This document is a Specifications/Scope of Work for the United States Department of Interior's FWS Cache River National Wildlife Refuge (NWR) in Arkansas. The solicitation requires a contractor to supply and tailgate spread approximately 700 tons of SB2 Kentucky blue/gray limestone across five different road locations in Prairie, Monroe, and Jackson Counties. The limestone must be delivered and spread to a depth of approximately 3 inches, with delivery trucks required to have tailgate chains to ensure consistent spreading.
The period of performance is 90 days from the award date, with contractors expected to coordinate delivery of a minimum of 100 tons of limestone daily between 7:30 AM and 4:00 PM, Monday through Friday. Delivery is prohibited on weekends, federal holidays, and during wet conditions that could damage existing roads. The contractor is responsible for all delivery, spreading, and grading equipment, and must provide scale tickets documenting weight, material, and date for each load to the refuge representative. Each delivery location will receive 140 tons of limestone, with complete delivery and spreading at one location required before moving to the next.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FS326Q0016_Amd_0001.pdf | ||
| Sol_140FS326Q0016.pdf | ||
| Cache_River_Aggregate_Contract_North_Map.pdf | ||
| Sol_Clauses_Q1.pdf | ||
| Cache_River_Aggregate_Contract_South_Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Interior
FWS CACHE RIVER NWR
26320 HIGHWAY 33 SOUTH
AUGUSTA AR 72006-5027
Supply, tailgate spread SB2 Limestone at the Cache River NWR
Specifications/Scope of Work
Contractor to supply approximately 700 tons SB2 limestone tailgate spread and delivered approximately (3) inches in depth on Cache River National Wildlife Refuge (NWR) in Prairie, Monroe and Jackson Counties, Arkansas.
Delivery locations, quantity, and directions are listed below:
1. Bisco bottoms Road Asset # 10041483 - 140 tons
2. Nail Tract Road Asset # 10069906- 140 tons
3. Greorge Tract Road Asset # 10017407 – 140 tons
4. Algoa Road Asset # 10039193 - 140 tons
5. Bank of Brinkly Road Asset # 10017445- 140 tons
Amount: Total of 700 tons of SB2 Kentucky blue/gray limestone – delivered and tailgate spread outlined by refuge personnel.
All Delivery trucks must be fitted with tailgate chains to allow consistent spreading of gravel.
All gravel will be tailgate spread. Trucks not fitted with chains will not be allowed to dump.
Period of Performance: Will be 90 days from award date
Contractor will coordinate with refuge representative to deliver a minimum of 100 tons of limestone daily from 7:30 AM to 4:00 PM, Monday through Friday. Delivery will not be accepted weekends, Federal Holiday or during wet conditions that could damage existing roads and parking areas. Contractor is responsible for all equipment used to deliver, spread, and grade to final specifications. Delivery, spreading and grading at each location or group of adjoining locations will be made in entirety before moving to a new location. Scale tickets with a minimum of weight, material and date will be provided to refuge representative for each load.