This document provides detailed specifications for a herbicide application contract. The contract involves treating approximately 2392 acres located 50 miles northwest of Elko, Nevada for various noxious weed species including hoary cress, Scotch thistle, and spotted knapweed. The anticipated treatment window is May 8 to June 30. The contractor must supply all necessary equipment, chemicals, and personnel to complete aerial or ground application of an aquatic or terrestrial herbicide mixture between those dates while following all environmental protection requirements. The Bureau of Land Management Nevada Region is soliciting bids for contract number 140L3923Q0027 to conduct this Tuscarora Herbicide Weeds Treatment project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A04_SOW_General_Herbicides.doc | DOC document | |
| A06_BLM_Herbicide.pdf | ||
| A06_Map_2.pdf | ||
| A06_PAR_Example.pdf | ||
| A06_BLM_Adjuvants.pdf | ||
| B03_Wage_Determination.pdf | ||
| A06_Map_1.pdf | ||
| Sol_140L3923Q0027.pdf | ||
| A06_PAR_Template.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DETAILED SPECIFICATIONS
HERBICIDE APPLICATION
2023 Tuscarora Herbicide Weed Treatment
1. Target Species: Hoary Cress, Scotch thistle, and spotted knapweed Additional noxious weed species found within the designated contract boundary, and susceptible to chemical intended for use, will also be treated.
2. Treatment Area: 2392 acres with approximately 182 acres of streams/have the potential for water present and will require the use of both aquatic herbicide and adjuvant. Treatment areas vary in the amount of noxious weeds that are within the polygon. Actual weed treatments will be less than that of the treatment area itself. Treatments along roadsides have a 60-foot width.
3. Location of Work Site: Project area is located approximately 50 miles northwest of Elko, Nevada. Legal description of the treatment area: T40N, R51E and T39N, R51E. See Attached Location Maps.
Access to Work Site: Public or private access roads damaged by the Contractor shall be restored, at the Contractor’s expense, to the same condition they were in at the commencement of work.
4. Approximate Performance Period: Period of performance is estimated and timing of treatments will need to be flexible in order to maximize the effects on target weed species. The anticipated treatment window for this project is May 8 to June 30 and the Contractor must be available during that time period.
5. Requirements of Equipment to be supplied by the Contractor: Sufficient to meet specifications of the contract.
6. Loading Facilities: Use of any loading area on federal or private land, shall be arranged by and at the discretion and risk of the contractor.
7. Work Crew Requirements: Work crew for handling and mixing of chemical and loading equipment shall be furnished by the Contractor.
8. Requirements of Chemical to be supplied by the Contractor: Herbicide, surfactant, and dye shall be used and selected from the attached lists of Approved Herbicide Formulations and Approved Adjuvants for use on BLM land. Colorant/dye must be visible for 3 days after application.
| 9. | Kind of Chemical: Chlorsulfuron + 2,4-D + Surfactant + Dye; Aquatic 2,4-D + Aquatic Surfactant + Dye |
| Contractor must provide a list of chemicals intended for use prior to pre-work conference. |
10. Rate of Application:
· Terrestrial Mix: Chlorsulfuron (Telar XP or equivalent) at 1.0 ounces/acre (0.047 lb AI/acre) + 2,4-D (Alligare 2,4-D or equivalent) at 32 ounces/acre (0.95 lb ae/acre) + surfactant (Rate as specified on product label) + dye
· Aquatic Mix (and spotted knapweed): 2,4-D (Weedar 64 or equivalent) at 64 ounces/acre (1.9 lbs AE/acre) + aquatic surfactant (i.e. Kinetic or equivalent; Rate as specified on product label) + dye
11. Remarks and Other Requirements: Apply the spray solution in properly maintained and calibrated equipment capable of delivering the desired volume. Controlling drift is the responsibility of the Applicator.
Due to the high sage grouse value of the treatment area, mobilization to or from the site, and application of chemical will not occur between 6pm and 9am until after May 15th. In the event a sage grouse is flushed on site the contractor must apply a 0.25 mile buffer around the area where the sage grouse was observed for the duration of the performance schedule. No application will occur within that 0.25 buffer; backpack application only is allowed within the 0.25-0.5 mile buffer around the area where the sage grouse was observed.
If water is present during the time of application, the buffers for non-aquatically formulated herbicides will be maintained at 10 feet for application by handgun and 25 feet for application with boom equipment. Spraying up to the water’s edge (within the buffer) will require use of aquatic herbicide formulation and surfactant.