material delivered to the construction site.
B. The delivery ticket shall show brand name, catalog number, and number of items received.
1.10 Waste Manifests
A. The Contractor shall submit copies of all waste manifests.
B. Manifests shall state type of waste (i.e., construction debris, hazardous asbestos, etc.), location of disposal, landfill designation, EPA registration of landfill, and EPA registration for transportation of any hazardous wastes.
* The applicable FAR clauses will be provided in full text to the resultant contractor at the pre-construction conference.
(END OF SECTION 01330)
DIVISION 1 SECTION 01420
GENERAL REQUIREMENTS DEFINITIONS AND STANDARDS
01420-1
1.1 Regulatory Requirements
A. All Work shall be accomplished in strict accordance with the regulations, codes, and laws in effect at the time the Work is performed for the location where it is to be performed. All completed construction shall comply with OSHA, NFPA, NEC and ABA regulations.
B. All work performed on this project shall comply with
Title 40, Protection of the Environment, Code of Federal Regulations.
C. All electrical installations, components and work shall comply with the most current edition of NFPA 70 National Electric Code.
1.2 Means and Methods
A. Means and methods used in the performance of this Contract must be in accordance with all applicable Federal Acquisition Regulations in addition to OSHA regulations, 29 Code of Federal Regulations, acceptable industry practices as recognized by societies, associations, building codes, manufacturers’ specifications and any applicable state safety and health requirements.
1.3 Permits
A. All permits required to support the construction activities such as road permits for oversize, overweight vehicles and equipment, bridge permits, and utility hookup permits, shall be obtained and paid for by the Contractor.
(END OF SECTION 01420)
DIVISION 1 SECTION 01770
GENERAL REQUIREMENTS PROJECT CLOSEOUT
01770-1
1.1 Manufacturer's Specifications
A. The installation of manufactured products and equipment, together with all associated parts, shall be in conformance with the manufacturer's recommendations, and code requirements. All installations shall be complete and ready for immediate use, and every part required for proper operation of the manufacturer's equipment shall be provided. Following the completion of the Work under this Contract, all installed equipment shall be tested for proper operation and compliance with the Contract.
1.2 Final Inspection
A. The Contractor shall request a final inspection in writing at least ten (10) days prior to the anticipated date of completion.
B. Work will not be considered ready for final inspection until all the Work has been completed and the Contractor has certified that all items are properly operating and in strict compliance with all Contract terms and conditions.
C. The Contractor or the project supervisor shall be at the job site during the final inspection.
1.3 Tests
A. Complete all tests required to prove actual operating performance of equipment and systems incorporated into the project.
B. Submit reports of all tests to the Contracting Officer prior to final payment.
C. Provide any regulatory acceptance documents in cases of cleanup.
01770-2
1.4 Maintenance and Operating Instructions
A. Submit three (3) final copies of all operating, maintenance instructions and parts lists for all equipment and systems that require adjustment, servicing, and attention for proper operation.
Include all information necessary for proper operation of equipment. Use simple, non-technical language where possible. Provide all necessary diagrams and schematics required by repairmen. Any hazards likely to occur in operation of equipment shall be pointed out to avoid improper operation of any equipment that might result in damage or danger to equipment, building or personnel.
B. Final copies of all maintenance and operating information shall be submitted in bound form as a "Manual of Operating Instructions" with items grouped by sections of Work. Append each manual with name, address, telephone number of Contractor, subcontractor and companies or individuals providing service for equipment used.
C. Provide competent personnel to meet with the
Government representative to fully explain and familiarize the Government personnel with all equipment and its operation and maintenance.
1.5 Record Drawings:
The Contractor shall provide and maintain in proper order and in good, clean condition, at the project office or at the project site, one (1) complete set of full size prints of all Drawings. On this set, with red pencil or ink, the Contractor will neatly inscribe all changes in Work. At time of final acceptance, and prior to final payment, these corrected prints will be presented to the COR. The Contractor will note all data and changes on these record drawings in sufficient detail and clarity to provide information necessary for preparation of "as built" drawings by the Government.
01770-3
1.6 Guarantees, Warranties and Certificates
A. The Contractor will submit all guarantees, warranties and certificates to the Government prior to final payment.
B. The Government requires a 100% warranty for a period of one full year after final acceptance. Items of Work found defective during the warranty period will be replaced at no cost to the Government and the warranty for that particular part of the Work shall automatically extend for one full year beyond the completion date of repairs.
C. If a manufacturer or supplier offers a guarantee in excess of the one year requirement outlined herein, then the longer guarantee period will apply for those particular items.
(END OF SECTION 01770)
DIVISION 2 SECTION 02071
SITE WORK SELECTIVE DEMOLITION & STAGING
02071-1
1.1. General
1. The work of this section consists of the demolition, removal, and disposal of the existing concrete, asphalt, and other miscellaneous items as shown on the drawings.
PART 2 – PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 Disposal
1. Concrete/asphalt material or other non-regulated demolition material shall be removed from the hatchery site and disposed of in accordance with State and local regulations.
2. All hazardous demolition material such as treated wood shall be removed from the hatchery site and disposed of in an EPA licensed landfill or as otherwise required by state and local regulations.
3. The contractor is encouraged to take any non-regulated materials removed from this project to a recycling center.
4. Excavated materials or mixtures of materials such as rock, clay, or saturated soils that are not suitable for reuse and compaction shall be removed and disposed of legally off the hatchery site.
3.2 Execution
1. The Contractor shall demolish, remove, and dispose of the existing concrete and asphalt pavement including but not limited to the concrete, asphalt, and other items as shown on the drawings.
DIVISION 2 SECTION 02071
SITE WORK SELECTIVE DEMOLITION & STAGING
02071-2
2. The contractor shall adjust all existing valves, floor boxes, and pipes to the proposed finish grade of the new pavement.
3. The use of explosives will not be permitted.
4. All existing pavements, sidewalks, or other surfaces where construction shall be connected, shall be saw-cut at removal limits. The contractor shall take special precautions to ensure saw dust or water used during sawing does not contaminate, or pollute the adjacent raceways.
5. The Contractor shall provide pumps, dams, sheet piling, or other dewatering methods as needed to construct the improvements.
3.3 Construction Staging
1. The Contractor shall stage construction so that the existing raceways that are not to be crack sealed can remain operational while the new improvements are constructed.
(END OF SECTION 02071)
DIVISION 2 SECTION 02200
SITE WORK EXCAVATION, TRENCHING AND BACKFILLING
02200-1
1.1 General
A. The requirements of this section shall include the excavation, backfilling, compaction, and grading necessary for the installation of the improvements as shown on the drawings and specified herein.
B. The Contractor shall have the local utility field mark utility locations and verify location of existing utilities prior to excavation.
C. The Contractor shall design and construct a dewatering system in order to keep all excavations free of water.
D. Trench excavations shall be as shown on the trench detail in the Contract Drawings.
E. The Contractor shall compact all locations disturbed by construction operations to eliminate voids and settling.
1.2 Submittals
A. Granular Material (for pipe bedding): Submit Gradation, Material Certification, and Stockpile location.
B. Engineered or Granular Fill Material: Submit Gradation, Material Certification, and Stockpile location.
C. Test Report: Provide successful compaction tests reports prior to submitting for progress payment.
PART 2 – PRODUCTS
2.1 Materials
A. Embankment and backfill material: All fill areas and trench backfills shall be imported and compacted Granular Fill material.
B. Granular Material: Granular material furnished and used in the work shall consist of natural sand.
02200-2
PART 3 – EXECUTION
3.1 Execution
A. Pipe, Wall and other Misc. Excavation
1. All trench areas shall be excavated and free (stripped) of any gravel, topsoil, or vegetation.
2. Over-excavation below grade shall be corrected by replacing and compacting with Engineered Fill material.
3. Slopes: Excavated to at least the angle of repose and as required by the State or OSHA, whichever is more restrictive. Brace, shore, and otherwise support excavations in order to protect property and provide worker safety.
4. Pile excavated material in a manner that will not endanger work or pollute the adjacent creek. Remove excavated materials from the site prior to the end of each day.
5. Dewater ground as necessary to excavate trench and install improvements. Hold ground water level to a minimum 2 feet below bedding. Provide filter bags and other means of preventing downstream erosion, sedimentation, and pollution.
6. Over-excavate when bottom of trench contains unstable or unsuitable material. Bring excavation up to grade with engineered fill material. Notify COR of soil conditions which may be poor bearing capacity and when organic soils are encountered.
7. Provide temporary support, remove, relocate, or reconstruct existing utilities located within trench excavation. Utility owner shall designate method employed. Use care and provide compacted fill or other stable support for utility crossings
02200-3 to prevent displacement, rupture, or failure.
8. All trenches shall be excavated and shored as necessary, in accordance with OSHA requirements.
All excavations shall comply with OSHA 29CFR1926, Subpart-P-Excavations. The trench shall be wide enough to permit operation of hand operated compaction equipment without damaging the pipes.
9. Excavated material not suitable or required for backfill shall be hauled and spread out at the designated spoils site located at the hatchery.
Materials containing, wood, concrete, asphalt, rocks, metal, vegetation, or other debris must be hauled off-site and disposed of legally.
B. Backfill
1. Backfill with Granular Fill materials.
2. Backfill material shall be placed in uniform depth layers not exceeding a loose depth of 8-inches and shall be compacted over the entire width. Backfill not meeting the requirement shall be excavated and re-compacted.
3. Only mechanical or hand operated compaction equipment shall be used. Water jetting shall not be allowed.
4. Compact materials to 95% of Modified Proctor
Density, per ASTM D 1557. Provide compaction test results to COR for each 8” layer of backfill.
Testing shall be performed by a qualified testing company and certified by a Geotechnical Engineer.
(END OF SECTION 02200)
DIVISION 3 SECTION 03300
CONCRETE CAST-IN-PLACE CONCRETE
03300 - 1
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
B. All concrete work not specifically covered by these specifications shall conform to ACI Standard Building Code Requirements for Reinforced Concrete (ACI 318-77).
1.2 SUMMARY
A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following:
1. Concrete pavement, drives, or floors within the raceway building
B. Related Sections:
1. Division 2, Sections: 02200-Excavation, trenching, and backfill. 02630-Water drainage.
1.3 DEFINITIONS
A. Cementitious Materials: Portland cement Type I, IA, III, or IIIA conforming to the requirements of ASTM C-150.
1.4 SUBMITTALS
A. Design Mixtures: The proportions of all components of the concrete mix shall be by weight and shall be submitted for approval prior to placement of any concrete. The approved mix design and supplier shall not be changed throughout concrete placement unless a new mix design and supplier are approved.
03300 - 2
1. Indicate amounts of mixing water to be withheld for later addition at Project site.
B. Steel Reinforcement: Include information from manufacturer on bar sizes, lengths, material, grade, and supports for concrete reinforcement.
C. Material Certificates: For each of the following:
1. Cementitious materials.
2. Admixtures.
3. Steel reinforcement and accessories.
4. 10mil Vapor Barrier
1.5 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs Project personnel who are qualified as ACI-certified Flatwork Technicians and Finishers and a supervisor who is an ACI-certified Concrete Flatwork Technician.
B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."
PART 2 - PRODUCTS
2.1 REINFORCEMENT ACCESSORIES
A. Reinforcing steel bars shall conform to the requirements of ASTM A-615, grade 60, latest revision.
B. Reinforcing steel shall not be epoxy coated.
03300 - 3
2.2 CONCRETE MATERIALS
A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project:
1. Portland Cement: ASTM C 150, Type I, IA, III, or
IIIA.
B. Normal-Weight Aggregates: ASTM C 33, coarse aggregate or better, graded. Provide aggregates from a single source
1. Maximum Coarse-Aggregate Size: 1 inch nominal.
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
C. Water: ASTM C 94/C 94M and potable.
2.3 ADMIXTURES
A. Air-Entraining Admixture: ASTM C 260.
B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.
1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A.
2.4 CONCRETE MIXTURES
A. Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength: 4500 psi at 28 days.
2. Maximum Water-Cementitious Materials Ratio: 0.45
3. Slump Limit: 3-5 inches.
4. Air Entrainment Admixture-ASTM C-260
5. Air Content %: 5-8%
2.5 VAPOR BARRIER
A. Provide a 10mil Class A Vapor Retarder under all concrete that meets or exceeds ASTM E1745.
B. Provide vapor barrier by Stego Wrap or approved equal.
03300 - 4
PART 3 - EXECUTION
3.1 FORMWORK
A. Provide clean, sturdy, and suitable forms to ensure concrete is poured to the lines and grades specified.
B. Clean forms and adjacent surfaces to receive concrete.
Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.
C. Coat contact surfaces of forms with a non-toxic form-release agent, according to manufacturer's written instructions, before placing reinforcement.
3.2 STEEL REINFORCEMENT
A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement.
B. Clean reinforcement of loose earth, ice, and other foreign materials that would reduce bond to concrete.
C. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.
D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
3.3 JOINTS
A. Control Joints: Install control joints true to line with faces perpendicular to surface plane of concrete as specified on the drawings.
B. Expansion Joints: Install 3/4” Fiber board or foam expansion around all existing pier/column bases. Install other locations as appropriate.
03300 - 5
3.4 CONCRETE PLACEMENT
A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.
B. Do not add water to concrete during delivery, at Project site, or during placement unless approved by Government.
C. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.
D. The contractor shall broom finish all concrete.
3.5 CONCRETE PROTECTING AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.
B. Comply with ACI 306.1 for cold-weather protection.
C. Curing shall be by covering the concrete surfaces with impermeable sheets of polyethylene material with joints lapped and sealed to make watertight or by wet burlap blankets. No chemical curing compounds shall be used.
3.6 TESTING
A. Testing Agency: Contractor must engage a qualified independent testing and inspecting agency to perform field tests and inspections and to prepare test reports.
B. Testing Frequency: Contractor shall take concrete cylinders once daily during concrete construction. Air and slump tests shall be taken at the beginning of concrete placement. All costs for concrete testing shall be included in the contractors bid/proposal.
3.7 FINISHING
A. Light Broomed Finish: Surfaces shall be striked off with a wooden or mechanical screed then floated with a padel, followed by hand troweling and edging. After completion
03300 - 6 of trowel finish, the surfaces shall be slightly roughened by brooming with a fiber-bristle brush.
END OF SECTION 03300
07900 - 1
SECTION 079000 – JOINT SEALANT
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes sealing of existing joints & cracks in concrete, for the following:
1. Raceway slabs and walls.
1.3 STANDARDS
A. All materials and methods shall comply with the specified standard of the American Society for Testing And Materials
(ASTM).
1.4 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Safety Information: Provide Material Data Sheets for each type of product indicated.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs project personnel who have at least 3 years experience in concrete repair.
B. Manufacturer Qualifications: A firm experienced in manufacturing joint sealants for concrete products and whose product is ISO 9001:2008 certified.
C. Source Limitations: Obtain each type of joint sealant from the same manufacturer. Do not mix products.
07900 - 2
D. Install materials in accordance with all safety and weather conditions required by the manufacturer in addition to all local, state, and federal regulations.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Joint Sealants: Deliver sealant to the site in original un-opened containers with clear marking of the manufacturer and showing the expiration date or manufacturing date. Allow all materials to adjust to on-site conditions as per manufacturer’s recommendations.
PART 2 - PRODUCTS
2.1 JOINT SEALANT MATERIALS
A. Specified Sealant:
1. Sikaflext-2c NS EZ-Mix, as manufactured by Sika Corporation, 201 Polito Avenue, Lyndhurst, NJ 07071.
(or approved equal)
2.2 Performance Criteria:
A. Color: Limestone or Gray.
B. ASTM C-920, Type M, Grade NS, Class 25, use T, NT, M, A, G, A, O, I.
C. Meets Federal SpecificationsTT-S-00227E, Type II, Class A
D. Non-sagging to be used for walls & floors.
E. Shelf Life: 1 year minimum
F. Service Temperature Range: -40 to 170 degree F
G. Shore ‘A’ Hardness (ASTM D-2240) 21 day: 25 +/- 5.
H. Tensile Strength (ASTM D-412) at break: 95psi
I. Weathering Resistance: Excellent
07900 - 3
2.3 JOINT SEALANT ACCESSORIES
A. Backer Rods or bond breaker tape: Non-water absorbent foam or rubber rods or tape in variable sizes as approved by the COTR.
B. Primer: Sikaflex Primer manufacturered for this application.
2.4 EPOXY BASED CONCRETE REPAIRS
A. Provide an epoxy based joint filler compatible with the joint sealant and as recommended by the sealant manufacturer for repairs to concrete damaged during joint cleaning.
B. Minimum compressive strength of epoxy mortar shall be 4,500 psi at 28 day cure time.
PART 3 - EXECUTION
3.1 JOINT SEALING AND FILLING
A. Prepare, clean, and install joint sealants according to manufacturer's written instructions. Do not proceed to install joint sealants until the joints are sufficiently dried to the satisfaction of the hatchery staff or COTR.
1. Do not fill joints until existing joint removal operation has permanently ceased.
2. Do not fill joints until the expected air temperature is consistently above 40 degrees.
B. Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave contact faces of joint clean and dry. Blow out all dust and heat lance all to remove all moisture before sealing.
C. Install joint sealant in locations and as specified on the drawings. Do not overfill joint, maintain slightly below top of joint after hardening. Minimum joint depth shall be 1/2". For joints wider than 1/2" use a 1:1 ratio of depth to width.
07900 - 4
3.2 CONCRETE SURFACE REPAIRS
A. Damaged Concrete: Repair and patch areas damaged during the removal of the existing sealant as specified by the Government.
B. Perform repairs of concrete, subject to COTR’s approval, using epoxy adhesive and patching mortar.
C. Repair materials and methods shall be approved in writing by the Government before the repairs are completed.
3.3 FIELD QUALITY CONTROL
A. Testing and Inspecting: Contractor shall perform a field pull test of the sealant to determine if the product is resulting in suitable adhesion of the material to the existing concrete surfaces. When the sealant is pulled it should tear instead of releasing from the concrete surface. If the product is determined not to be adhering to the surfaces, a different primer shall be recommended by the manufacturer and the test shall be performed again.
Testing area shall be no less than 8 feet.
B. Testing and Inspecting: Engage the manufacturer’s representative or testing agency to perform testing and inspections recommended by Sealant Manufacturer; or do pull test that is witnessed by COTR and Hatchery Manager.
3.4 PROTECTION OF JOINT SEALANTS
A. Protect joint sealants from damage and wear during the remainder of construction period and full curing time.
Use protective methods and materials, including temporary covering, recommended in writing by the manufacturer.
END OF SECTION 07900
S U
B M
IT
T
A L
R E
G
IS
T E
R P
A G
E of
D A
T E
S H
O P
D R
A W
IN
G
S , E
Q U
IP
M
E N
T D
A T
A , A
N D
M A
T E
R
IA
L S
A M
P L
E S
C O
N T
R A
C T
N O
C
O N
T R
A C
T O
R
C O
N S
T
M A
N A
G E
R
P R
O
JE
C T
A
D D
R E
S S
L O
C A
T
IO
N
S P
E C
IF
IC
A T
IO
N
D E
S C
R
IP
T
IO
N D
A T
E T
R A
N S
.R E
V
IE
W E
D D
A T
E A
C T
A
C T
IO
N
D A
T E
A C
T
IO
N C
O M
M E
N T
S
S E
C T
IO
N
N O
S
U B
M
IT
T E
D N
O
B Y
T A
K E
N C
O D
E R
E S
U B
M .C
O D
E
0.
1.
S af et y O ff ic er /P la n
0.
1.
P re co ns tr uc ti on S af et y C he ck li st
0.
1.
P ro gr es s
S ch ed ul e
0.
1.
P ri ce
B re ak do w n
0.
1.
S ub co nt ra ct or
's L is t
0.
1.
W as te
M an if es ts
0.
1.
A s B ui lt s
0.
1.
G ra di ng S ub m it ta ls
0.
1.
D es ig n M ix tu re s, r ei nf
I nf o
A ct io n
C od es
A
A pp ro ve d as
S ub m it te d
D
N o
A ct io n
T ak en
S ee
C om m en ts
B
A pp ro ve d E xc ep t A s
N ot ed
R es ub m is si on N ot R eq ui re d
E
D is ap pr ov ed
S ee C om m en ts
R es ub m is si on
R eq ui re d
C
A pp ro ve d E xc ep t A s
N ot ed
R es ub m is si on R eq ui re d
PRECONSTRUCTION SAFETY CHECKLIST
PROJECT LOCATION:
PRECONSTRUCTION MEETING
DATE:
NAME AND ADDRESS OF
CO NT RACT OR :
NAME OF CONTRACTOR
SU PER INT EN DE NT /FO RE M AN
NAME OF SERVICE
CONTRACTING OFFICER:
NAM E O F C ON TR ACT OR ’S
COM PETEN T PERSO N (PER 29
CFR
PROPOSED CONSTRUCTION
STAR T D ATE:
PROJECT T ITLE: CONTRACT NUMBER:
The Fish and Wildlife Service (FWS) places safety and health as a top priority at all Service contracted construction sites (360 FW 4). The contractor has ultimate responsibility for safety during construction until final completion and acceptance of the project by FWS.
This checklist serves as an assurance tool/guide in assessing safety program preparations of the contractor, and is not all-inclusive. As tasks change and new risks and hazards are introduced, you may need to address additional safeguards and corrective measures.
The contractor and subcontractor(s) must comply with all Occupational Safety and Health Administration (OSHA) regulations applicable to the construction project, including requirements set forth w ithin solicitation provisions and contract clauses (e.g., FAR 52.236-13 “Accident Prevention” with Alternate I and Special Provisions). It is the responsibility of the contractor/subcontractor(s) to adhere to regulations found at 29 CFR 1910, 1926, and 1928. (See page 5 for Table of Contents of OSHA Construction Safety Standards.) Each contractor/subcontractor must initiate and maintain an effective safety program that provides adequate systematic policies, procedures, and practices to protect their employees from, and allow them to recognize, job-related safety and health hazards. The program must include provisions for the systematic identification, evaluation, and prevention/control of general work s ite hazards, specific job hazards, and potential hazards that may arise from foreseeable conditions, as well as providing a competent person to conduct frequent and regular inspections. The contractor must instruct each employee to recognize and avoid unsafe conditions and the regulations applicable to the work environm ent.
The contractor will address the following items prior to and/or during the Preconstruction Conference (the Contracting
Officer/Contracting Officer’s Representative will record these items):
1.
FAR 52.236-13, Accident Prevention, Alternate I and applicable safety provisions?
The contractor has read and understands his/her re spo nsibilities for compliance with contractual safety language -
NO ___YES ___
2. Has contractor prepared a Safety Plan that analyzes anticipated hazards of the project and indicates how the hazards will be controlled?
use, scaffolding, excavat
Contractor must identify specific procedures for controlling hazardous operations such as crane
NO ___ion/trenching, hot work/welding, etc,. ES ___ Y N/A
FWS Form 3-2199 05/03 Page 1 of 5
3. How will contractor/subcontractor address the four leading hazards of construction work: falls, struck by, caught in/betw nd electr ical?
4. The “Designated Competent Person” (responsible for the pro ject’s safety and health performance) is knowledgeable corrective measures?
in applicable OSHA regulations and capable of identifying existing/predictable hazards, and has the authority to prompt
YES ___ NO ___
5.
haza
Do contractor and subcon tractor em ployees know wha t to do in the event of an em erge ncy (e.g., injury, fire, accident, ESYrdous material spill, etc.) with regard to the following actions? NO
a. Notification of Departm ent, FW S Facility Manager, CO, COR, CI, etc.
b. Means of com munication with contact numbers (e.g., radio, cellular, pager, etc.).
c. Availability of first-aid/medically-trained contractor personnel with appropriate medical supplies.
d. Personnel (including subcontractors) knowledge of location for imm ediate aid (e.g., first-aid, etc.).
e. Evacuation routes, signals, and procedures are provided to all on-site personnel.
f. Safety and health information disseminated to all site personnel (e.g., contractor and subcontractor employees).
6.
(If no, skip to # 7)
a. Location and type of trailer (office or equipment).
b. Telephone hook-up.
c. Electrical hook-up.
d.
W ill a contractor/s ubc ontra ctor tra iler be broug ht on site and its hook-up/p lacem ent coord inated with COR /CI?
e. Propane used for heating?
f. Serve as first-aid station? YES
Vehicle parking arrang em ent (adequate space).
YES ___
___NO ___
NO ___
7. Is contractor aware that he/she must ensure construction area is clearly delineated and posted with appropriate warning signs (e .g., “Hard Hat Area”, “Construction Site – CLOSED”, rea C losed to Public”, etc.), and that instructional signs (e.g., designated parking area, etc.) and flagmen or barriers may be required? Yes No
Housekeeping - Is contractor/subcontractor aware that they must ensure that following acceptable housekeeping
NO
“A
8.
standards are practiced from project’s start to finish?
YES
a. Form/scrap lumber with protruding nails and all other debris shall be kept clear from work areas.
b. Combustible scrap and debris shall be removed at regular/frequent intervals.
c. Materials shall be stored with regard to their fire characteristics with effective fire protection and prevention measures used.
d. An enclosed chute shall be used whenever materials are dropped more than 20 feet to an exterior point of a building.
e. Aisles, exits, and passageways shall be kept clear and in good repair.
9.
Is contractor aware of following Environmental and Personal Controls standards? YES NO
a. Potable water provided.
b. Restroom facilities provided.
c. W ashing facility provided for employees engaged in operations involving harmful substances.
d. Intoxicating beverages, controlled substances, and/or firearms are not permitted under any circumstances on the construction site.
e. All activities in or around water bodies must be in compliance with regulations for worker safety, including personal flotation devices or buoyant work vests, lifelines, ring buoys and guardrails while working over or adjacent to water hazards, and from barges, boats, and/or launches.
FWS Form 3-2199 05/03 Page 2 of 5
10.
a. Confined Space.
b. Scaffolding.
c. Fall Protection.
d. Hazard Comm unication.
e. Lockout/Tagout.
f. Respiratory Protection.
g. First Aid.
Is contractor/subcontactor aware that following employee training considerations may need to be addressed?
YES NO
11. Contractor/subcontractor is responsible for requiring the wearing of appropriate personal protective equipment in all operations where there is an exposure to hazardous conditions or where the need is indicated for using such equipment to reduce the hazard to their employee(s). The contractor/subcontractor is also responsible for ensuring equipment may include the following: Discussed with contractor?
that personnel using protective equipment shall be trained and medically qualified to do so. Such personal protective
a. Eye and face protection (safety goggles, safety glasses, welding goggles, face shields, etc.).
b. Protective footwear (safety shoes, boots).
c. Protective gloves (leather, rubber, insulated).
d. Respirators (dust, half-face, full-face, etc.).
e. Hearing protection (ear plugs, muffs, etc.).
f. Coast Guard-approved PFD/buoyant vest.
g. Fall protection equipm ent.
12. Tools (hand, electric, pneumatic) Standards: Discussed with contractor?
a. Hand tools, power tools, and jacks are maintained in safe operating condition and used only for the purpose for which they were designed.
b. Electric power-operated tools must be either approved double-insulated, or be properly grounded (see Item
#13 “Electrical” for additional considerations).
13. Electrical Standards:
a. Ground Fault Circuit Interrupters (GFCIs) or an assured equipment-grounding conductor program must be used to protect employees from ground-fault hazards.
b. Electrical cords/insulation must be in good condition (not frayed or damaged).
c. All ground plugs must be on electrical cords, if so designed by the manufacturer.
d. W orkspace, walkways, and similar locations shall be kept clear of electrical cords.
e.
f.
All electrical extension cords must be of the three-wire type.
Contractor/subcontractor must determine need and implem ent an appropriate Lock-out/Tag-out program.
14. W ill motor vehicles, cranes, and/or heavy equipment be used? YES NO __ (If no, skip to #15)
a. Crane and derrick use must comply with applicable standards.
b. Rollover protection as required.
c. Back-up alarms or observer signals as required.
d. No crawler type vehicles are allowed on an improved road.
e. All utilities must be located prior to excavating soil.
15. Excavating and Trenching work? YES ___ NO ___ (If no, skip to #16)
a. All excavating/trenching must be in accordance with applicable safety standards.
b. All utilities must be located prior to excavating.
FWS Form 3-2199 05/03 Page 3 of 5
16. Elevated W ork? YES ___ NO ___ (If no, skip to #17) a.
Ladders and their use must conform to standards.
b. Aerial lift usage must meet applicable requirements.
c. Fall protection needs must be assessed per standards.
d. Scaffold work must conform to standards.
e. Stair design, construction, and use must meet applicable requirements.
f. Toeboards, when used to protect workers from falling objects, must be erected along the edge of the overhead walking/working surface.
g. Safety net use must comply with standards.
h. Railing must conform to standards.
17.
Contractor is aware of and understands the need to incorporate app licable requirem ents for concrete and m asonry
YES ___ NO ___ N/A ___
18. Contractor is aware of and understands the need to incorporate welding and cutting operations that com ply with etc.).
applicable safe ty requirem ents (e.g., compressed gas cylinders are protected from vehicle traffic, valve caps secured, 19.
paint
Contrac tor is aw are o f and understands the need to m anage hazard ous m aterials/waste appro priately (e.g., YES N/A
N/A ___ s, solvents, fuels, etc.) including the following: NO ___
a. Use and storage of flammable/combustible liquids.
b. Aboveground fuel storage tanks properly managed/contained.
c. Com pressed gases and cylinders managed correctly (e.g., secured and protected from damage, etc.).
d. Procedures for managing use, storage, and disposal of hazardous materials properly established.
e. Excess/waste product(s) and containers properly disposed of per environmental regulations.
f. Hazards of product use and the need for protective measures (e .g., personal protective equipment, etc.)
conveyed to employees.
g. Asbestos work conform s to applicable standards.
h. Exposure to toxic gases, vapors, fum es, dusts , and m ists managed correctly.
i. Lead, laser, and any other hazardous components managed per the applicable standard.
j. Contract employees must conduct hazardous waste operations work within the parameters…