This document is a Statement of Work for a federal contract opportunity issued by the National Park Service (NPS) at Oregon Caves National Monument and Preserve (ORCA). The NPS requires the preparation and submission of both a temporary and permanent water rights transfer application, which will include the creation of a certified water rights map.
The key details are: The project is located at Oregon Caves National Monument and Preserve in Josephine, OR. The Contractor shall provide all supervision, labor, equipment, testing, and supplies necessary to complete the work as identified. The North American Industry Classification System (NAICS) Code for this requirement is 541360, with a corresponding size standard of $28,500,000 million. This acquisition is a Total Small Business Set-Aside. The Government anticipates award of a firm-fixed-price purchase order resulting from this solicitation. Evaluation for award will be made in accordance with the simplified acquisition procedures outlined in FAR Part 13.106.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL REQUIREMENTS Page 1
OREGON CAVES NATIONAL MONUMENT
CERTIFIED WATER RIGTHS MAP
PMIS # 324138
Solicitation #140P8424Q0037
STATEMENT OF WORK
GENERAL REQUIREMENTS
PART 1 – SUMMARY OF WORK (SECTION 01 11 00) & DEFINITION OF CLINs (01 27 00)
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. General: All work outlined below will be performed under a single contract.
B. Project Location: This project is located near the HQ building at Oregon Caves National
Monument.
C. Project Scope of Work / Definition of Contract Line Items: The Work consists of the following:
1. Contract Line Item No. 0001: Certified Water Rights Map and Transfer
Application(s)
This item shall consist of creating the certified water right maps and transfer applications.
GENERAL REQUIREMENTS Page 2
PART 2 TECHNICAL REQUIREMENTS
Oregon Caves National Monument currently has two separate water rights that are used for domestic water purposes. The primary permit (#11389) is located on Lake Creek and the water is used for the main park visitor area. The second permit (#26663) is from a small spring located near the HQ area.
Water from this spring is used to supply an admin building and staff housing unit. The spring associated with permit #26663 has become unreliable in recent years. To address this issue the park intends to construct an additional point of diversion downstream of the existing point of diversion for permit
#11389. From the new point of diversion, a raw water line will be constructed to serve the HQ area.
Water from permit #11389 will then be used to supply the HQ area.
To construct an additional point of diversion the park must submit a water rights transfer application to the state. That application requires a map that is to be created by a certified water rights examiner.
Therefore, as a requirement of this scope, the bidder must be listed as a certified water rights examiner with the state of Oregon. The NPS has already created a rough version of the map required (see attached) but does not have a certified water rights examiner on staff. The NPS has also already drafted the transfer application as well. A copy of the draft map that was prepared by the NPS is attached for reference. Copies of the draft application, and the draft construction plans for the raw water line will be provided to the successful bidder for reference.
From conversations with State officials, the NPS was made aware that there is currently a backlog to review applications, and some application reviews are taking longer than 1-year to complete. The NPS intends to construct the raw water main in the summer of 2024. Therefore, the scope of this task also includes preparing and submitting a temporary transfer application with the same intent. The NPS was told that the temporary transfer application can be processed much sooner and could allow for construction on the intended timeline. The idea is that the NPS would obtain the temporary transfer that would be followed up by the permanent transfer. Both applications would be submitted at the same time. Permit #26663 will remain as-is. The NPS still intend to use water from this source when feasible.
Therefore, the scope of this task is as follows:
1. Research survey records to determine corners to be tied to locate quarter-quarter section lines.
2. Field survey (as required) to make corner ties, recover monuments, etc.
3. Field survey to map diversion points, infrastructure and places of use.
4. Draft transfer application map.
5. Prepare and submit transfer application form and supporting documents.
6. Visit Josephine County planning to obtain OWRD land use form.
7. Modify permanent transfer map to meet temporary transfer requirements.
GENERAL REQUIREMENTS Page 3
8. Prepare and submit temporary transfer application and supporting documents.
9. Advise NPS staff as needed to complete the application process.