This document is a Statement of Work (SOW) for constructing repair services on the Headquarters/Visitor Center Building at the Sandy Point National Wildlife Refuge in the Virgin Islands.

The SOW outlines four key construction tasks: replacing and re-routing electrical and communication services to the facility, performing mold evaluation/detection, and conducting mold remediation. It provides details on the specific work required, such as relocating underground electrical and communication lines, installing new poles and transformer, remediating any mold issues, and providing as-built drawings upon completion. The SOW also includes general construction requirements, communication protocols, payment procedures, safety guidelines, and closeout procedures.

The related federal contract opportunity is for the rehabilitation of the storm-damaged Headquarters/Visitor Center Building at the Sandy Point National Wildlife Refuge, issued by the Department of the Interior Fish and Wildlife Service. The solicitation number is 140FHR24R0011.

View the file

Other files

File Type Posted
Sol_140FHR24R0011_Amd_0002.pdf PDF
A04_-_SOW_(Updated_11_06_24)_0002.pdf PDF
Sol_140FHR24R0011_Amd_0001.pdf PDF
Sol_140FHR24R0011.pdf PDF
B03_-_DOL_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sandy Point HQ/VC Building Rehabilitation Project Page 1 of 12

STATEMENT OF WORK

FOR

CONSTRUCTION REPAIR SERVICES PROJECT

ON

HEADQUARTERS/VISITOR CENTER BUILDING

AT

SANDY POINT NATIONAL WILDLIFE REFUGE

September 11, 2024

Asset Number: 10036975

WO#: F2023485156

BACKGROUND:

The Sandy Point National Wildlife Refuge (NWR) Headquarters/Visitor Center Building requires mold remediation services and rehabilitation/repairs services on the damaged Communication and Power Lines due to Hurricane Fiona of 2022. This Statement of Work (SOW) defines all the required tasks to repair these damages. The material and performance specifications for the Construction Services tasks are incorporated in the project description below. Consult any changes or recommendations with the Contracting Officer (CO).

Any dimensions provided below are approximate in nature. The Contractor shall verify all dimensions and note such dimensions on the submitted proposal. Product data submittals shall be required for all construction materials proposed herein.

DESCRIPTION OF WORK:

Task 1: Construction Services Task – Replace and Re-route Electrical Service to Facility – Base Bid

1. Task shall consist of a full evaluation of the existing electrical services to the HQ/VC Building.

Contractor shall identify all required tasks to relocate approximately 500 linear feet of existing underground electrical services and power transformer, currently located on a pad.

Note: A direct connection to the local power authority (WAPA) service aerial lines located on Tranberg Road is required (See Appendix A). As indicated, lines and poles are property of WAPA, the local power authority.

2. The Contractor is responsible for conducting all the required coordination and making all payments to the local power authority (WAPA); or to any other agency that has jurisdiction on the service line. The Contractor shall ensure all coordination and certifications dictated by the local power authority are met.

3. The Contractor shall install a new pole or poles as indicated by WAPA, the transmission lines, Sandy Point HQ/VC Building Rehabilitation Project Page 2 of 12 and all equipment, including a new pole mounted transformer. All WAPA requirements, regulations, and codes shall be met.

4. The Contractor shall place the required meter mount at the building’s nearest pole or by the location dictated by WAPA.

5. The Contractor shall coordinate with the U.S. Fish & Wildlife Service point of contact (POC) for the routing of the new underground section of the power line, from the last installed pole to the HQ/VC building’s service.

• A minimum of two manholes are required for the underground section of the power line.

• All underground work shall be conducted in accordance with the NEC and as per the local authority’s requirement.

6. Task shall include the disconnection and disposal of the pad mounted transformer. The Contractor shall coordinate with WAPA and perform all the required work safely. The underground service power line to the old transformer needs to be disconnected and isolated from a point indicated by WAPA. The old power lines connections to the HQ/VC building’s will be removed from the pad. Coordinate with staff prior to removal.

7. Upon completion of this task, the Contractor shall provide U.S. Fish & Wildlife Service three

(3) physical copies of the As-Builts, single line technical drawings, for the new service power lines, and any other document required by local agencies.

Task 2: Construction Services Task – Replace and Re-route Aerial Communication Service to the Facility – Base Bid

1. Task shall consist of a full evaluation of the existing aerial communications service line, approximately 500 linear feet. Contractor shall identify all required tasks to relocate and replace the communication service line.

2. Contractor shall replace and relocate the communication service line to the newly installed pole/s per Task 1. Project include the construction of communication pull box and underground conduits. Minimum of 2” PVC with one spare will be require.

3. The communication service line shall be routed from the building’s nearest pole located at the Tranberg Road to the new communications pull box and underground conduits into the HQ/VC building.

4. The Contractor is responsible for conducting all the required coordination and making all payments to the local authorities and service provider for the connection of the new communication service line to the nearest Tranberg Road pole. The Contractor is also responsible for coordination with the Sandy Point NWR staff prior to commencing this task.

5. The Contractor shall coordinate with the U.S. Fish & Wildlife Service point of contact (POC) for the routing of the new underground section of the communication service line, from the last installed pole/s to the HQ/VC building’s service.

• A minimum of two pull boxes are required for the underground section of the communication service line.

• A run of two 2” Schedule 40 PVC conduits installed between communication boxes shall be included.

Sandy Point HQ/VC Building Rehabilitation Project Page 3 of 12

• All underground work shall be conducted as per the local authorities’ and service provider’ requirements.

6. Upon completion of this task, the Contractor shall provide U.S. Fish & Wildlife Service three

(3) physical copies of the As-Builts, single line technical drawings, for the new communication service lines, and any other document required by local agencies.

Task 3: Construction Services Task – Perform Mold Evaluation/Detection – Base Bid

1. Task shall consist of conducting a mold evaluation and detection of the interior of the HQ/VC building (approximately 2,500 SF). Submit a Mold Detection Plan prior to performing the tests. The Plan should include type of tests, quantity, and areas where tests will be performed.

2. Upon receiving results of the mold evaluation/inspection, Contractor shall notify the U.S. Fish & Wildlife Service of all the results.

3. As part of their final report, Contractor shall identify and propose exacting mold remediation procedures and required treatments for all affected areas in accordance with all EPA and OSHA standards.

4. All work must be performed by an experienced and certified mold testing and mitigation company. The Contractor is responsible for providing certifications for all individuals conducting this task.

Task 4: Construction Services Task – Perform Mold Remediation – Option

1. Contractor will be responsible to conduct all mold remediation procedures and required treatments approved by U.S. Fish & Wildlife Service, upon review and discussion of Mold Evaluation/Detection Report.

2. Contractor shall also conduct any repair including painting of all damaged surfaces, if any during the mold remediation activities.

3. Contractor is responsible for the proper disposal of all contaminated materials.

4. All work must be performed by an experienced and certified mold mitigation company. The Contractor is responsible for providing certifications for all individuals conducting this task.

GENERAL NOTES:

A. The Contractor shall coordinate with the Refuge on appropriate stockpile locations for demolished and/or excess materials.

B. The Contractor is responsible for the security of materials. The Contractor shall provide secured areas deemed necessary for the protection of their materials.

C. The Contractor shall coordinate with refuge staff for safety and operational requirements.

D. PERIOD OF PERFORMANCE: 365 days

E. DEFINITIONS

1. Commissioning is the act of statically and dynamically testing the operation of equipment and building systems to ensure they operate as designed and can satisfactorily meet the

Sandy Point HQ/VC Building Rehabilitation Project Page 4 of 12 needs of the building throughout the entire range of operating conditions.

2. Construction is defined as, but not limited to, constructing (giving form by combining the parts), altering, repairing, adding to, subtracting from, improving, restoring, moving, wrecking or demolishing any building, highway, road, excavation or other structure, project, or improvement attached to real estate.

3. Contracting Officer (CO) is defined as a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the United States of America. The term includes certain authorized representatives of the Contracting Officer such as the Construction Specialist (CS), Contracting Officer's Representative (COR), Construction Representative (CR) and Site Representative (SR) acting within the limits of their authority as delegated by the Contracting Officer.

4. Day or Days shall mean calendar days unless otherwise specifically noted.

5. “Service” or “FWS” means United States Department of Interior, Fish and Wildlife Service, Region 4 (Southeast Region).

6. Government may also be referred to as the Owner, Contracting Officer, Contracting

Officer's Representative, the Service, or Fish and Wildlife Service (FWS).

7. Incident Rate (IR) is the number of recordable incidents resulting in days away from work for each 100 full-time employees per year, based on 2,000 hours worked per employee per year.

8. Local Authority Having Jurisdiction: Duly adopted local code authority, agency, or serving utility governing or serving the location of the project.

9. Management Plan: Contractor's project approach for planning, design, and construction and includes, at a minimum, but is not limited to the following:

• Schedule

• Project Staffing Plan

• Safety Plan

• Subcontracting Plan

• Organization Chart with Roles and Responsibilities

• QA/QC Plan

• Commissioning Plan

10. DOI “Sustainable Building Assessment and Compliance Tool Construction Checklist for

New Construction and Major Renovation Projects” and supporting documents. (This checklist will be furnished to the Contractor by the USFWS)

11. Notice to Proceed (NTP): There will be one NTP for this project issued by the Contracting Officer (CO) to initiate the construction phase. The NTP will identify any qualifications, limitations, or exceptions to the work.

12. Open Book Accounting is the right of the government to have free and open access to financial and accounting documents that the Contractor has associated with the project being completed.

13. Performance Specifications are specifications that state what the required results will be with measurable or observable criteria for verifying compliance.

14. Public Works is construction performed under a contract with a Federal, State, County, Sandy Point HQ/VC Building Rehabilitation Project Page 5 of 12

City, or other government entity.

15. Schedule is a chronological layout of the work to be performed prepared using commercially available scheduling software.

16. Subcontractor is any person or entity retained by the Contractor as an independent

Contractor to perform a portion of the Work and shall include material, labor and suppliers.

17. Sub-Subcontractor is any person or entity retained by a Subcontractor as an independent

Contractor to perform any portion of a Subcontractor's Work and shall include material, labor and suppliers.

18. Work is comprised of all permitting, construction and other services required by the Contract Documents, including procuring and furnishing all materials, equipment, services and labor reasonably inferable from the Contract Documents.

CONSTRUCTION SERVICES

A. GENERAL

1. Following the Issuance of the Construction NTP, the Contractor shall provide the following items to the COR at the Preconstruction Meeting for approval and amendment into the contract file:

a. A project schedule reflective of the critical path and other phases of the work.

b. A schedule of the planned site visits. The prime Contractor shall periodically, and at appropriate times, visit the site to inspect the construction. They shall prepare a site visit report for each visit and shall submit the reports to the COR within 5 calendar days after the visit. The reports shall include comments about overall quality and accuracy of the construction. The reports shall also note all deficiencies observed.

2. The Contractor shall possess and maintain, for the duration of this project, a state license as a general Contractor in the State the project is located, if required by the state.

3. The Contractor shall provide supervision, labor, materials, equipment, tools, construction equipment and machinery, inspection, testing, start-up, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.

4. The Contractor shall have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.

5. The Contractor shall perform all construction activities efficiently and with the requisite expertise, skill, and competence to satisfy the requirements of the Contract Documents. At all times exercise complete and exclusive control over the means, methods, sequences, and techniques of construction.

6. The Contractor shall utilize Subcontractors who are duly licensed and qualified to perform the Work consistent with the Contract Documents. Government may reasonably object to Contractor's selection of any Subcontractor.

7. The Contractor is responsible for quality control of its own work and work performed by its Subcontractors and their Sub-subcontractors. Provide and pay for the services of an independent construction materials testing laboratory accredited by an acceptable laboratory accreditation authority. Laboratory shall sample and test materials and perform

Sandy Point HQ/VC Building Rehabilitation Project Page 6 of 12 required special inspections. Laboratory shall be authorized to perform work in the state where project is located. Government may reasonably object to the Contractor’s selection of laboratory.

8. The Contractor shall assume responsibility for the proper performance of the Work of Subcontractors and all acts and omissions in connection with such performance. Nothing in the Contract Documents is intended or deemed to create any legal or contractual relationship between Government and any Subcontractor or Sub Subcontractor.

9. The Contractor shall coordinate the activities of all Subcontractors. If Government performs other work on the Project or at the Site with separate Contractors under Government's control, Contractor agrees to reasonably cooperate and coordinate its activities with those of such separate Contractors so that the Project can be completed in an orderly and coordinated manner without unreasonable disruption.

10. The Contractor shall minimize creation of construction, deconstruction, and demolition waste. Minimize factors that contribute to waste such as over-packaging, improper storage, ordering error, poor planning, breakage, mishandling, and contamination. Develop a Waste Management Plan to ensure that existing site and building materials are reused, salvaged, or recycled. Unless modified by the CO, divert 50%, minimum, of total project waste from landfills. Dispose of all materials not salvaged, reused, or recycled legally, off-site, in licensed disposal facilities.

11. During normal working hours (Monday to Friday from 7:00 am. to 3:30 pm.) throughout the duration of the contract, the Contractor shall promptly furnish information and provide reasonable facilities and access for obtaining information respecting: the character of the materials, condition of the work-in-progress, number of workers employed, their pay rate, time worked, inspection reports and test results from sampling and testing laboratories, and similar information.

12. Government buildings and other facilities are not available for storage of Contractor's materials, equipment, and tools except for designated staging areas. Government owned equipment is not available for Contractor's use to accomplish any Work.

13. Housing for workers and campsites are not available on site.

14. The Contractor shall furnish all temporary facilities and utilities needed including heat, light, power, water, telephone, sanitary facilities, job offices, material handling equipment, temporary construction aids, and storage enclosures. The Contractor is responsible for all temporary connections and disconnections.

15. Permits. It is the responsibility of the Contractor to obtain all permits and pay all permitting fees required for this project. The Contractor is responsible for providing permitting drawings, engineering data and other technical information required by the permitting authority.

B. COMMUNICATION

1. The FWS Project Manager must be in the information loop for Quality Assurance purposes.

a. RFI Process: Unless a more stringent protocol is accepted in the Management Plan, the Contractor shall utilize the following protocol:

(i) Utilize a RFI Form: All supplemental information and answers to questions shall be documented on Request for Information (RFI) forms. The Contractor may use any

Sandy Point HQ/VC Building Rehabilitation Project Page 7 of 12 format they choose for the Request for Information form but all shall be identified with the words “Request for Information” at the top of the form along with the Government Contract Number, Project Location (Sandy Point NWR) Project Title and the Contractor’s Name.

(ii) Numbering: RFI’s shall be sequentially numbered, logged and filed and shall be part of the Closeout Documents submitted to the Government.

(iii) FWS Concurrence: As RFI’s are generated and answered, submit copies to the COR for review within 2 business days for concurrence via email .pdf format. A non-response from the COR within 4 days of receipt of the RFI will signify concurrence with the RFI answer. If the RFI is sent on a Friday, then Saturday and Sunday do not count as business days.

(iv) RFI Files Onsite: The Site Superintendent shall maintain a file of RFI changes. This RFI file shall be subject to inspection by the FWS without advance notice.

b. Submittals: Unless a more stringent protocol is accepted in the Management Plan, the Contractor shall utilize the following protocol.

(i) Utilize a Submittal Register: Develop a submittal register and update this register as submittals and logged and processed.

(ii) Numbering: Submittals shall be sequentially numbered. A completed submittal register shall be submitted with the Project Closeout Documents.

(iii) FWS Concurrence: Provide the FWS Project Manager with (1) copy of the approved submittal and provide the FWS Construction Representative (1) copy of the approved submittal within (2) business days of the approval date.

(iv) Site Responsibility: The Contractor’s Site Superintendent shall maintain a file of approved submittals for reference purposes. This Submittal file shall be subject to inspection by the FWS without advance notice.

C. PAYMENT PROCEDURES

1. Measurement: No measurement of the work will be made unless unit prices are included in the project.

2. Schedule of Values: Prepare a Schedule of Values in the format of the American Institute of Architects (AIA) form number G702/703 Application and Certificate for Payment (or approved equivalent format). Submit a detailed Schedule of Values no less than 7 calendar days prior to the start of on-site construction work.

a. Payment Request Data: In addition to data required by the Contracting Officer: (1) Format the Schedule of Values to match the Schedule of Items and show sufficient additional detail to allow accurate calculation of monthly progress payments; and (2) Submit updated construction schedule identifying actual work complete.

D. PROJECT SAFETY

1. The Contractor shall have the ultimate responsibility for safety on the project site at all times, from issuance of the Notice to Proceed until final completion and acceptance of the project by the Contracting Officer. Ensure that all onsite activities, equipment, and facilities constructed by the Contractor, Subcontractor, or supplier conform fully to the standards of

Sandy Point HQ/VC Building Rehabilitation Project Page 8 of 12 the Department of Labor, Occupational Safety and Health Administration (OSHA) 29 CFR 1926 and 1910; and DOI and FWS policies. In addition, the Contractor shall adhere to all current Federal, State and local safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern.

2. The Contractor shall initiate and maintain, throughout the performance of this contract, an effective safety and health program that provides adequate policies, procedures, and practices to protect employees from, and allow them to recognize, job-related safety and health hazards. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections. Each employee (Contractor and Subcontractors) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.

3. The Contractor shall provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel. Where project work affects public roads, provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD) as published by the US Department of Transportation, Federal Highway Administration.

4. The Contractor shall provide Rollover Protection and Seat Belts.

E. Protections:

1. The Contractor shall comply with all applicable federal, state, and local environmental laws and regulations. This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, erosion control, surface runoff, and cultural resources.

2. The Contractor shall provide erosion control methods (such as watering dry soils) and appurtenances (such as silt fence) as necessary to prevent wind-borne dust and water-borne silt from leaving the immediate work area.

3. The Contractor shall immediately stop work if paleontological, archaeological or historical remains (including burials or skeletal material) are encountered, immediately stop the work and notify the Construction Representative, COR, or Contracting Officer. The Contracting Officer will notify the Regional Archaeologist so the provisions of 36 CFR 800.7 (Resource Discovered During Construction) and other relevant laws are followed. Work will cease in the immediate vicinity until permitted to resume by written order from the Contracting Officer. Work in other areas may proceed as approved by the Contracting Officer.

4. The Contractor shall protect adjacent vegetation, property, structures, and improvements from damage.

5. Heavy equipment operated on FWS roads and parking areas shall comply with highway-legal load limits unless explicitly approved otherwise. Prior to operations, the Contractor and contracting officer will document condition of roads and parking. The Contractor is responsible for repairs of damage to roads and parking caused by their own actions.

6. Clearing limits and working limits are as shown on the drawings and approved in the field.

Do not remove any trees without prior COR field review and approval. If no clearing limits are indicated, contact the COR for clarification. Coordinate with the local FWS staff to

Sandy Point HQ/VC Building Rehabilitation Project Page 9 of 12 select a construction staging area. Construction equipment and operations shall be contained within the work limits and staging areas.

F. Closeout Procedures

1. Training: The Contractor shall thoroughly familiarize the local FWS staff with the improvements and train them to be proficient in overall system operation and maintenance.

2. Tools and spare parts: The Contractor shall deliver to the project site all specialty tools, valve handles, fan belts, filters, spare parts, keys and similar devices such that the FWS staff is able to operate and maintain the work.

3. Maintenance Materials: The Contractor shall deliver maintenance materials to Station Manager, coordinate location of storage. (Provide consumable items in such quantities as needed for the first year of operation.)

4. Final Inspection: The Contractor shall submit a request in writing to the CO requesting the Final Inspection. Notify the COR at least 10 calendar days prior to the anticipated date of completion of all work. The COR will proceed with Final Inspection as promptly as practicable. The time required for such Final Inspection and for making any corrections as a result thereof shall be included in the contract performance time. The Contractor representative responsible for the work shall be present at the Final Inspection and shall submit a preliminary list of unfinished work prior to Final Inspection.

PROJECT CONTACTS:

Coordination at the Project Site shall be directed to:

TBD

Questions regarding the SOW and technical matters shall be directed to:

TBD

END OF STATEMENT OF WORK

Sandy Point HQ/VC Building Rehabilitation Project Page 10 of 12

I. Appendix A – Location Map and Project site

Figure 1 - Location Map of Sandy Point National Wildlife Refuge at Frederiksted, Virgin Islands

Figure 2 – HQ/VC Building Project Site Yellow arrow: Existing underground privately owned (WAPA) connection.

Orange Square: Existing location of underground transformer and eye level bare connections.

Orange arrow: Internet cable along the fence and ground.

Yellow Star: Nearest authority electric pole at Tranberg Road.

Sandy Point HQ/VC Building Rehabilitation Project Page 11 of 12

II. Appendix B – Current Site Photos

Figure 3 – HQ/VC Building

Figure 4 – Existing Pad Mounted Transformer

Sandy Point HQ/VC Building Rehabilitation Project Page 12 of 12

Figure 5 – Existing Pad Mounted Transformer – Closer look

I. Appendix A – Location Map and Project site
Figure 1 - Location Map of Sandy Point National Wildlife Refuge at Frederiksted, Virgin Islands
Figure 2 – HQ/VC Building Project Site
II. Appendix B – Current Site Photos
Figure 3 – HQ/VC Building
Figure 4 – Existing Pad Mounted Transformer
Figure 5 – Existing Pad Mounted Transformer – Closer look

File details come from the government source that posted it. Updated .