This is a Statement of Work for structural repair services at Bears Bluff National Fish Hatchery, located at 7030 Bears Bluff Road, Wadmalaw Island, South Carolina 29487.
The contractor shall install ten new marine-grade treated pilings alongside damaged pilings on two catwalks in a "sistered" arrangement. The pilings must be 12-inch butt 2.5 CCA (Chromated Copper Arsenate) marine-grade treated pilings, driven to a minimum depth of 10 feet below ground, with distances from ground to piling tops ranging from approximately 14 to 16 feet. All existing pilings remain in place. The contractor is responsible for measuring and recording all site metrics, determining piling lengths accordingly, and conducting a site visit to gather necessary information for bidding. New pilings shall be connected to existing pilings using SAE 316 stainless steel grade hardware and sixteen new 3-inch by 8-inch, 0.60 CCA header boards spanning across the new pilings with 5/8-inch all-thread rods. Each set of eight piling pairs requires a minimum of two header boards, two threaded rods, four flat washers, four lock washers, and four nuts, all SAE 316 stainless steel or higher grade. The contractor is responsible for removal and replacement of any dock materials that must be removed to drive pilings and is liable for damage to existing materials. All work must comply with applicable local, state, and federal codes; trash disposal is the contractor's responsibility. Work restrictions include no fishing, swimming, or weekend work, with advance scheduling required for hours outside normal operation. The on-site point of contact is James Henne at 843-559-2315 or James_Henne@fws.gov. Contractors must submit any recommended deviations from the SOW with their quote for Contracting Officer review; absent noted deviations, all specifications will be met or exceeded at the quoted price.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC126R0013.pdf | ||
| B03_General_Decision.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Replace Marine Catwalk Pilings
Bears Bluff National Fish Hatchery Wadmalaw Island, SC 29487
Replace Dock Pilings Scope Summary:
Conduct structural repair of storm-damaged catwalk pilings by Installing ten marine grade treated pilings alongside the damaged pilings and connecting them using SAE 316 stainless steel grade hardware and marine grade treated header boards.
Services Requested Contractor shall provide permanent installation of a total of ten new pilings alongside and connected to damaged pilings (as a “sistered” arrangement) on two catwalks in the following manner:
• Ten pilings to be replaced will be marked by station management.
• Photo provided for conceptual purposes only. Bidders should not rely on the photos for locations or measurements. These metrics should be measured, recorded, and calculated by the bidder.
• Bidder to determine piling length, based on a minimum of 10-ft ground penetration.
Distances from ground to the tops of the pilings range from approximately 14 to 16 feet.
• All existing pilings are to be left in place.
• Provide and install (drive) ten 12-inch butt 2.5 CCA (Chromated Copper Arsenate) marine grade treated pilings such that they are driven alongside the existing, damaged pilings. Note that if any part of the dock (framing, railings, decking, etc.) must be removed to drive pilings, the contractor is responsible for the removal and replacement of those materials.
The contractor will be responsible for any damage to existing materials that are to remain in place, as well as materials to be removed and reinstalled or replaced. Any material to be reinstalled must be reviewed and approved by station management before reinstallation.
Otherwise, the material must be replaced with the same, but new material.
• Connect the new pilings with the existing (as sister pilings) using SAE 316 stainless steel grade hardware and sixteen new 3” x 8” 0.60 CCA headers to span across the new pilings with 5/8” all-thread rods. All stainless hardware, including threaded rods, nuts, and washers, must be SAE 316 stainless steel grade hardware or higher for prolonged contact with marine salt water.
• Each set of eight sets of pilings will require a minimum of two header boards, two threaded rods, four flat washers, four lock washers, and four nuts (material specifications called out above).
• All work must be completed following all applicable local, state, and federal code requirements.
• Haul off/dispose of any trash resulting from this work.
The prospective contractor is responsible for recording all measurements, photos, and any other information necessary for developing an accurate bid for this work during their site visit. Contractor must provide any recommended deviations from this SOW in their quote. Recommended deviations should be submitted to the Contracting Officer for a request to change the SOW. If no deviations are noted in the quote and submitted to the Contracting Officer, all installation procedures and specifications listed in this SOW will be met or exceeded by the contractor at the quoted price. Note that the contractor, subcontractor, and any other employees performing this work must comply with all station rules and regulations, including, but not limited to, that fishing, swimming, and weekend work are not permitted, and all employees performing this work must follow established safety guidelines. If the contractor wishes to work outside of the normal hours of operation, they must schedule this in advance with the station Project Leader.
Site location: USFWS, Bears Bluff National Fish Hatchery, 7030 Bears Bluff Rd, Wadmalaw Island, South Carolina, 29487.On Site POC: James Henne, 843-559-2315, James_Henne@fws.gov
Southeastern catwalk. Note one missing piling indicated by red arrow is one of the ten pilings to be replaced. Example of a header board set is indicated with yellow arrow.
Northeastern catwalk.