A06_-_140L1721Q0050_-_Section_012200_1.pdf
PDF 63 KB Posted
- Attached to
- BLM CO UCR GJFO GRAND VALLEY OPEN OHV P3
- Solicitation number
- 140L1721Q0050
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLM CO State Office
5/1/2020 UNIT PRICES
BLM-CO GJFO Grand Valley Open OHV Staging Area Phase III 012200 - 1
SECTION 012200 - UNIT PRICES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
1.3 DEFINITIONS
A. Unit price is a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.
1.4 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
C. Government reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Government’s expense, by a surveyor acceptable to Contractor.
D. List of Unit Prices: A schedule of unit prices is included with the contract package.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012200
File details come from the government source that posted it. Updated .