This document is a Statement of Work (SOW) for the supply and delivery of 24-inch diameter steel casing pipe to support the construction of a new water pipeline at the Neosho National Fish Hatchery in Neosho, Missouri. The SOW requires the contractor to furnish and deliver approximately 620 linear feet of steel casing pipe that must meet specific ASTM standards and be delivered in mid-to-late January 2024 ahead of the pipeline construction. The delivery location is the Missouri Department of Transportation Neosho Maintenance Building. The SOW also notes that the government may perform testing on the materials to ensure compliance with specifications, and the contractor must cooperate and provide access for testing. The related federal contract opportunity is solicitation number 140FS225Q0006 issued by the U.S. Fish and Wildlife Service.

View the file

Other files

File Type Posted
Sol_140FS225Q0006.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Neosho National Fish Hatchery, Elm Spring Pipe Encasement, Scope of Work

GENERAL REQUIREMENTS (MATERIALS) 110000 - 1

Hwy 60 Water pipeline project Sept. 2024

SECTION 110000 – GENERAL REQUIREMENTS (MATERIALS)

PART 1 − GENERAL

1.1 SUMMARY

A. Section Includes:

1. Summary of work included under these specifications.

2. Site Location

3. Specifications

4. Government Testing

5. Safety

1.2 SUMMARY OF WORK

A. The U.S. Fish & Wildlife Service is requesting proposals for the supply and delivery of

Steel Casing pipe to install under roadways for the future construction of a new water pipeline at the Neosho National Fish Hatchery in Neosho, Missouri. The Contractor shall furnish & deliver the following materials in the amounts specified and in compliance with the specifications.

MATERIALS LIST ESTIMATED QUANTITY

1. 24” DIAMETER STEEL CASING PIPE 620 Lineal Feet

B. Deliver pipe to: Missouri DOT - Neosho Maintenance Building, 1439 Malcolm Mosby

Drive, Neosho, MO 64850.

C. The pipe shall be required to be delivered in mid to late January, ahead of when the roadwork is anticipated to begin construction.

D. If additional amounts of materials are required to complete the project, the contractor and government shall negotiate for a per LF cost for additional materials to be delivered.

1.3 LOCATION & INSPECTION OF THE SITE

A. The project site is located near the intersection of Hwy 60 and Route HH in Neosho, Missouri. The delivery site for the pipe is the Neosho Missouri Department of

Transportation, Neosho Maintenance Building 1439 Malcolm Mosby Drive, Neosho, MO

64850. Delivery Contact is Sheila Denmark, Missouri DOT at (417)-621-6355.

B. All prospective bidders, contractors, subcontractors, and related persons are encouraged to visit the site of the proposed work and to assess the location and extent of the work prior to submitting bids/quotes. Persons may inspect the site by contacting the Hatchery

Manager for an appointment.

Neosho National Fish Hatchery, Elm Spring Pipe Encasement, Scope of Work

GENERAL REQUIREMENTS (MATERIALS) 110000 - 2

Hwy 60 Water pipeline project Sept. 2024

1.4 SPECIFICATIONS

A. Steel Casings: Steel casings for future water line construction shall be newly fabricated smooth wall, welded steel pipe conforming to American Society for Testing and

Materials (ASTM) A 139 (ANSI B36.10); Grade B, minimum yield strength of 35,000 psi. Minimum wall thickness shall be 0.375”. Joints shall be prepared for butt welds to be performed in the field. Lengths of pipe to be supplied shall be approx. 20’ but can be plus or minus 2’.

B. The contractor shall be required to provide certifications or reports to the government to ensure the materials being supplied meet the specifications. Steel used in this contract must be provided in accordance with the “Buy American Act”.

C. Certifications shall be submitted to the Contracting Officers Representative (COR) for review and approval before materials are ordered, fabricated, or delivered.

D. The construction of the water pipeline is to be completed by other contractors. The work included in this contract is limited to supplying materials and delivery to the project site.

1.5 GOVERNMENT TESTING

A. The Government may at its expense perform testing of the materials being supplied to ensure that they meet the required specifications. The contractor shall be required to cooperate and provide access to materials for testing purposes.

1.6 SAFETY

A. Contractor shall be responsible for ensuring that all delivery vehicles have proper safety equipment, insurance, and trained operators. All equipment and delivery activities shall comply with OSHA regulations.