A04 Statement of Work PR 40472503.pdf

PDF 452 KB Posted

Attached to
WATER SAMPLING AND TESTING - SNDO Federal contract opportunity
Solicitation number
140L3920Q0014
Issued by
Department of the Interior Bureau of Land Management Nevada Region

View the file

Other files for this federal contract opportunity

Other files attached to WATER SAMPLING AND TESTING - SNDO, newest first.
File Type Posted
B09 Questions and Answers 140L3920Q0014_0001.pdf PDF
Sol_140L3920Q0014.pdf PDF
B03 DOL Wage Determination PR 40472503.pdf PDF
A06 Bid Schedule PR 40472503.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Service

FINAL

Southern Nevada District Office Las Vegas, NV

Water Sampling/Public Water Systems Southern Nevada District

Bureau of Land Management Nevada

1.0 PROJECT INTRODUCTION

Project Name: Water Sampling and Testing

Address:

BLM-SNDO

4701 North Torrey Pines Drive

Las Vegas NV 89130

1.1 Location of Facilities

(1) Red Rock Visitor Center, 1000 Scenic Loop Drive, Las Vegas NV 89161

(2) Red Rock Fire Station, 2925 Moenkopi Road, Las Vegas NV 89124

(3) Pahrump Fire Station, 7501 East Chromium Boulevard, Pahrump NV 89061

(4) Red Rock Campground, 3293 Moenkopi Road, Las Vegas NV 89161

(5) Desert Tortoise Center, 11795 S. Rainbow Boulevard, Las Vegas NV 89179

(6) Walking Box Ranch, Walking Box Ranch Rd, Searchlight, NV 89046

1.2 Short Project Description

This project consists of sampling and testing the public water systems at each of the above locations to

Nevada Department of Environmental Protection (NDEP) standards in the Southern Nevada District areas.

1.3 BLM Points of Contact

NVSO Contracting Officer Marian Rodriguez 1340 Financial Blvd Reno NV 89502 702-515-5123 Office 702-441-0310 Fax

Contracting Officers Representative/Project Manager

To be provided at time of Award

4701 N. Torrey Pines Drive Las Vegas, NV 89130

(702) 515-5XXX

BLM Safety Officer

To be provided at time of Award

4701 N. Torrey Pines Drive

Las Vegas, NV 89130

(702) 515-5XXX

2.0 PROJECT REQUIREMENTS

2.1 Scope of Work and Project Summary/Requirements

Red Rock Visitor Center Complex:

• Collect weekly total coliform/E. coli samples from the pump room during the water hauling event at the Red Rock Visitor Center. (40 CFR 141.74 (b) (1.)

-This requirement could end based on the on-site well going live, the contractor will be notified a week prior of cancelation.

• Collect bi-weekly total coliform/E. coli samples from Fee Station, and one other (upper) sample tap locations from the administration building, visitor center, or lower restroom

(compliance sampling for public water system, Nevada Revised Statue 40 CFR 141.853) -

This requirement will go in effect when the weekly is canceled.

• Collect a yearly Nitrate sample (40 CFR 141.23)

• Collect every three years Nitrite and Secondary IOCS (40 CFR 141.23)

Red Rock Campground:

• Collect bi-weekly total coliform/E. coli samples during facilities operating season, September – May (compliance sampling for public water system, Nevada Revised Statue

40 CFR 141-853)

• Collect one total coliform/E. coli sample in the beginning of August before operating season begins.

• Collect a yearly Nitrate sample (40 CFR 141.23)

• Collect every three years Nitrite and Secondary IOCS (40 CFR 141.23)

Red Rock Fire Station:

• Collect quarterly coliform/E. coli samples (compliance sampling for public water system, Nevada Revised Statue 40 CFR 141.853)

• Collect a yearly Nitrate sample (40 CFR 141.23)

• Collect every three years Nitrite and Secondary IOCS (40 CFR 141.23)

Pahrump Fire Station:

• Collect monthly total coliform/E. coli samples (for one year; then return to quarterly samples) (compliance sampling for public water system, Nevada Revised Statue 40 CFR

141.853)

-This requirement will end once NDEP’s requirement has been satisfied, the contractor will be notified a week prior of cancelation.

• Collect quarterly coliform/E. coli samples (compliance sampling for public water system, Nevada Revised Statue 40 CFR 141.853)

-This requirement will go in effect when the monthly is canceled.

• Collect a yearly Nitrate sample (40 CFR 141.23)

• Collect every three years Nitrite and Secondary IOCS (40 CFR 141.23)

Desert Tortoise Center:

• Collect quarterly coliform/E. coli samples (compliance sampling for public water system, Nevada Revised Statue 40 CFR 141.853)

• Collect a yearly Nitrate sample (40 CFR 141.23)

• Collect every three years Nitrite and Secondary IOCS (40 CFR 141.23)

Walking Box Ranch:

• Collect quarterly coliform/E. coli samples (compliance sampling for public water system, Nevada Revised Statue 40 CFR 141.853)

• Collect a yearly Nitrate sample (40 CFR 141.23)

• Collect every three years Nitrite and Secondary IOCS (40 CFR 141.23)

All Locations:

• Collect quarterly total coliform/E. coli samples from water systems as required/necessary.

• Collect annual nitrate samples as required/necessary.

• If notified by the Lab of a positive total coliform/E. coli sample, take three repeat samples and a well sample within 24 hours of notification and three repeat samples the following month.

• All samples need to be taken in accordance with all NDEP state guidelines and regulations.

2.2 Deliverables required from compliance sampling

• Invoice to show sampling(s) was completed from at which location, along with chain-of-custody record from laboratory.

• A copy of the laboratory report on samples taken showing test results.

• All personnel performing the compliance sampling must be certified/trained on how to properly take a compliance water sample according to NDEP, state and regulatory guide lines.

2.3 Working Hour Restrictions

All work shall be limited to the weekday hours of 8:00 am to 4:00 pm unless otherwise approved by the

Contracting Officer Representative. Coordination for site access needs to be scheduled with Bureau of

Land Management Safety Officer in advance. No work shall occur on federal holidays or weekends without prior approval. This work should be completed in one or two days during normal work hours of

8:00 a.m. to 4:00 p.m. and quarterly samples will be taken toward the beginning of each quarter.

2.4 Smoking

Smoking within buildings or temporary storage sheds is prohibited and smoking areas are in open areas and will be away from entrances at least fifty feet away.

3.0 PERFORMANCE REQUIREMENTS

3.1 Protection

Protect any areas adjacent to the project site from any debris. Comply with governing regulations pertaining to environmental protection. Ensure safety of persons in the work area. Provide temporary barricades as required to protect personnel and public from injury due to water sampling.

Water Sampling Schedule

Location Weekly Bi-Weekly Quarterly Annually

Red Rock Visitor Center X* X X X

Red Rock Fire Station** X X X

Pahrump Fire Station** X X X

Red Rock Camp Ground*** X X X

Derest Tortoise Center X X

Walking Box Ranch X X

*Red Rock Visitor Center: Weekly is only during water haul event, estimated to end Dec 2018

**Fire Stations: Seasonal, April 1 – September 30

*** Red Rock Camp Ground: Seasonal, September 1 – May 31

A04 Statement of Work PR 40472503
Water Sampling Schedule