A04 SOW_Spec and Work Data_Malta BLM Road Grading.pdf
PDF 386 KB Posted
- Attached to
- Phillips County Montana Road Grading, BLM Malta Fi Federal contract opportunity
- Solicitation number
- 140L3121Q0006
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A06 Maps_Malta BLM Road Grading.pdf | ||
| B08 SubContractorInfoRequest.pdf | ||
| B08 ExperienceandPastPerformanceQuestion.pdf | ||
| B03 DOL Wage Determination.pdf | ||
| Sol_140L3121Q0006.pdf | ||
| B08 52.212-3 Offeror Rerepresentations and Certifications_Jan2021.pdf | ||
| B08 Value Schedule_BLM Malta Road Blading.pdf | ||
| B08 FAR 52.204-24_to be signed by quoter.pdf | ||
| B08 FAR 52.204-26_to be signed by quoter.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES DEPARTMENT OF INTERIOR
BUREAU OF LAND MANAGEMENT
2021 MALTA
BLM
ROAD GRADING
NORTH CENTRAL
DISTRICT
MALTA FIELD OFFICE
PHILLIPS COUNTY, MT
SPECIFICATIONS INDEX
MALTA BLM ROAD GRADING
DIVISION 1 - GENERAL REQUIREMENTS TITLE
01009 17301
GENERAL INFORMATION AND REQUIREMENTS
ROAD MAINTENANCE
RELATED DOCUMENTS TITLE
WORK DATA SHEET
MALTA BLM ROAD GRADING GENERAL INFORMATION AND REQUIREMENTS
01009-1
SECTION O I 009
GENERAL INFORMATION AND REQUIREMENTS
PART I: GENERAL
1.01 SUMMARY:
A. Description of Work: Furnish labor, equipment, supplies, and materials necessary to grade approximately 50.5 miles of roads of varying widths. This contract will consist of base plus option miles. The base miles consist of graveled roads to be graded in spring of 2021, while options will consist of three (3) separate dirt roads with average width of 18 feet, along with re-grading Dry Fork graveled road in the fall of 2021.
B. Location: Work under this Contract is in Phillips County, Montana. The work locations are shown on the drawings.
C. Work Data Sheet: Designates the type and quantity of work required at each project location.
1.02 REFERENCES:
A. Referenced Specifications/ Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/ standards referred to herein may be procured by the Contractor, from the following:
MUTCD Manual on Uniform Traffic Control Devices for Streets and Highways Superintendent of Documents Government Printing Office Washington, DC 20402
1.03 GRADING PROGRESS SCHEDULE/SEQUENCE OF OPERATIONS
A. Submit grading schedule for review at the Pre-Work meeting to illustrate the sequence and time allotted for each road in order to achieve completion of the work within the time limit specified in the Contract. The schedule shall include the following:
1 . Sequence of grading with start dates, duration, and finish dates.
2 . When requested, the Contractor shall submit an updated schedule within 3 working days.
01009-2
1.04 QUALITY ASSURANCE:
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
1.05 PROJECT/SITE CONDITIONS:
A. Access to the Work: Access to the work is by state, county, and BLM roads.
B. Environmental Considerations:
1 . The aesthetic values of the sites and surrounding areas are of prime importance. The Contractor shall take all care necessary to preserve all plant life and other natural features.
Travel of motor vehicles and heavy equipment shall be limited to existing roads and parking areas. Soil disturbance shall be limited as much as practical. No off-road travel is permitted except for minimal turn-around areas. Any surface damage outside the project areas shall be corrected by the Contractor at his expense.
2 . All vehicles and equipment shall be power washed before transportation to the sites, to prevent the spread of weed seeds.
PART 2: PRODUCTS
(There are no applicable requirements.)
PART 3: EXECUTION
3.01 PROJECT MEETINGS:
A. Pre-Work Conference:
I . A pre-work conference will be held prior to the start of work.
The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, specifications, payments, and administrative provisions of the Contract.
2. The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.
01009-3
3. The Contractor shall be prepared to summarize and explain procedures planned for the project and present the grading schedule (per 1.03 A).
B. Progress Meetings:
I. Meetings shall be held at the project site, or as determined by the Contracting Officer.
2. Meetings may be called by either the Contracting Officer or the Contractor.
shall state who should attend and include an agenda.
C. Final Inspection:
Request
I. Meeting shall be held at the project site, or as determined by the Contracting Officer.
2. The Contractor shall notify the Contracting Officer in writing at least 2 working days before the completion date so the Government can schedule final inspection.
3. The Contractor shall require the superintendent to be present during this inspection.
PART 4: MEASUREMENT AND PAYMENT
4.01 METHOD OF MEASUREMENT:
A. Units: The work described in this section will not be measured for payment.
4.02 BASIS OF PAYMENT:
A. Payment: No direct payment for the work described under this section will be made. The Contractor shall include consideration for this item in the bid price for other items of the Contract.
END OF SECTION
MALTA BLM ROAD GRADING
GENERAL INFORMATION AND REQUIREMENTS
01009-4 03/06/2020
MALTA BLM ROAD GRADING ROAD MAINTENANCE
17301-1
SECTION 17301
ROAD MAINTENANCE
PART 1: GENERAL
1.01 WORK INCLUDED:
A. Description: Work consists of blading and shaping existing roads to restore proper drainage. Work is described and scheduled on the Work Data Sheet.
1.02 DEFINITIONS
A. Reshaping the road surface requires cutting through the crust to remove potholes, washboard, and ruts. The material is redistributed across the roadway.
B. In case weather makes it questionable whether the work can be completed within the dates specified, the Contracting Officer may extend the Contract.
1.03 PROJECT CONDITIONS:
A. Public Safety and Signing: The Contractor shall exercise due caution and care when operating equipment to prevent undue conflict with public users of the road.
1 . A reflective "Slow Moving" vehicle symbol shall be attached to the rear of all appropriate equipment.
2 . Post warning signs on both ends of the section being worked on. Signs shall be moved as needed, so that a sign does not precede the machinery more than one mile. Signs shall be of the size, style, and color as required in the current edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways - MUTCD".
3 . Berms, windrows, or other obstructions shall not be left in the roadway overnight or on weekends.
1.04 QUALITY ASSURANCE:
A. Failure Criteria: Not limited to the following:
1 . Formation of pools of moisture on road surfaces. Site drainage shall be considered to be of prime importance.
2 . Flow of moisture toward, or entrapment against cattle guard and culvert foundations.
3 . Grading of material into cattle guard grids or pits, streams, rivers, or other waterways.
17301-2
PART 2: PROJECT/SITE CONDITIONS
2.01 TIMING
A. Maintenance/improvement shall begin this spring after the roads have thawed and dried to an appropriate moisture level. The Malta Field Office will notify the Contractor 7 days in advance of the date they wish blading operations to begin. These conditions usually occur between April 15 and June 15, however, work may be performed outside of these windows if there are adequate moisture conditions. All work will be performed in a timely manner when appropriate moisture is present for satisfactory performance.
B. The gravel road maintenance/improvements shall be done when adequate moisture is present for satisfactory performance. The Government shall instruct the Contractor when conditions are either to dry or too wet for grading. However, as a rule of thumb the following may be used to determine moisture readiness: if a half ton pickup leaves ruts of greater than 2" then the roads are too wet and if one cannot dig down 2" and find moisture then conditions are likely too dry.
C. The dirt road maintenance/ improvements shall be done when the material will shatter and spread evenly over the road surface. Any curling of the material off the moldboard will be an indication that the conditions are too wet to perform any maintenance activities.
PART 3: EXECUTION
3.01 INSTALLATION
A. Contractor will furnish a road grader with operator that has a minimum of 135 horsepower, 12-foot blade, and a scarifier. Where potholes, washboards, or ruts are over 3" deep, scarify to a minimum depth of 3-4 inches below the road surface, process the material, and reshape the surface.
B. Road width: Road segments shall be maintained to uniform widths. This does not mean that every road will be of uniform width from start to end, but that each segment of road will be essentially uniform.
C. Grades: Grades shall be maintained to the present grade between points, or uniform slopes where elevations change. Abrupt changes in slopes shall be rounded.
D. Blading: Blading of road surfaces will be done to minimize the loss of aggregate material. High blading, which is merely filling depressions with loose material, will not be acceptable: Berms or ridges shall not be left along the shoulders. During the blading operation, material shall not be graded into cattle guard pits. All loose rock larger than 6 inches shall be removed from the roadbed.
Road segments being bladed shall not be longer than 2 miles in length. Berms/windrows created during blading operations shall be removed prior to the end of each day. Edges or berms created at approaches shall be feathered and smoothed.
E. A uniform crown of 2% in straight sections where crown has been established prior to contract is desired. Contractor shall work towards creating crown in other sections.
Super elevation on curve sections is desired, including smooth transitions to a straight section crown.
17301-3
F. If excessive brush or weeds (vegetation in excess of 6” in length) have established themselves on the sides of the roadway within the specified width, it shall be mowed to a height not to exceed 6”. The method of mowing shall shatter the stems and leaves so berms containing this material will not be left on the side of the road. The maximum allowable height of roadside vegetation at the time of blading will be 6” typical all roads.
PART 4: MEASUREMENT AND PAYMENT
4.01 METHOD OF MEASUREMENT
A. Units: The work described in this section and on the Work Data Sheet will be measured and paid for by the linear mile (measured to the tenth of a mile) as measured along the center line of the roads.
4. 02 BASIS OF PAYMENT
A. Payment: The base bid will include only Dry Fork Road and the Camp Creek Campground Roads (late spring, early summer blading). Blading of Manning Coral, CK Ridge, and Pea Ridge Roads will be each an option awarded as funding, and moisture conditions allow (this will occur anytime from contract award thru fall). Fall blading of Dry Fork Road will be an option awarded as funding and moisture conditions allow. Prices and payment will be full compensation for the work described in this section. Payment will be made under:
PAY ITEM DESCRIPTION BASE OR OPTION BID UNIT
17301(1) Dry Fork Road (Spring) BASE BID Mile
17301(2) Camp Crk Campground roads (Spring) BASE BID Mile
17301(3) Manning Coral Road OPTION 1 BID Mile
17301(4) CK Ridge Road OPTION 2 BID Mile
17301(5) Pea Ridge Road OPTION 3 BID Mile
17301(6) Dry Fork Road (Fall) OPTION 4 BID Mile
END OF SECTION
17301-4
WORK DATA SHEET
BLM ROAD GRADING
SECTION 17301
NO.
PROJECT LENGTH
SIT E IN MILES
AVERAGE WIDTH
TN FEET (est.) SURFACE MATERIAL
1. Dry Fork Road 23.8 24 GRAVEL
2. Camp Crk Campground Road
3. Manning Coral Road
4. CK Ridge Road
5. Pea Ridge Road
1.2 7.1 9.4 9.0
GRAVEL
DIRT
DIRT
DIRT
TOTAL 25.0 miles of gravel roads
25.5 miles of dirt roads
Spring early summer blading of Dry Fork Road and Camp Creek Campground 25.0 miles
Blading during the period of performance of Manning Coral Rd, CK Ridge Rd, and Pea Ridge Road 0 to 25.5 miles
Fall Blading of Dry Fork Road 0 to 23.8 miles
MALTA BLM ROAD GRADING 1 WORK DATA
| 2020 MALTA BLM |
| NORTH CENTRAL DISTRICT |
| 3. The Contractor shall be prepared to summarize and explain procedures planned for the project and present the grading schedule (per 1.03 A). |
File details come from the government source that posted it. Updated .