A04-Transformer-SOW.pdf

PDF 1 MB Posted

Attached to
GATE-REPLACEMENT OF 300 KVA TRANSFORMER Federal contract opportunity
Solicitation number
140P4524Q0042
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document is a Performance Work Statement (PWS) for the replacement of a 300 kVA 4160/120/208 transformer at Fort Wadsworth in the Staten Island Unit of Gateway National Recreation Area. The existing transformer is leaking coolant oil and needs to be replaced to restore uninterrupted electrical service to U.S. Coast Guard housing units. The contractor will be responsible for disconnecting power, removing the existing transformer, providing and installing a new transformer, and disposing of the old unit per environmental regulations. Key requirements include providing safety plans, equipment submittals, a work schedule, and proper personal protective equipment. The work is to be performed during normal business hours Monday through Friday, with weekend work requiring approval. The contract period of performance is July 27, 2024 to January 27, 2025. Final payment will be made upon acceptance of the work by the Contracting Officer's Representative.

View the file

Other files for this federal contract opportunity

Other files attached to GATE-REPLACEMENT OF 300 KVA TRANSFORMER, newest first.
File Type Posted
Sol_140P4524Q0042_Amd_0002.pdf PDF
Transformer-revised_SOW_08_02_2024_0002.pdf PDF
Sol_140P4524Q0042_Amd_0001.pdf PDF
B03-WD_NY_20240003.pdf PDF
Sol_140P4524Q0042.pdf PDF
06-Transformer_Price_Schedule.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Work Statement (PWS) 4160V 208/120 300kVA Step-Down Transformer in Fort Wadsworth in the Staten Island

Unit of Gateway N.R.A.

STATEMENT OF WORK

1.0 Background

2.0 Scope

3.0 Objectives

4.0 Tasks

5.0 Service Requirements

6.0 Security

7.0 Place of Performance

8.0 Period of Performance

9.0 Payment

1.0 Background

Fort Wadsworth has two high voltage main feeds located at Bay Street and New York Avenue and McClean Avenue and Battery Road. The main feeds are supplied by ConEd and energize the high voltage electrical distribution system. The distribution is made of 4160V switches and 4160V, 208/120 step down transformers.

2.0 Scope

The 300kVA 4160/120/208 transformer provided feeding power to two USCG housing buildings on Florida Court is leaking coolant oil. The oil has been contained. GATE requires the transformer be replaced by a licensed electrical contractor. The leaking transformer will be removed from the existing mounting pad and a new transformer will be replaced in kind. This requirement does not require excavation or concrete placement. The service is limited to work in DIV 26, Electrical.

3.0 Objectives

This action is intended to replace the leaking transformer. This will allow for continued, uninterrupted electrical service to the USCG housing units and stop the oil from leaking onto the pad and possibly the soil in the area around the transformer.

4.0 Tasks

1. Contractor shall disconnect power at the switch to the East of the leaking transformer.

2. The Primary and Secondary cables shall be disconnected and made safe.

3. The existing transformer shall be removed from the slab. The existing transformer shall become the property of the contractor. The contractor shall be responsible for disposal of the failed transformer in accordance with Local, State, and Federal Guidelines.

4. The contractor shall provide a 4160V, 120-208 300 kVA transformer, all labor, equipment, and PPE necessary to remove the existing transformer, safely transport, mount, connect, energize, and test the new transformer.

5.0 Service Requirements

6.1 Bid Requirements

1. No official Pre-bid meeting is schedule. If a potential bidder would like to visit the job site, please contact Rafael Hernandez (c) 347-672-3080 or by email at rafael_hernandez@nps.gov.

2. Bid packages shall include an electrical trade license.

3. Bid packages shall include 3 past performance references illustrating relevant experience. Relevant experience is defined as work involving repair, installation, modification of primary and secondary power supply.

4. Bid packages shall include a tentative schedule based on equipment lead times.

6.2 Post Award Division 1 Submittals

1. Safety plan:

i. Safety Plan to include overhead lift procedures for removal and replacement of the transformer.

ii. Safety Plan to include procedure for de-energizing the transformer, proper

PPE for employees working around Primary and Secondary power.

2. Work Schedule

3. Certificates of Insurance

6.3 Materials and Equipment Submittals

1. Transformer specifications

2. Any connection hardware specifications for connection of Primary and Secondary power at the transformer.

3. One-year parts and labor warranty on equipment.

4. 3-year limited warranty on equipment.

6.4 Work Requirements

1. All work shall take place between the hours of 7:00 A.M. and 5:00 P.M., Monday through Friday. Weekend shall only be approved with a written request to the

COR.

2. All employees shall be in proper PPE including high visibility vests when working near vehicle traffic lanes.

3. Contractor shall not be given access to Government Buildings unless accompanied by an NPS employee.

4. The existing transformer shall become the property of the Contractor. The Contractor shall be responsible for following Local, State, and Federal Guidelines when disposing of the transformer.

6.0 Security

1. The Contractor shall not have possession of keys to any buildings or equipment enclosures while performing work.

2. The Contractor shall not have access to any Government Buildings with out an escort from NPS or USCG personnel.

7.0 Place of Performance

Work took place on Fort Wadsworth in the Staten Island Unit of Gateway National Recreation Area. The specific location of the transformer is attached to the PWS.

8.0 Period of Performance

July 27, 2024-January 27, 2025

9.0 Payment

The contractor shall submit a paid invoice for the transformer to receive payment for materials.

Final Payment will be approved when all wok has been accepted by the COR.

N ew

Y o rk A ve

B at te ry

W ee d R d S

I - 278

Major Ave.

Battery Rd.

Li ly

Po n d

A ve

Marshal Rd.

Ayres Rd.

School Rd.

Wadsworth Ave.

H u d so n

R d

North Rd.

Mont Sec Ave.

U ss

T e n n es se e R d

South Rd.

C lifto n R d

Tompkins Ave.

B attery

W ee d R d N

B a y

S t.

Verrazano-Narrows Bridge

FO

W

A W al ki n g

To u r

114113

320 314

Base Chapel

Visitor Center (temporarily closed)

Gateway NRA Headquarters

Carriage House

Seaplane Hangar

Motor Pool

Officer Club

Housing

Battery

Weed

Fort Tompkins

Back Gate

Battery Duane

Battery Bacon

Battery Hudson

Battery Mills

Battery Dix

Battery

Upton

Battery Barry

Battery Richmond

Battery Ayres

Battery

Catlin

Battery Barbour

Battery Turnbull

Command Post - Battery 218

Front Gate

Tennis Courts

Overlook

Camp Hudson

Handball Court

Observation Deck

U n i t e d

S t a t e s

C o a s t G u a r d

U n i t e d S t a t e s

A r m y R e s e r v e s

U n i t e d S t a t e s

A r m y R e s e r v e s

U n i t e d

S t a t e s

C o a s t

G u a r d

Gateway National Recreation Area Legislative Boundary

Fishing Area

Produced by GATE - Elizabeth Thomas

National Park Service U.S. Department of the Interior

Gateway National Recreation Area Fort Wadsworth

0 20

1, Feet

Document Path: Y:\GIS_Projects\EThomas\GMP Base Map Redo\MXD\GATE_GMP_Fort Wadsworth.mxd Date Saved: 8/5/2015 rsdaniels Text Box Florida Court rsdaniels Oval rsdaniels Callout Transformer Location

02-V2-SOW.pdf
Transformer Map.pdf

File details come from the government source that posted it. Updated .