A04_Statement_of_Work_0044016984.pdf

PDF 80 KB Posted

Attached to
Boardwalk Materials for Bear River NWR
Solicitation number
140FGA25Q0022
Issued by

About this file

This Statement of Work (SOW) details design services for a boardwalk purchase at the Bear River Migratory Bird Refuge, Project 23-001D. The contract requires supplying precast concrete decking with specific technical requirements, including helical pier installation, minimum 9-PSF uniform loading capacity, 4,000 PSI compressive strength, textured surface, and a ten-year warranty. Additional requirements include 316 stainless steel integral railing with two four-foot lockable gates, and a complete LumenPod 16 lighting system that is night sky compliant, LED-based, with specific technical specifications like 24V power requirement, -40°C to +60°C temperature range, and IP54 outdoor rating.

The SOW outlines comprehensive submittal requirements, including detailed plan submissions for connections, railing, brackets, reinforcements, lighting, decking, and other components. Contractors must provide physical samples and documentation, with alternatives to specified materials requiring a detailed written comparison. The government will review submittals within 14 days, with the option to request seven-day extensions if needed. Delivery of materials will be to the employee parking lot area east of the building, with the supplier responsible for identifying heavy equipment weights and preferred lifting solutions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Boardwalk Purchase P a g e 1 | 3

STATEMENT OF WORK

Design Services

Bear River Migratory Bird Refuge

Boardwalk Purchase

Project 23-001D

I. PROJECT SCOPE

A. General

Contract shall provide, based on the specifications and drawings:

1. Supply precast concrete decking and attachments, such as PermaTrak or equal. The attachments shall adhere to helical pier installation.

• Helical piers will be installed

• The boardwalks connect to the building. The contract shall supply an attachment mechanism.

• Withstand a minimum of 9- PSF uniform loading and for H-5 truck.

• Compressive strength of a minimum of 4,000 PSI after 28-days.

• Textured contact surface to reduce ice buildup and slipperiness, similar to PermaTrak beachwood, or equal.

• Interlocking sections.

• Minimum of ten year warranty for defects in material and workmanship

2. Supply integral railing

• 316 stainless steel handrail, posts, cables, support brackets, and hardware.

• Shall include a toe board.

• Install two four-foot gates on each side of the west boardwalk that is possible to be locked by some mechanism. The gate will allow staff to access the building ground level. The gate shall closely match the railing. All components shall be 316 stainless steel.

3. Lighting system

• The number of lights depends on the illumination. The entire boardwalk sides shall be illuminated.

• Corrosion resistant materials.

• Provide and install a complete LumenPod 16 by Wagner, or approved equal, lighting system on the boardwalk handrail. Include all parts, labor, and materials needed to install a complete working system. The lighting system must run the full length of the boardwalk in the railing on both sides of each boardwalk. The lighting system shall meet the following requirements.

• All lighting shall be night sky compliant with lights pointed

Boardwalk Purchase P a g e 2 | 3 towards the ground.

• LED Light source

• Light Output: Standard Output, 2700K or amber in color.

• Beam Angle: Asymmetric

• Listings: ETL Listed for wet or dry locations to UL 1598, UL

8750, and CSA22.2

• Power Requirement: 24V

• Power Supply: 24V/100W

• Temperature Range: -40° C through +60° C

• Product Rating: Interior and Exterior Applications, ETL Class 2 circuit.

• All lighting shall be rated for outdoor use and meet IP54 ratings or better.

The material shall be delivered to the employee parking lot area located directly east of the building.

B. Delivery

1. Station can offload materials after visual inspection of the materials. Prior to delivery, the supplier shall identify the weight of the heavy pieces of equipment and the preferred lifting solutions.

2. The supplier shall identify all materials that need to be stored indoors prior to delivery.

C. Submittal lists

1. Plan details showing all connections

2. Railing

3. Brackets

4. Reinforcements

5. Anchor attachment

6. Welded and bolted connections

7. Lighting

8. Lighting attachment

9. Decking with physical sample

10. Toe board

11. Gate

12. Concrete slump sample to prove compressive strength

13. Grout color match (supplier does not need to provide grout)

IV. SUBMITTALS

A. If alternatives to the means and materials described in these specifications are offered, the submittal must contain a written description of the proposed means and materials comparing all features, options, and codes (if any), in detail. A detailed explanation of why the proposed alternative should be accepted must also be submitted.

Boardwalk Purchase P a g e 3 | 3

B. The Contractor shall submit manufacturer's warranties, guarantees, and certificates for all installed equipment listed on the Project Submittal List.

C. All submittals shall be reviewed within 14 days of submission. If extensions are needed by the Government, the Government will notify within seven days.

D. All construction items shall be submitted for approval.

E. The attached submittal form shall be used.