This document is a Performance-Based Statement of Work (SOW) for replacing Water Well #16 at the Patuxent Research Refuge in Laurel, Maryland. The U.S. Fish and Wildlife Service requires a licensed Maryland well drilling contractor to repair the well, which serves the North Tract Visitor Contact Station. Specific work requirements include removing the existing pump, installing a new HP 2300 stainless steel Schaefer pump, 4" PVC well cap, pitless head unit, 220 feet of pump wire, and 1" polyethylene pipe, and completing well disinfection according to Maryland Department of the Environment regulations.

The contract (Solicitation Number 140FC225Q0033) has an estimated performance period of approximately 8 weeks from award, with work to be completed at 230 Bald Eagle Drive, Laurel, MD 20742. The contractor must provide 24-hour advance notice for site access, work during 7 AM to 3:30 PM hours, and ensure all employees have proper identification. Deliverables include a fully functional well, proper disposal of old equipment, and a test pump report. The government point of contact is Martin Brockman, USFWS Facilities Manager, reachable at 301-497-5584 or 240-374-9350.

View the file

Other files

File Type Posted
Sol_140FC225Q0033.pdf PDF
B03_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Based Statement of Work Replacement of Water Well #16 Pump and Accessories. SAMMS ASSET 10021754 230 Bald Eagle Drive Patuxent Research Refuge – Laurel, MD 20742

General Information Introduction Patuxent Research Refuge (PRR) is in Laurel MD. The refuge is a unit of the US Fish and Wildlife Service’s National Wildlife Refuge System. This statement of work requires a certified well drilling company to repair and disinfect water well #16 which provides water to the North Tract Visitor Contact station. Undetected continuous pumping resulted in the motor start capacitor failing. The pump, when energized, continues to cycle on at approximately 42 PSI and off at 62 PSI, per the gauge installed at the bladder tank. The loss of pressure, which occurs without demand is attributed to failure of the check valve installed in the casing. The well was completed on 4/1/1992, the manufacturers date on the pitless adapter is 1990. We believe the well pump is the same unit originally installed in 1992.

The government needs to have a new ¾ HP 2300 stainless steel Schaefer pump or equivalent, a 4” x 1 ¼” pitless head unit, A new 4” PVC well cap, approximately 220 feet of #12-2 pump wire, 220 feet of 1” 160 PSI polyethylene pipe or tubing. A check valve should be incorporated into the new pump, or be installed in the polyethylene pipe. All labor should be included in well contractor’s pricing. The well must be disinfected prior to being placed back in service.

Background:

The water well was originally drilled in 19921 and consists of a 4” steel casing drilled to a depth of approximately 150’. The well is tagged AA88-7584 with MDE well permit number AA1992G011(02) Scope:

In accordance with the work requirements below, the contractor shall perform all required steps to repair water well #16 in compliance with Maryland Department of the Environment regulations.

Work Requirements:

Technical requirements:

The contractor is responsible for:

1. The contractor shall be a licensed well driller in the state of Maryland.

2. Selective Demolitions: The contractor shall remove and legally dispose of one well pumping unit.

3. Verify well depth by sounding.

4. Install a ¾ HP 2300 stainless steel Schaefer pump or equivalent

5. Install a 4” x 1 ¼” pitless head unit,

6. Install A new 4” PVC well cap,

7. Install approximately 220 feet of #12-2 pump wire,

8. Install approximately 220 feet of 1” 160 PSI polyethylene pipe or tubing. A check valve should be incorporated into the new pump or be installed in the polyethylene pipe.

9. The contractor shall complete disinfection of the well per Maryland Department of the Environment Water well procedures.

10. The contractor shall test pump the well as appropriate and shall provide a copy of the test report to the Government’s COR.

Notes

· All old equipment will be removed, disposed and recycled per federal and state laws

· The refuge is a closed facility. Access will be provided to areas behind locked gates. The contractor must provide 24 hours’ notice of intention to complete work so access can be guaranteed.

· Work hours are 7AM to 3:30 PM

· Patuxent Research Refuge is a controlled access facility. Contractor employees must have identification. Employee names must be provided to COTR in advance of starting work.

Deliverables:

The contractor shall provide all labor, material, technical knowledge and expertise to meet the necessary requirements. The contractor shall remove and properly dispose of all old equipment and materials and leave the site without any debris around it. The contractor may dispose of clean scrap metal in the facilities metal recycling dumpster. Area must be clean of all rubbish caused by the well Repair process. A complete working well shall be demonstrated as the requirement for completion and final payment.

Delivery Dates:

From Time of award to the end of the contract (approximately 8 weeks)

Place of performance:

US FWS Patuxent Research Refuge 230 Bald Eagle Drive Laurel, MD 20742 Government Furnished Property N/A Special considerations

1. Technical / government liaison for this contract is the USFWS Facilities Manager, Mr. Martin Brockman located at the Service Building 12311 Beech Forest Rd, Laurel MD 20708. Contact office phone is 301 497 5584 or cellular 240 374 9350.

2. Normal working hours for Facility Staff are from 7:00 AM to 3:30 PM Monday through Friday except for Government holidays and special events.

Project Safety:

The Contractor shall be responsible for strict compliance with all provisions of Occupational

Safety and Health Administration (OSHA) requirements during performance of the work.

image2.emf image1.emf