A04_Statement_of_Work.pdf

PDF 268 KB Posted

Attached to
Replace Roof and Gutter - CNHP Federal contract opportunity
Solicitation number
140P4225Q0013
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This Statement of Work details a roofing and gutter replacement project for a housing unit located at 109 Jefferson St. in Williamsburg, Virginia, within the Colonial National Historical Park. The project requires removing and replacing approximately 2,000 square feet of asphalt architectural 30-year shingles, synthetic underlayment, damaged plywood sheeting, flashing, and approximately 300 linear feet of gutters with downspouts and gutter guards. The contractor must perform work between 8 AM and 4 PM, ensure all materials match existing specifications, follow OSHA guidelines, and provide a minimum 1-year warranty on building components and 5-year warranty on workmanship. Key requirements include using new materials, protecting the building during construction, installing dark gray architectural shingles with interlocking tabs, replacing drip edges, installing ridge vents, and completing a thorough cleanup of the work site upon project completion.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Roof and Gutter - CNHP, newest first.
File Type Posted
Sol_140P4225Q0013_Amd_0001.pdf PDF
A06_Photos.pdf PDF
B03_Wage_Determination.pdf PDF
Sol_140P4225Q0013.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COLO PMIS 319423 December 7 2024

COLONIAL NATIONAL HISTORICAL PARK

Williamsburg, Virginia

Replace Roof and Gutters on 109 Jefferson St (Park Housing Quarters)

PROJECT MANUAL

Summary of Work

NATIONAL PARK SERVICE

December 7, 2024

STATEMENT OF WORK

REMOVE/REPLACE ASPHALT SHINGLE ROOF AND GUTTERS ON Jefferson St (Park Housing Quarters)

109 Jefferson St. Williamsburg VA 23185 Colonial National Historical Park

Virginia

PART 1 - GENERAL

1.01 DESCRIPTION OF WORK

A. This contract provides for the removal and replacement of approximately 2,000 -SF of asphalt architectural 30 year shingles and #30/synthetic underlayment, repair/replace damaged plywood sheeting, replace flashing around chimney(s), replace drip edge, install roof underlayment, installation of a ridge vent(s) along the length of the building, the removal and replacement of approximately 300-LF of gutter with downspouts and installation of approximately 300-LF of gutter guards on 109 Jefferson St..

1. The building is a two-story housing unit/garage with an asphalt shingle roof. The building has gutters along the front and the back.

2. The buildings may be occupied during this contract.

B. The contract work includes:

1. Remove and dispose of the existing asphalt shingle roof(s) and roofing underlayment off site

2. Protect the building structure and contents from weather and other potentially damaging elements

3. Inspect the existing roof supports (rafters) and fascia boards, replace damaged facia, trim boards

4. Repair or replace in kind as necessary damaged roof supports (rafters), decking, sheathing revealed by inspection

5. Replace in kind all existing flashing

6. Install new 30 pound or synthetic asphalt saturated roofing underlayment

7. Install new dark gray 30 year architectural shingles with interlocking tabs

8. Install new drip edges around the entire perimeter of the roof

9. Install full length ridge cap roof vent system

10. Flash Chimney

11. Install new waterproof vent collars

12. Remove and replace approximately 300 linear feet of gutter and associated downspouts on building.

Note: One section of gutter and downspout are missing from backside of house, new section will need to be installed

13. Install gutter guards on all gutters

14. Disposing properly of all excess materials and debris;

15. Erosion prevention and quality assurance testing;

16. Reconstruction and restoration of disturbed areas.

C. All work will be performed under a single contract.

D. Work and materials shall adhere to the following mitigations:

1. Replacement architectural asphalt shingles should match existing shingles in size, color, and texture. New shingles must be approved by COR before installation.

2. Materials shall be stored on pavement at work location.

3. Must follow OSHA guidelines for work performed on an elevated surface.

1.02 LOCATION AND ACCESS

A. The project site is located at 109 Jefferson St. Williamsburg VA 23185.

1.03 CONTRACTOR-FURNISHED ITEMS

A. The Contractor shall furnish all necessary supervision, personnel, equipment, transportation, materials, and incidentals required to complete the contract requirements.

B. Contractor shall provide proof of liability insurance for all personnel working in completion of this project.

1.04 WORK CONDITIONS AND LIMITATIONS

A. FACILITY USE

B. REQUIRED PERFORMANCE PERIOD

1. Work performance period is to be determined; all work shall be performed between 8 AM – 4 PM.

C. CONTRACTOR’S USE OF PREMISES

1. Confine on-site material storage, equipment and vehicle parking, and staging to paved parking areas or other areas specifically designated by the Contracting Officer’s Representative (COR).

2. Keep job site clear of trash and debris. Dispose of any trash, debris and other unusable material legally at authorized facilities on non-Federal land.

D. FIELD VERIFICATION

1. The measurements and quantities specified are estimates and provided for information only. The Contractor must verify all locations, dimensions and conditions affecting the work.

1.05 QUALITY ASSURANCE

A. All proposed materials and methods must meet or exceed the current local, state, and federal codes, standards, and regulations applicable to the contract work.

B. All personnel performing work shall be fully qualified and experienced in the type of work they will execute.

1.06 WARRANTIES

A. Building components: Minimum 1-year warranty against defects. Provide a minimum 5-year warranty for workmanship.

B. Prior to beginning work, report to the COR any conflict in warranty requirements, work scheduling or material availability before proceeding with the work.

1.07 MATERIAL HANDLING

A. Deliver materials to the job site as per COR instructions. Comply with all manufacturers’ recommendations for storage, protection and handling.

PART 2 - MATERIAL

2.01 GENERAL

A. Use new materials except as otherwise approved by the Contracting Officer (CO).

2.02 REQUIRED SUBMITTALS AND APPROVALS

A. LIST OF REQUIRED SUBMITTALS

1. Contractor Liability Insurance

2. Warranty Information

B. CHANGES TO MATERIAL REQUIREMENTS

1. Any proposed changes by the Contractor to the construction materials shall be submitted in writing to the

COR

PART 3 - EXECUTION OF WORK

3.01 GENERAL

A. SERVICE INTERRUPTION

1. Indicate by work schedule expected periods of construction to avoid conflict with operations.

B. SITE INVESTIGATION

1. The Contractor is responsible for investigating site conditions in the vicinity of the required work for any hazards or obstacles which may increase time or cost of the work.

C. CHANGES TO CONSTRUCTION METHODS

1. Any proposed change by the Contractor to the specified construction methods and manufacturer’s instructions must be submitted in writing to the CO along with the justification for the proposed change.

Approval from the CO is required for changes in specified construction methods.

D. PROTECTION OF WORK SITE

1. Work site is not protected and is open with no fencing.

2. Maintain the work area and approaches clean and free from trash and debris to reduce interference with ongoing maintenance operations.

3. Provide a safe bypass for NPS employees, and contractor’s personnel.

3.02 PROJECT CLOSEOUT

A. CLEANUP

1. Remove all tools, equipment, excess materials, construction debris, and trash from the project site. Leave project site clean and ready for use at the time of final inspection.

2. Legally dispose of all excess and unusable materials at authorized disposal facilities.

B. FINAL INSPECTION AND ACCEPTANCE OF WORK

1. When all work including any site restoration and cleanup has been completed, the Contractor shall contact the COR to arrange the final inspection.

2. The Contractor shall be notified of any deficiencies found during the final inspection. After all deficiencies have been corrected and all required closeout submittals have been forwarded to the COR, the CO will issue a letter of final acceptance and request the release of claims.

C. CLOSEOUT SUBMITTALS

A. Provide to the COR the following closeout submittals and any other closeout submittals required by the CO:

1. Cut-Sheet Binder: Submit one binder with all manufacturer product information and cut-sheets for all materials installed under this contract. Label binder with project title and include one “contents” page.

PART 4 – PAYMENT

1. Final payment shall be processed upon confirming all noted contractor performance deficiencies have been satisfactorily corrected.

1.02 LOCATION AND ACCESS
1.03 CONTRACTOR-FURNISHED ITEMS
1.04 WORK CONDITIONS AND LIMITATIONS
A. FACILITY USE
C. CONTRACTOR’S USE OF PREMISES
D. FIELD VERIFICATION
1.05 QUALITY ASSURANCE
1.06 WARRANTIES
1.07 MATERIAL HANDLING
PART 2 - MATERIAL
2.02 REQUIRED SUBMITTALS AND APPROVALS
A. LIST OF REQUIRED SUBMITTALS
B. CHANGES TO MATERIAL REQUIREMENTS
PART 3 - EXECUTION OF WORK
A. SERVICE INTERRUPTION
B. SITE INVESTIGATION
C. CHANGES TO CONSTRUCTION METHODS
D. PROTECTION OF WORK SITE
3.02 PROJECT CLOSEOUT
A. CLEANUP
B. FINAL INSPECTION AND ACCEPTANCE OF WORK
C. CLOSEOUT SUBMITTALS

PART 4 – PAYMENT