A04 Survey SOW tish nfh drain.docx
DOCX document 19 KB Posted
- Attached to
- TOPO SURVEY AT TISHOMINGO NFH
- Solicitation number
- 140F0220Q0017
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B03 REGISTER OF WAGE DETERMINATIONS UNDER.docx | DOCX document | |
| A04 Tish Streamflow Measurement .PNG | PNG image | |
| B08 SF330.pdf | ||
| B08 Past_Performance_Questionnaire_PPQ Attachment 4 .pdf | ||
| A06 Tish Existing Site Plan ...pdf | ||
| Sol_140F0220Q0017.pdf | ||
| A06 Tish Survey view map..pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TISHOMINGO NATIONAL FISH HATCHERY – SURVEY
Statement of Work - Request for Quote
1. TISHOMINGO NWR HEADQUARTERS SITE
A. Description: Site survey of existing sites for development of grading and drainage plans, and for future facilities construction projects. The site is located northwest of Tishomingo, Oklahoma.
Site areas are approximately as follows; Site 1 - 12.3 Acres; Site 2 - 4.3 Acres; Site 3 - 32 Acres (includes all of Sites 1 & 2 also). The survey site boundaries are shown on the attached plan titled TISH SURVEY.
An Existing approximate site plan is available for reference and surveyor's use, and is attached in pdf format and titled TISH EXISTING SITE PLAN. The AutoCAD format of this site plan is available for surveyors use.
B. Services Required:
I. Perform topographic survey of sites as shown on attached image, using total station and/or GPS equipment with frequency of shots or data at least every 200 feet on a grid, with additional shots as needed to locate break lines, changes in elevation, and other features of interest including but not limited to utility lines (above and below ground – including water, sewer, electric power, telephone, data and others found), buildings, structures, trees, areas of vegetation, rock outcroppings, water bodies, pavement edges, and existing survey markers.
“Potholing” or other methods to accurately locate underground utilities is required. It is estimated that 15 potholes are required for Sites 1 &2, and an additional 15 for the total Site 3.
II. Data gathered shall be sufficient for preparation of an AutoCAD 2019 drawing at 1 foot contours.
III. Elevations shall be consistent with known sea level elevations and tied in to established benchmarks.
IV. Trees over 30 feet in height shall be shown either individually or in groups with approximate density indicated.
V. Set permanent survey markers with elevations and coordinates, separated by suitable distances to establish baselines for future construction.
VI. Survey shall be prepared by an Oklahoma licensed surveyor.
C. Deliverables:
I. AutoCAD drawing file showing contour lines, utilities, roads, structures, trees, survey markers, and other items described in Section B.
II. Electronic data file.
III. D-Size AutoCAD drawing stamped by an Oklahoma licensed surveyor.
IV. Permanent survey markers – quantity as established in the bid items.
General Information
USFWS Engineering Contact: Jeff Johns, USFWS Division of Engineering, 500 Gold SW, Albuquerque, NM 87102 505-248-7955.
Hatchery Contact: Kerry Graves, Tishomingo NFH Manager, 580-384-5700.
Performance time: 21 Calendar days.
Bid Items:
PROJECT: Site Surveys
LOCATION: Tishomingo NFH
DESIGNER:
| SUMMARY: Site Survey |
| QUANTITY |
| MATERIAL & LABOR |
| No. Units |
| Unit |
| Per Unit |
| Total |
Sites 1 & 2
| General Site Survey |
| 16.6 |
| Acres |
| Set Monuments |
| 4 |
| Each |
| Pothole for Utilities |
| 15 |
| Holes |
Data Download & Drafting
Hours
Travel
Miles
Per Diem
Days
Sub Total
Overhead & Profit
TOTAL
| SUMMARY: Site Survey |
| QUANTITY |
| MATERIAL & LABOR |
| No. Units |
| Unit |
| Per Unit |
| Total |
Site 3
| General Site Survey |
| 32 |
| Acres |
| Set Monuments |
| 6 |
| Each |
| Pothole for Utilities |
| 30 |
| Holes |
Data Download & Drafting
Hours
Travel
Miles
Per Diem
Days
Sub Total
Overhead & Profit
TOTAL
File details come from the government source that posted it. Updated .