A06_Specifications_1.pdf
PDF 6 MB Posted
- Attached to
- BLM-CO TRFO CANM LAKEVIEW INTERN HOUSING Federal contract opportunity
- Solicitation number
- 140L1725R0003
About this file
This document is a comprehensive set of project specifications for the Bureau of Land Management's Canyons of the Ancients Lake House Renovation project located in Dolores, Colorado. The project involves renovating a 2,230 sq.ft. single-family residential structure into a code-compliant congregate living residential facility, with key improvements including converting an unconditioned garage into two new bedrooms, a bathroom, laundry, and mechanical/electrical room. Additional scope encompasses installing a fire sprinkler system, fire alarm and detection system, reconfiguring the kitchen, applying new exterior cladding, and making various cosmetic improvements.
The solicitation is anticipated to be set aside for an Indian Small Business Economic Enterprise (ISBEE), with a NAICS code of 236118 (Residential Remodelers) and a size standard of $45 million. The estimated price range is between $500,000 and $1,000,000, with a projected solicitation release date of August 2nd, 2025. The period of performance will be 270 days after the Notice to Proceed, and the project is located at 27549 CO-184, Dolores, Colorado 81323. A pre-bid site tour will be announced when the Request for Proposals is released, and interested parties are advised to monitor SAM.gov for updates.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BID_SCHEDULE_1.pdf | ||
| A06_Drawings_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CANYONS OF THE ANCIENTS NATIONAL MONUMENT
INTERN LAKE HOUSE RENOVATION
DOLORES, COLORADO
BUREAU OF LAND MANAGEMENT
PROJECT SPECIFICATIONS
U.S. DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
DOLORES, COLORADO
17 January 2025
TABLE OF CONTENTS CANM LAKE HOUSE RENOVATION
TABLE OF CONTENTS
CONSTRUCTION DOCUMENTS
The following listed documents comprise the Table of Contents for the Bureau of Land Management Canyons of the Ancients Lake House Renovation Project located in Dolores, Colorado.
COVER
TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
000101 PROJECT TITLE PAGE
000115 LIST OF DRAWING SHEETS
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY
013100 PROJECT MANAGEMENT AND COORDINATION
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013233 PHOTOGRAPHIC DOCUMENTATION
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
015000 TEMPORARY FACILITIES AND CONTROLS
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
DIVISION 02 – EXISTING CONDITIONS
024119 SELECTIVE DEMOLITION
028210 ASBESTOS REMEDIATION
DIVISION 03 – CONCRETE
033000 CAST-IN-PLACE CONCRETE
DIVISION 04 – MASONRY
NOT USED
DIVISION 05 – METALS
NOT USED
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061000 ROUGH CARPENTRY
061600 SHEATHING
062023 INTERIOR FINISH CARPENTRY
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
072100 THERMAL INSULATION
072500 WEATHER BARRIERS
072600 VAPOR BARRIERS
074646 FIBER-CEMENT SIDING
079200 JOINT SEALANTS
DIVISION 08 – OPENINGS
081416 FLUSH WOOD DOORS
081613 FIBERGLASS DOORS
083113 ACCESS DOORS
085313 VINYL WINDOWS
087100 DOOR HARDWARE
DIVISION 9 – FINISHES
092900 GYPSUM BOARD
093013 CERAMIC TILING
096513 RESILIENT BASE AND ACCESSORIES
096700 LAMINATE FLOORING
099113 EXTERIOR PAINTING
099123 INTERIOR PAINTING
DIVISION 10 – SPECIALTIES
102800 TOILET, BATH, AND LAUNDRY ACCESSORIES
DIVISION 11 – EQUIPMENT
111300 ATTIC LADDERS
113013 RESIDENTIAL APPLIANCES
DIVISION 12 – FURNISHINGS
123530 RESIDENTIAL CASEWORK
DIVISION 21 – FIRE SUPPRESSION
211000 WATER-BASED FIRE-SUPPRESSION SYSTEMS
DIVISION 22 – PLUMBING
220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING
220529 HANGERS AND SUPPORT FOR PLUMBING PIPING AND EQUIPMENT
220548 VIBRATION AND SEISMIC CONTROLS FOR PLUMBING PIPING AND
EQUIPMENT
220700 PLUMBING INSULATION
221116 DOMESTIC WATER PIPING
221119 DOMESTIC WATER PIPING SPECIALTIES
221316 SANITARY WASTE AND VENT PIPING
221319 SANITARY WASTE PIPING SPECIALTIES
223400 FUEL-FIRED DOMESTIC WATER HEATERS
224000 PLUMBING FIXTURES
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
230517 SLEEVE AND SLEEVE SEALS FOR HVAC PIPING
230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING & EQUIPMENT
230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC
230700 HVAC INSULATION
233100 HVAC DUCTS AND CASINGS
233713 DIFFUSERS, REGISTERS, AND GRILLES
237333.16 INDOOR, INDIRECT, GAS-FIRED HEATING AND VENTILATING UNITS
DIVISION 26 – ELECTRICAL
260500 ELECTRICAL MATERIALS AND METHODS
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
260923 LIGHTING CONTROL DEVICES
262416 PANELBOARDS
262713 ELECTRICITY METERING
262726 WIRING DEVICES
264313 SURGE PROTECTION FOR LOW-VOLTAGE ELECTRICAL POWER CIRCUITS
265000 LIGHTING
284621 CONVENTIONAL FIRE ALARM SYSTEMS
DIVISION 30 - EARTHWORK
312113 RADON MITIGATION
333010 SEPTIC SYSTEM
333020 RV UTILITIES AND SITE WORK
END OF SECTION
BLM GAOA CANM Lake House
PROJECT TITLE PAGE 000101 - 1
SECTION 000101 - PROJECT TITLE PAGE
PART 1 - GENERAL
1.1 PROJECT MANUAL
A. VOLUME Review Set - Not for Construction.
1. CANM Lakeview Intern Housing Renovation.
2. Bureau of Land Management.
3. Dolores, Colorado.
4. BLM National Operations Center.
5. Denver Federal Center, Building 85.
6. Denver, Colorado 80225-0047.
7. Phone: 303-236-8857.
8. Website: https://www.blm.gov/services/national-operations-center.
PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)
END OF SECTION 000101
BLM GAOA
CANM Lake House
LIST OF DRAWING SHEETS 000115 - 1
DOCUMENT 000115 - LIST OF DRAWING SHEETS
1.1 LIST OF DRAWINGS
A. List of Drawings: Drawings that will be enumerated in the Owner/Contractor Agreement as part of the Contract Documents are the following Drawings and other drawings of type indicated, as modified by subsequent Addenda and Modifications:
1. G-000 COVERSHEET
2. G-001 CODE INFORMATION
3. C-01 SITE PLAN - EXISTING
4. C-02 SITE PLAN - PROPOSED
5. C-03 RV PADS
6. A-001 LEGENDS & ABBREVIATIONS
7. A-002 TYPICAL DETAILS
8. AR-100 EXISTING FIRST FLOOR PLAN
9. AR-101 EXISTING ROOF PLAN
10. AR-201 EXISTING ELEVATIONS
11. AR-301 EXISTING SECTIONS
12. AD-101 DEMOLITION PLAN
13. A-100 FOUNDATION PLAN
14. A-101 FLOOR PLAN
15. A-102 REFLECTED CEILING PLAN
16. A-103 ENLARGED FLOOR PLAN - NEW BEDROOMS
17. A-104 ENLARGED FLOOR PLAN & INTERIOR ELEVATIONS
18. A-105 ROOF PLAN
19. A-106 FINISH PLAN
20. A-201 ELEVATIONS
21. A-301 SECTIONS
22. A-302 SECTIONS
23. A-601 DETAILS
24. A-602 DETAILS
25. A-801 DOOR & WINDOW SCHEDULES
26. A-802 TYPICAL WINDOW DETAILS
27. A-803 TYPICAL DOOR DETAILS
28. S-101 STRUCTURAL PLANS
29. S-501 STRUCTURAL SECTIONS & DETAILS
30. S-502 STRUCTURAL SECTIONS & ELEVATIONS
31. S-503 STRUCTURAL SECTIONS
32. M-001 LEGENDS, ABBREVIATIONS & GEN. NOTES
33. M-201 FLOOR PLAN - DUCTWORK
34. M-202 FLOOR PLAN - PIPING
35. M-501 DETAILS
36. M-601 MECHANICAL SCHEDULES
37. E-001 PNL SCHEDULE, ONE LINE, LEGENDS & GEN. NOTES
38. E-101 POWER PLAN
BLM GAOA
CANM Lake House
LIST OF DRAWING SHEETS 000115 - 2
39. E-102 LIGHTING PLAN
40. FA-101 FIRE DETECTION PLAN
41. P-001 LEGENDS, ABBREVIATIONS & GEN. NOTES
42. P-201 CRAWLSPACE – DOMESTIC WATER
43. P-202 CRAWLSPACE – SANITARY
44. P-203 FLOOR PLAN – DOMESTIC WATER
45. P-204 FLOOR PLAN – SANITARY
46. P-601 PLUMBING SCHEDULES & DETAILS
47. P-901 ISOMETRIC
PART 2 - PRODUCTS (Not Used)
END OF DOCUMENT 000115
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Contractor's use of site and premises.
4. Work restrictions.
5. Specification and Drawing conventions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.2 PROJECT INFORMATION
A. Project Identification: Canyons of the Ancients Lake House Renovation.
1. Project Location: 27549 CO-184, Dolores, Colorado 81323.
B. Owner: Bureau of Land Management.
1. Contracting Officer’s Representative: Peter Russell, PE, BLM Colorado State Office.
C. Architect: BLM National Operations Center, Section 671.
1. Architect's Representative: Jacob Laureska, RA, National Operations Center Architect.
D. Architect's Consultants: Architect has retained the following design professionals, who have prepared designated portions of the Contract Documents:
1. Structural Engineering: BLM National Operations Center, Section 671.
a. BLM Structural Representative: Richard Zaragoza, PE, National Operations Center
Structural Engineer.
2. Mechanical & Plumbing Engineering: BLM National Operations Center, Section 671.
a. BLM Mechanical & Plumbing Representative: Joshua Burris, PE, National
Operations Center Mechanical Engineer.
3. Electrical Engineering: BLM National Operations Center, Section 671.
SUMMARY 011000 - 2
a. BLM Electrical Representative: Don Lira, National Operations Center.
4. Civil Engineering: BLM Colorado State Office.
a. BLM Civil Representative: Peter Russell, PE, BLM Colorado State Office.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:
1. Renovation of an existing 2,230 sq.ft., Type VB single-family residential structure to a code-compliant congregate living residential facility. Includes the conversion of the existing unconditioned garage space to new conditioned space, which will house two new bedrooms, a bathroom, laundry, and mechanical/electrical room. Other improvements to the building include a fire sprinkler system, fire alarm and detection system, renovated/re-configured kitchen, new exterior cladding, and other various cosmetic improvements. and other work indicated in the Contract Documents.
1.4 CONTRACTOR'S USE OF SITE AND PREMISES
A. Restricted Use of Site: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Limits on Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits on Use of Site: Confine construction operations to areas immediately surrounding the existing dwelling. Contractor shall not have access to the Canyons of the Ancients
(CANM) visitor center and office facilities to the north of the project site.
2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
D. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
SUMMARY 011000 - 3
1.5 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work to between 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.
1. Hours for Utility Shutdowns: Coordinate with Owner.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
D. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
E. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances on Project site is not permitted.
F. Employee Identification: Provide identification tags for Contractor personnel working on
Project site. Require personnel to use identification tags at all times.
G. Employee Screening: Comply with Owner's requirements for background screening of
Contractor personnel working on Project site.
1. Maintain list of approved screened personnel with Owner's representative.
1.6 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless
SUMMARY 011000 - 4
otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. On-Site Work Hours: Limit work to between 7:00 a.m. to 5:00 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.
C. Work shall not occur on Federal Holidays.
D. Work shall not begin until after September 1, 2025.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 011000
PROJECT MANAGEMENT AND
COORDINATION
013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Web-based Project management software package.
6. Project meetings.
B. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.
2. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. RFI: Request for Information. Request from Contractor seeking information required by or clarifications of the Contract Documents.
B. COR: Contracting Officer’s Representative.
1.3 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
013100 - 2
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.4 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Government will return without response those RFIs submitted to the Government by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Owner name.
3. Owner's Project number.
4. Date.
5. Name of Contractor.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Schedule of Values.
13. Contractor's signature.
14. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Form bound in Project Manual.
1. Attachments shall be electronic files in PDF format.
D. COR’s Action: The COR will review each RFI, determine action required, and respond. Allow 14 calendar days for the COR’s response for each RFI. RFIs received by the COR after 1:00
013100 - 3 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of COR's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. COR's action may include a request for additional information, in which case the COR's time for response will date from time of receipt of additional information.
3. COR's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal.
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify COR in writing within 5 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly with not less than the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of Architect.
4. RFI number, including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date COR's response was received.
8. Identification of related Minor Change in the Work, Construction Change Directive, and
Proposal Request, as appropriate.
9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.
F. On receipt of COR's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify COR within seven days if Contractor disagrees with response.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013100
CONSTRUCTION PROGRESS
DOCUMENTATION
013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
1.1 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Startup construction schedule.
2. Contractor's Construction Schedule.
3. Construction schedule updating reports.
4. Daily construction reports.
5. Material location reports.
6. Site condition reports.
7. Unusual event reports.
B. Related Requirements:
1. Section 014000 "Quality Requirements" for schedule of tests and inspections.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine the critical path of Project and when activities can be performed.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Event: The starting or ending point of an activity.
F. Float: The measure of leeway in starting and completing an activity.
1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet
013200 - 2 schedule milestones and Contract completion date.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
G. Resource Loading: The allocation of labor and equipment necessary for completing an activity as scheduled.
1.3 SUBMITTALS
A. Government approval is required for submittals with a “G” designation; submit the following in accordance with Section 01 33 00 “Submittal Procedures”:
1. SD-02 Contractor’s Submittals
a. Format for Submittals: Submit required submittals in the following format:
1) Working electronic copy of schedule file.
2) PDF file.
b. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
1) Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.
c. Construction Schedule Updating Reports: Submit with Applications for Payment.
d. Daily Construction Reports: Submit at weekly intervals.
e. Material Location Reports: Submit at weekly intervals.
f. Site Condition Reports: Submit at time of discovery of differing conditions.
g. Unusual Event Reports: Submit at time of unusual event.
1.4 QUALITY ASSURANCE
A. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's Construction Schedule, including, but not limited to, the following:
1. Review software limitations and content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Review schedule for work of Owner's separate contracts.
4. Review submittal requirements and procedures.
5. Review time required for review of submittals and resubmittals.
6. Review requirements for tests and inspections by independent testing and inspecting agencies.
7. Review time required for Project closeout and Owner startup procedures.
8. Review and finalize list of construction activities to be included in schedule.
9. Review procedures for updating schedule.
1.5 CONTRACTOR'S CONSTRUCTION SCHEDULE
A. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.
013200 - 3
1. Contract completion date to not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
B. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Products Ordered in Advance: Include a separate activity for each product.
2. Work Restrictions: Show the effect of the following items on the schedule:
a. Uninterruptible services.
b. Use-of-premises restrictions.
c. Seasonal variations.
d. Environmental control.
C. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule three (3) business days before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate Final Completion percentage for each activity.
D. Distribution: Distribute copies of approved schedule to COR, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility at each scheduled progress meeting.
1. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
1.6 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. List of subcontractors at Project site.
2. Approximate count of personnel at Project site.
3. Material deliveries.
4. High and low temperatures and general weather conditions, including presence of rain or snow.
5. Testing and inspection.
6. Accidents.
7. Meetings and significant decisions.
8. Unusual events.
9. Stoppages, delays, shortages, and losses.
10. Emergency procedures.
11. Orders and requests of authorities having jurisdiction.
013200 - 4
12. Change Orders received and implemented.
13. Services connected and disconnected.
14. Equipment or system tests and startups.
15. Substantial Completions authorized.
B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
C. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise COR in advance when these events are known or predictable.
1. Submit unusual event reports directly to Owner within one day(s) of an occurrence.
Distribute copies of report to parties affected by the occurrence.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013200
PHOTOGRAPHIC DOCUMENTATION 013233 - 1
SECTION 013233 - PHOTOGRAPHIC DOCUMENTATION
1.1 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Preconstruction photographs.
2. Concealed Work photographs.
3. Periodic construction photographs.
4. Final Completion construction photographs.
5. Preconstruction video recordings.
B. Related Requirements:
1. Section 017700 "Closeout Procedures" for submitting photographic documentation as Project Record Documents at Project closeout.
2. Section 024119 "Selective Demolition" for photographic documentation before selective demolition operations commence.
1.2 SUBMITTALS
A. Government approval is required for submittals with a “G” designation; submit the following in accordance with Section 01 33 00 “Submittal Procedures”:
1. SD-02 Contractor’s Submittals
a. Digital Photographs: Submit image files within three days of taking photographs.
1) Submit photos by uploading to web-based Project management software site. Include copy of key plan indicating each photograph's location and direction.
2) Identification: Provide the following information with each image description in web-based Project management software site:
a) Name of Project.
b) Date photograph was taken.
c) Description of location, vantage point, and direction.
1.3 CONSTRUCTION PHOTOGRAPHS
A. General: Take photographs with maximum depth of field and in focus.
B. Concealed Work Photographs: Before proceeding with installing work that will conceal other work, take photographs sufficient in number, with annotated descriptions, to record nature and location of concealed Work, including, but not limited to, the following:
1. Underground utilities, inc. bedding, thrust blocks & drain stone.
2. Underslab services.
PHOTOGRAPHIC DOCUMENTATION 013233 - 2
3. Piping.
4. Electrical conduit.
5. Waterproofing and weather-resistant barriers.
6. Work within framed walls..
C. Periodic Construction Photographs: Take 20 photographs weekly. Select vantage points to show status of construction and progress since last photographs were taken.
D. Final Completion Construction Photographs: Take 100 photographs after date of Substantial Completion for submission as Project Record Documents. Architect will inform photographer of desired vantage points.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013233
SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 – SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUBMITTALS
A. Government approval is required for submittals with a “G” designation; submittals not having a
“G” designation are for information only.
1.2 INFORMATION ONLY SUBMITTALS
A. Normally submittals for information only will not be returned. Approval of the Contracting
Officer’s Representative is not required on information only submittals. The Government reserves the right to required the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work, and does not relieve the Contractor of the requirement to furnish samples for testing by the
Government.
1.3 GOVERNMENT APPROVING AUTHORITY
A. The Contracting Officer’s Representative will:
1. Note the date on which the submittal was received.
2. Review submittals for approval within 10 working days of receipt.
3. Identify returned submittals with one of the actions defined in paragraph REVIEW
NOTATIONS and with markings appropriate for action indicated.
B. Upon completion of review of submittals requiring Government approval, one copy of the submittal will be retained by the Contracting Officer’s Representative and one copy of the submittal will be returned to the Contractor.
C. Review Notations
1. Submittals will be returned to the Contractor with the following notations:
a. Submittals marked “approved” or “accepted” authorize the Contractor to proceed with the work covered.
b. Submittals marked “approved as noted” or “approved, except as noted, resubmittal not required,” authorize the Contractor to proceed with the work covered provided the Contractor takes no exception to the corrections.
c. Submittals marked “not approved” or “disapproved,” or “revise and resubmit,” indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked “not reviewed” will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked “not
SUBMITTAL PROCEDURES 013300 - 2
reviewed” will be returned with an explanation of the reason it is not reviewed.
Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked “receipt acknowledged” indicate that submittals have been received by the Government. This applies only to “information-only submittals” as previously defined.
D. DISAPPROVED SUBMITTALS
1. Make corrections required by the Contracting Officer’s Representative. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled
CHANGES, is to be given to the Contracting Officer.
2. If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
E. APPROVED SUBMITTALS
1. The Contracting Officer’s approval of submittals is not to be construed as a complete check.
2. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible fore.
1.4 SUBMITTAL REGISTER
A. The contractor shall maintain a current register of all active and closed project submittals. The register shall be available on-site at all times and available to the COR upon request.
B. The following list provides an overview of the required project submittals. Refer to the submittals’ respective specification sections for more information.
SUBMITTAL REGISTER
SD-01 Directives
Not Used
SD-02 Contractor’s Submittals
Section Submittal
013200 Contractor’s Construction Schedule
013200 Construction Schedule Updating Reports
013200 Daily Construction Reports
013200 Material Location Reports
013200 Site Condition Reports
013200 Unusual Event Reports
013233 Digital Photographs
015000 Site Utilization Plan
015000 Implementation and Termination Schedule
017700 Contractor’s List of Incomplete Items
SUBMITTAL PROCEDURES 013300 - 3
017700 Certified List of Incomplete Items
017700 Certificate of Release
017700 Certificate of Insurance
028210 Asbestos Remediation Work Plan
284621 Fire alarm system installer qualification data
SD-03 Product Data
028210 Encapsulation coating material
033000 Concrete mix designs
061000 Rough carpentry products
061600 Sheathing products
062023 Interior finish carpentry
072100 Thermal insulation
072500 Weather barriers
072600 Vapor barriers
074646 Fiber-cement siding
079200 Joint sealants
081416 Flush wood doors
081616 Fiberglass doors
083113 Access door
085313 Vinyl windows
087100 Door hardware and schedule
092900 Gypsum board
093013 Ceramic tiling
096513 Resilient base and accessories
099113 Exterior paint
099123 Interior paint
102800 Toilet, bath, and laundry accessories
111300 Attic ladders
113100 Residential appliances
211000 Fire suppression valves, sprinklers, specialties & alarms
220700 Plumbing insulation
221116 Domestic water piping
221316 Sanitary waste and vent piping
223400 Fuel-fired domestic water heaters
224000 Plumbing fixtures
230529 Hangers and supports for HVAC piping and equipment
230700 HVAC insulation
232300 Refrigerant piping
233100 HVAC ducts and casings
233713 Diffusers, registers, and grilles
237333.16 Indoor, indirect, gas-fired heating and ventilating units
260500 Electrical materials
260519 Low-voltage electrical power conductors and cables
260533 Raceways and boxes for electrical systems
260923 Lighting control devices
262416 Panelboards
262713 Electricity metering
262726 Wiring devices
SUBMITTAL PROCEDURES 013300 - 4
265000 Lighting
284621 Fire alarm system
312113 Radon mitigation system
333020 Electrical pedestal
333020 Freezeless hydrant
333020 Curb stop and waste valve
333020 Aggregate base course
SD-04 Samples
062023 Trim and molding profiles
074646 Fiber-cement siding
092900 Gypsum board texture mock-up
093013 Ceramic tiling and grout samples
099113 Exterior paint
099123 Interior paint
238126 Split-system air conditioners
SD-05 Design Data
061000 Rough carpentry evaluation reports
061600 Sheathing evaluation reports
072100 Thermal insulation technical information and data
085313 Vinyl window technical information
111300 Attic ladder weight information
265000 Lighting data
284621 Fire alarm system data and reports
SD-06 Test Reports
033000 Concrete strength testing
033000.1 Concrete test results
072600 Vapor barrier test reports
211000 Fire suppression test reports
230593 TAB reports
260923 Lighting control devices field quality-control reports
SD-07 Shop Drawings and Samples
102800 Toilet, bath and laundry accessories
211000 Fire suppression system drawings and calculations
238126 Split-system air conditioner
260923 Lighting control devices interconnection diagrams
262713 Electricity metering
312113 Radon mitigation system
SD-08 Certificates
SUBMITTAL PROCEDURES 013300 - 5
074646 Fiber-cement siding warranty
081616 Fiberglass door warranty
085313 Vinyl window warranty
113100 Residential appliance warranties
223400 Gas water heater
260923 Lighting control devices warranties
284621 Fire alarm system
333010 Septic system OWTS permit
SD-09 Manufacturer Instructions
Not Used
SD-10 Maintenance Data
260500 Electrical materials
265000 Lighting O&M data
284621 Fire alarm system O&M data
SD-11 Operation and Maintenance Manuals (O&M)
017823 Final Manual Submittal
223400 Fuel-fired domestic water heater
238126 Split-system air conditioner
PART 2 - PRODUCTS (Not Used)
END OF SECTION 013300
QUALITY REQUIREMENTS 014000 - 1
SECTION 014000 - QUALITY REQUIREMENTS
1.1 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's other quality -assurance and quality-control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-assurance and quality-control services required by the Government, authorities having jurisdiction are not limited by provisions of this Section.
1.2 DEFINITIONS
A. Experienced: When used with an entity or individual, "experienced," unless otherwise further described, means having successfully completed a minimum of three previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
B. Field Quality-Control Tests and Inspections: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, subcontractor, or sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations.
1. Use of trade-specific terminology in referring to a Work result does not require that certain construction activities specified apply exclusively to specific trade(s).
D. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials are incorporated into the Work, to verify performance or compliance with specified criteria. Unless otherwise indicated, copies of reports of tests or inspections performed for other than the Project do not meet this definition.
E. Product Tests: Tests and inspections that are performed by a nationally recognized testing laboratory (NRTL) in accordance with 29 CFR 1910.7, by a testing agency accredited in accordance with NIST's National Voluntary Laboratory Accreditation Program (NVLAP), or by
QUALITY REQUIREMENTS 014000 - 2
a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with specified requirements.
F. Source Quality-Control Tests and Inspections: Tests and inspections that are performed at the source (e.g., plant, mill, factory, or shop).
G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. The term "testing laboratory" has the same meaning as the term "testing agency."
H. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work, to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
I. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work, to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Contractor's quality-control services do not include contract administration activities performed by the Government.
1.3 CONFLICTING REQUIREMENTS
A. Conflicting Standards and Other Requirements: If compliance with two or more standards or requirements is specified and the standards or requirements establish different or conflicting requirements for minimum quantities or quality levels, inform the Architect regarding the conflict and obtain clarification prior to proceeding with the Work. Refer conflicting requirements that are different, but apparently equal, to Contracting Officer’s Representative (COR) for clarification before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified is the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to COR for a decision before proceeding.
1.4 ACTION SUBMITTALS
A. Mockup Shop Drawings:
1. Include plans, sections, elevations, and details, indicating materials and size of mockup construction.
2. Indicate manufacturer and model number of individual components.
3. Provide axonometric drawings for conditions difficult to illustrate in two dimensions.
1.5 INFORMATIONAL SUBMITTALS
A. Contractor's Quality-Control Plan: For quality-assurance and quality-control activities and responsibilities.
B. Qualification Data: For Contractor's quality-control personnel.
QUALITY REQUIREMENTS 014000 - 3
C. Testing Agency Qualifications: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
D. Reports: Prepare and submit certified written reports and documents as specified.
E. Permits, Licenses, and Certificates: For Owner's record, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.
1.6 CONTRACTOR'S QUALITY-CONTROL PLAN
A. Quality-Control Plan, General: Submit quality-control plan within 10 days of Notice to Proceed, and not less than five days prior to preconstruction conference. Submit in format acceptable to the Government. Identify personnel, procedures, controls, instructions, tests, records, and forms to be used to carry out Contractor's quality-assurance and quality-control responsibilities and to coordinate Owner's quality-assurance and quality-control activities. Coordinate with Contractor's Construction Schedule.
B. Quality-Control Personnel Qualifications: Engage qualified personnel trained and experienced in managing and executing quality-assurance and quality-control procedures similar in nature and extent to those required for Project.
1. Project quality-control manager may also serve as Project superintendent.
C. Submittal Procedure: Describe procedures for ensuring compliance with requirements through review and management of submittal process. Indicate qualifications of personnel responsible for submittal review.
D. Testing and Inspection: In quality-control plan, include a comprehensive schedule of Work requiring testing or inspection, including the following:
1. Contractor-performed tests and inspections, including subcontractor-performed tests and inspections. Include required tests and inspections and Contractor-elected tests and inspections. Distinguish source quality-control tests and inspections from field quality-control tests and inspections.
2. Special inspections required by authorities having jurisdiction and indicated on the Statement of Special Inspections.
3. Owner-performed tests and inspections indicated in the Contract Documents.
E. Continuous Inspection of Workmanship: Describe process for continuous inspection during construction to identify and correct deficiencies in workmanship in addition to testing and inspection specified. Indicate types of corrective actions to be required to bring the Work into compliance with standards of workmanship established by Contract requirements and approved mockups.
F. Monitoring and Documentation: Maintain testing and inspection reports, including log of approved and rejected results. Include Work Architect has indicated as nonconforming or defective. Indicate corrective actions taken to bring nonconforming Work into compliance with
QUALITY REQUIREMENTS 014000 - 4
requirements. Comply with requirements of authorities having jurisdiction.
1.7 REPORTS AND DOCUMENTS
A. Test and Inspection Reports: Prepare and submit certified written reports specified in other
Sections. Include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, telephone number, and email address of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample-taking and testing and inspection.
11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
B. Manufacturer's Technical Representative's Field Reports: Prepare written information documenting manufacturer's technical representative's tests and inspections specified in other Sections. Include the following:
1. Name, address, telephone number, and email address of technical representative making report.
2. Statement on condition of substrates and their acceptability for installation of product.
3. Statement that products at Project site comply with requirements.
4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
5. Results of operational and other tests and a statement of whether observed performance complies with requirements.
6. Statement of whether conditions, products, and installation will affect warranty.
7. Other required items indicated in individual Specification Sections.
1.8 QUALITY ASSURANCE
A. Qualifications paragraphs in this article establish the minimum qualification levels required;
individual Specification Sections specify additional requirements.
B. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units. As applicable, procure products from manufacturers able to meet qualification requirements, warranty requirements, and technical or factory-authorized service representative requirements.
QUALITY REQUIREMENTS 014000 - 5
C. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
D. Installer Qualifications: A firm or individual experienced in installing, erecting, applying, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that is similar in material, design, and extent to those indicated for this Project.
F. Specialists: Certain Specification Sections require that specific construction activities be performed by entities who are recognized experts in those operations. Specialists will satisfy qualification requirements indicated and engage in the activities indicated.
1. Requirements of authorities having jurisdiction supersede requirements for specialists.
G. Testing and Inspecting Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspection indicated, as documented in accordance with ASTM E329, and with additional qualifications specified in individual Sections; and, where required by authorities having jurisdiction, that is acceptable to authorities.
H. Manufacturer's Technical Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to observe and inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is…