A04-Statement_of_Work.docx
DOCX document 22 KB Posted
- Attached to
- GATE-FOWA STREET & SITE LIGHTING REPAIR
- Solicitation number
- 140P4522Q0047
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P4522Q0047.pdf | ||
| SCA_Wage_Determination_2015-487.pdf | ||
| Master_Combined_Synopsis_Solicitation_Template_(below_SAT).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work FOWA Street and Parking Lot Lighting Intent: This high voltage electrical work will repair the power supply for the streetlights on New York Avenue and Mont Sec Avenue. The repair will also restore site lighting at FOWA Building 210 and 120. This lighting will improve the safety and security of Fort Wadsworth for visitors, partner agencies and Gateway NRA employees.
The successful proposal shall include a scope of work from a licensed electrical contractor. The following scope describes the required work to be performed. This requirement is to repair existing power supply to street lighting.
Period Of Performance: Estimated Period of Performance is 5 days. Proposals must include anticipated lead times for materials and components. Work must be complete no later than 4 November 2022 Scope of Work DIV 00: Procurement and Contracting Requirements 00 25 16 Contractors are encouraged to perform a site visit before preparing a Proposal for the work.
DIV 01: General Requirements 01 14 13 All work will take place between Monday and Friday, from 7:30 AM to 3:30 PM.
01 33 23 Contractor will provide the NPS product information sheets for all materials and components used during the repairs.
01 45 23 Contractor will perform an acceptance test on the new cable and provide a written report of the results to the NPS for acceptance prior to final payment.
01 77 00 Contractor will provide the NPS all written warranty information for components used during the repairs.
Division 26: Electrical 26 56 16 Contractor will Demo existing 5 kV cable from the existing switch to transformer for LX-1 lot lighting.
Contractor will provide and install new 4/0 5 kV cable from existing switch to the transformer for LX-1 site lights.
Contractor will provide and install four (4) new 5 kV terminations on ends at the end of the new cables.
Contractor will provide and install two (2) 5 kV fuses for existing switch.
Contractor will energize LX-1 transformer and verify correct voltage.
26 56 19 Contractor will Demo existing 5 kV cable from the existing switch to transformer for LX-2 roadway lighting.
Contractor will provide and install new 4/0 5 kV cable from existing switch to the transformer for LX-2 site lights.
Contractor will provide and install four (4) new 5 kV terminations on ends at the end of the new cables.
Contractor will provide and install two (2) 5 kV fuses for existing switch.
Contractor will energize LX-2 transformer and verify correct voltage.
Note: Any deviations to the scope of work must be coordinated with the COR and approved by the Contracting Officer.
File details come from the government source that posted it. Updated .