This statement of work and related federal contract opportunity document outline requirements for replacement of potable water pipelines at the Red Rock Visitors Center located in Clark County, Nevada. The Bureau of Land Management seeks to award a firm fixed price contract to remove and replace an existing 4-inch diameter PVC potable water pipeline that is approximately 2,000 feet in length and a 1.5-inch diameter PVC potable water pipeline as identified in the statement of work, specifications, drawings, and related appendices. Work must be performed in accordance with the provided documents and includes pipeline construction, compliance with environmental and permitting requirements, and maintenance of transplanted plant life. The pre-bid site visit is scheduled for August 24, 2021 and the Bureau of Land Management intends to make a single award under FAR Part 15.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RED ROCK VISTORS CENTER

AND FEE STATION

POTABLE WATER SUPPLY

PIPELINE REPLACEMENTS

BUREAU OF LAND MANGEMENT

SATEMENT

OF

WORK

Table of Contents

SECTION A – PROJECT DETAILS

A1.0 Project Scope

A2.0 Construction Documents

A3.0 Geotechnical Report

A4.0 Important Locations

A5.0 Existing Pipeline Operations

A6.0 Existing Three Phase Power

A7.0 Traffic Control and Laydown Area Plans

A8.0 Stormwater Discharge Permit

A9.0 Dust Control Permit

A10.0 As-Built Drawings

A11.0 Fire Safety Concerns

A12.0 Government Furnished Items/Materials

A13.0 Inspection and Acceptance

A14.0 Use of Premises

A15.0 Occupancy Requirements

A16.0 Work Restrictions

A17.0 COTR and COR Nominations

A18.0 Contract Period of Performance

SECTION B – NATIONAL ENVIRONMENTAL POLICY ACT (PROJECT)

B1.0 Nesting Birds

B2.0 Desert Tortoise

B3.0 Landscape Preservation

B4.0 Temporary Roads

B5.0 Transplanted Flora

Table of Contents (continued)

APPENDICES

Appendix A – RRCNCA Visitor's Center and Fee Station Potable Water Pipelines - Construction Plans

Appendix B – RRCNCA Visitor's Center and Fee Station Potable Water Pipelines - Construction Specifications

Appendix C – NDEP Project Approval Letter

Appendix D – RRCNCA Visitor's Center and Fee Station Potable Waterline Replacement - BLM Decision Record

Appendix E – RRCNCA Visitor's Center and Fee Station Potable Water Pipelines Replacement - NEPA Terms

Appendix F – RRCNCA Visitor's Center and Fee Station Potable Water Pipelines - Geotechnical Report

SECTION A – PROJECT DETAILS

A1.0 Project Scope

The goal of this project is to construct a 4-inch diameter pvc potable water pipeline that is approximately 2,000 feet in length and a 1.5-inch diameter pvc potable water pipeline that is approximately 1,500 feet in length.

Both waterlines originate near the Red Rock Canyon National Conservation Area (RRCNCA) potable water supply well. The 4-inch diameter pipeline terminates approximately 130-feet south of the RRCNCA above ground potable water storage tank.

The 1.5-inch diameter pipeline terminates approximately 10-feet from the northwest side of RRCNCA fee station building.

The pipelines will be constructed to replace an existing 4-inch diameter pipeline that is currently co-located with a 3-phase power line in the same trench and a 1.5-inch diameter pipeline that is in a substandard condition.

A2.0 Construction Documents

Construction of the pipeline shall be performed in accordance with the documents listed below and this Statement of Work.

2.1 Project Improvement Plans - Red Rock Canyon Visitors Center and Fee Area Potable Water Supply Pipeline Replacement.

2.2 Project Specifications - Red Rock Canyon Visitors Center and Fee Area Potable Water Supply Pipeline Replacement.

2.3 NDEP Project Approval Letter (NV0005011) / (CL-0006588-20)A.

2.4 U.S. Department of the Interior – Bureau of Land Management Decision Record Red Rock Visitor's Center Well Head and Waterline Replacement – DOI-BLM-

NV-S020-2015-0009-EA.

2.5 Terms and Conditions for Red Rock Visitor Center Well Head and Waterline Replacement – DOI-BLM-NV-S020-2015-0009-EA.

A3.0 Geotechnical Report

A geotechnical report was prepared for BLM in 2015 and is included in the bidding documents. The report covers the northern area of the 4-inch diameter pipeline alignment. The southern 1,400-feet of the 4-inch pipeline and the entire alignment of the 1.5-inch pipeline have not been investigated. Caliche was identified in three borings at 3 to 4-feet below ground surface. Caliche may be present in work areas not explored in the geotechnical report at the pipeline burial depths indicated on the plans. However, its likely presence is expected to be low.

A4.0 Important Locations

The potable water supply well, fee station and visitor center are located near the approximate longitudes and latitudes listed below:

Water Well: Lat: 36.1304 / Long: -115.4278;

Fee Station: Lat: 36.1323 / Long: -115.4238;

Potable Water Storage Tank: Lat: 36.1356 / Long: -115.4275;

4-inch Water Line Tie-In: Lat: 36.13533 / Long: -115.4275;

Power Line Junction Box: Lat: 36.13399 / Long: -115.4279.

A5.0 Existing Pipeline Operations

Both the existing 4.0 inch diameter pipeline that runs from the well to the Visitor Center and the 1.5-inch diameter pipeline that runs from the well to the Fee Station shall remain in service during construction of the new pipelines. Contractor shall provide Government a one week advance notice of the date when the existing pipelines need to be shutdown so connection to the new pipelines can be made.

A6.0 Existing Three Phase Power

A three phase power line is co-located with the existing 4-inch diameter potable water pipeline. The Government has not physically located the power line but the design plans assume that it runs in a straight line between the transformer at the well house and the electrical junction box located near Latitude: 36.13398 / Longitude: -115.42801.

Contractor shall immediately notify Government if the power line differs from indicated alignment.

A7.0 Traffic Control and Laydown Area Plans

Contractor to submit traffic control plan for review and approval by Government. Traffic control plan must be approved by Government prior to initiating any work on site.

Equipment and material laydown areas have been provided by the Government.

Contractor to submit laydown plan to Government for review and approval prior to initiating any work on site. The traffic control plan and laydown plan may be combined into a single document.

A8.0 Stormwater Discharge Permit

Contractor is responsible for obtaining a Nevada Division of Environmental Protection stormwater discharge permit prior to commencing any construction activities. Contractor is responsible for all permit fees.

A9.0 Dust Control Permit

Contractor is responsible for preparing and processing the required plans and applications, and pay all respective fees related to obtaining a Clark County Dust Control Operating Permit.

A10.0 As-Built Drawings

The Contractor shall provide the Government one full set of As-Built drawings in the following formats:

a) Half size drawings on high quality paper;

b) Electronic AutoCAD 2015 or later format; and

c) Adobe pdf file.

Contractor to provide Government electronic files on Flash Drive.

If the future 4-inch pipeline alignment must change due to the location of the three phase power line or other reasons, the Contractor shall have Record Drawings prepared, sealed and signed by a Nevada Registered Civil Engineer. The Record Drawings shall be provided to the Government in the same formats listed for the as-built drawings.

The project pipeline design plans were prepared by the Jacobs Engineering Las Vegas office.

A11.0 Fire Safety Concerns

The work sites are in a dry rural desert environment. Prior to construction, the Contractor shall coordinate with the BLM Southern Nevada District Fire Management Officer at 4701 N. Torrey Pines Drive, Las Vegas, NV 89130; phone 702- 515-5135, to outline fire safety requirements at the work site.

The Contractor shall take all reasonable precautions to prevent and suppress fires. In case of a fire, the Contractor shall immediately notify the nearest emergency response center (911) and the Las Vegas Interagency Communication Center at 702-515-5300. If needed, the Contractor shall require his/her employees and those of any subcontractor to work under BLM Fire Management Officials in fire-control and suppression efforts.

Contractor shall be required to verify all materials are within specifications before placing. The contractor shall be responsible for any damages or spills resulting from the delivery of materials to the site. Surplus materials delivered to the site but not used shall not be permitted to be dumped or temporarily stored onsite, unless a container specifically designated for that purpose is in place prior to delivery and approved by the Contracting Officer. Contractor will be responsible for the cleanup and restoration of any areas damaged as the result of improper waste disposal, including damage caused by material suppliers.

A12.0 Government Furnished Items/Materials

The Government assumes NO LIABILITY for the accuracy or correctness of any information or data provided to the Contractor. Additionally, the Government assumes no liability for errors or omissions the documents provided may contain. The Contractor is responsible for verifying the accuracy of the data provided prior to submitting their proposal.

A13.0 Inspection and Acceptance

Regular construction inspections will be performed by a qualified Government inspector to ensure compliance with approved design drawings, specifications and this statement of work. The Contractor will assume liability for all work not performed per the approved design drawings and specifications. The contractor will remove, replace or repair any work that is not in conformance with the approved drawings, specifications and this statement of work at no additional cost to the Government.

A14.0 Use of Premises

14.1 Contractor shall have access of the premises within the designated work site to perform all specified work during the construction period of performance.

Contractor’s use of the premises is limited only by Government right to perform work or to retain other contractors on portions of the project.

14.2 Schedule operations so that Work is conducted during the hours between 7:00am and 4:00pm, Monday through Friday.

14.3 Limit use of the premises to work in areas indicated. Do not disturb portions of the Project site beyond areas in which the Work is indicated.

14.4 Government Occupancy: Allow for Government occupancy of Project site.

Government personnel will be continuously occupying areas near portions of the Work area. Conduct work in a manner that will minimize needs for disruption of normal Government operations. Secure Government’s written approval of activities that will impact normal Government operations to avoid delays in construction.

A15.0 Occupancy Requirements

15.1 Full Government Occupancy: Government will occupy site and existing nearby buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage.

Perform the Work so as not to interfere with Government day-to-day operations.

Maintain existing exits, unless otherwise indicated.

15.2 Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.

A16.0 Work Restrictions

16.1 On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00am to 4:00pm, Monday through Friday, except when otherwise indicated.

a) Weekend Hours: No weekend hours unless requested to and approved by the Government at least 72 hours in advance.

b) Early Morning Hours: No early morning hours unless requested to and approved by the Government at least 72 hours in advance.

c) Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent form the Government. Submit requests 72 hours in advance of the work to the government for approval.

d) No signs or advertisements (except those specified) shall be displayed on the construction site or withing the premises unless approved by the Government.

e) Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1) Notify Government not less than three days in advance of proposed utility interruptions.

2) Do not proceed with utility interruptions without Governments written permission.

3) Hours of Utility Shutdowns: should a utility shutdown be deemed necessary in order to perform an evaluation, coordinate hours with the Government. Hours for shutdowns will be evaluated on a case by case basis.

A17.0 COTR and COR Nominations

18.1 COTR and/or COR Nomination: Paul Lohman, P.E.

18.2 Project Manager/Liaison: Paul Lohman, P.E.

A18.0 Contract Period of Performance

The estimated period of performance is 150 calendar days.

SECTION B – NATIONAL ENVIRONMENTAL POLICY ACT (PROJECT)

B1.0 Nesting Birds

The nesting bird season is from February 15 thru August. If the project takes place during this time period, the Contractor shall provide a person with knowledge of nesting birds to be onsite and monitoring the construction area for the presence of nesting birds.

That person will need to continuously monitor for nesting birds on a daily basis during the project work hours.

B2.0 Desert Tortoise

Contractor shall comply with the following special stipulations developed to protect the desert tortoise.

a) Should a desert tortoise enter the area of activity, all activity shall cease until the animal has left the area of its own accord.

b) Workers shall be instructed to check underneath all vehicles before moving them as tortoises often seek shade underneath parked vehicles during the active season.

c) Workers will be provided educational information on the desert tortoise including their legal protection and consequences for Endangered Species Act violations.

2.1 Tortoise Monitor: Contractor to provide a desert tortoise monitor for the project. Before any mobilization or construction activities commence, the contractor shall submit to BLM for review and approval the resume of the monitor that will be used for the project. If the project takes place during the tortoise active season (March thru October), then an Authorized Desert Tortoise Biologist will have to be on site to monitor the project. The Authorized Desert Tortoise Biologist will need to submit their resume to United States Fish and Wildlife Service for review and approval prior to their engaging in this project service.

2.2 Tortoise Fencing: Install and maintain approved temporary tortoise-proof fencing around open excavations in accordance with section 2.2 thru 2.2.4 of this Statement of Work.

2.2.1 Fencing Installation: Install fencing all at one time or in phases along portions of the entire construction site to match construction activity and to encompass active construction area including staging areas and access roads.

Install fencing without ground disturbance outside of the fence line.

2.2.2 Approved Temporary Tortoise Fencing: Approved temporary tortoise fencing consists of 1 by 2-inch mesh, 14-gauge galvanized wire fence, 3-inches wide. Extend the top 18 to 24-inches of fence, with inch opening of mesh positioned vertically, above ground and firmly attached to the Site security chain link fence or 12 gauge galvanized smooth wire. Attach fence mesh to fence posts with 12 gauge galvanized smooth wire. Use hog rings at intervals of 1 foot to attach the 1 by 2-inch mesh to fence or wire. The bottom 12 inches of fence must be either buried vertically or bent at a right angle towards the outside of the work area and covered with 3 to 6-inches of dirt, rocks, or gravel from surrounding area. Place fence posts at appropriate intervals no more than 8 to 10 feet) for visibility to not pose a safety hazard to humans. Provide adequate fence grounding to prevent electric shock to workers and other Project personnel.

2.2.3 Fence Entrance and Exits: Install gates at appropriate access points with no more than 1inch ground clearance to deter ingress by desert tortoises. If necessary, install a concrete foundation under the gate to prevent erosion and maintain less than inch of clearance between gate and ground. Keep gates closed when not actively in use to prevent tortoise entry.

In place of or in addition to gates, install tortoise proof guards.

Acceptable design consists of two parallel steel I-beams, spaced 8-inches apart. A minimum 8-inch gap will prevent tortoise entry. A trench between the I-beams at a depth of 8 to12-inches with bedding material (soft soil or sand) will catch a tortoise that falls through the gap.

2.2.4 Integrity of Tortoise Fence: Maintain integrity of tortoise proof fence throughout project construction. If the fence is damaged during work, notify Government and stop work in the area of the damaged fence until fence is repaired to a standard acceptable to Government. Regular maintenance of the fence includes removal of trash and sediment accumulations, repair of any damage, and restoration of zero clearance between ground and bottom of the fence as needed.

2.3 Inspections by Contractors Biologist: Prior to any surface disturbance and after the fence route has been flagged, Contractors biologist shall conduct a desert tortoise clearance of the flagged area before the fence is installed. The Contractors biologist shall inspect and approve completion of the tortoise-proof fencing.

Contractors biologist shall conduct desert tortoise clearance survey of area(s) enclosed by fence and along exterior perimeter before Contractor conducts any initial ground disturbing activities, including but not limited to clearing and grubbing, blading, grading, or placement of equipment inside fenced area.

B3.0 Landscape Preservation

Preserve natural landscape and protect existing vegetation not authorized to be removed. Conduct operations to prevent injury to natural surroundings in vicinity of

Work. Move crews and equipment within rights-of-way and over routes provided for access to Work in manner to prevent damage to grazing land, crops, or property.

3.1 Protect Vegetation: Protect vegetation from damage or injury caused by construction operations, personnel, or equipment by use of protective barriers or other methods approved by Government. Provide access routes as approved by Government.

3.2 Tree Anchorages: Do not use trees for anchorages.

3.3 Damaged Vegetation: Repair or treat damaged vegetation; replace trees or shrubs as directed by Government. Contractor shall be responsible for injuries to vegetation caused by Contractor operations, personnel, or equipment. Repair or treat damaged vegetation, without delay as recommended by and under direction of experienced horticulturalist or licensed tree surgeon.

B4.0 Temporary Roads

Restore temporary roads to original landscape contours and make impassable to vehicular traffic when no longer required. Scarify and regrade Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will provide proper drainage and prevent erosion.

B5.0 Transplanted Flora

This work consists of transplanting cacti and yucca which includes salvaging protected/sensitive cacti and yucca species within the area of the project limits, transporting, stockpiling, replanting and maintenance which includes temporary protection fences, barriers, and signs as required for protection.

5.1 Qualifications: Company shall have minimum of 5 years of experience working regularly with salvage of native and protected/sensitive plant species including collection, transplanting, non- irrigated revegetation and maintenance operations within the Mojave Desert. Prior to the preconstruction conference, the company shall submit a detailed description of a minimum of 5 previous native plant salvage/revegetation projects (with reference contact information) where this work was successfully completed by members of this company. The work individuals completed while with a different company will not be considered.

5.2 Action Submittals: All submitted deliverables must be approved by the Government. The following submittal items will be required at the Preliminary Review Meeting, Pre-Final Review Meeting, and Final Review and Submittal:

a. Work plan for cactus survey;

b. Before and after photos of cacti and yucca;

c. Work plan for transplanting;

d. Schedule for cactus and yucca survey and transplanting;

e. Shipping permit from BLM (if transfer offsite is required); and

f. Maintenance plan.

5.3 Survey and Evaluation of Cacti and Yucca: Prior to any disturbance, the project site must be surveyed for cacti and yucca by a qualified biologist paid for by the contractor. The surveyor must provide a list of numbers of cacti and yucca by species. If hundreds of plants are known to occur, an estimate may be provided based on counting plants within a specific area (e.g., 0.12 mile) and then calculating the entire area to be disturbed. A copy of the evaluation shall be forwarded to the BLM forestry staff.

5.4 Salvaging Cacti and Yucca: Prior to any disturbance, cacti and yucca that will be impacted will be appropriately salvaged. The following pants require salvaging:

a) Joshua trees;

b) barrel cactus;

c) cottontop cactus;

d) hedgehog cactus;

e) all yucca over 1-foot tall;

f) all other cacti over 1-foot tall or 1-foot wide including prickly pear and cholla; and

g) cacti and yucca less than 1-foot tall and cholla cacti do not need to be salvaged.

Cooler months are best for salvage, but removal can occur at any time of the year.

Cacti and yucca are very shallow rooted and thus easy to remove. Cacti and yucca do not require being planted immediately. One or two weeks of drying time will decrease the chance for root infection, especially if the roots become damaged during digging.

Yuccas do require immediate transplanting. Joshua trees are sensitive to being moved.

Barrels and Joshua trees require that the north side of the plant be identified and marked, using flagging or other marking. These two species need to be planted in the same orientation as they were originally growing in to survive. Other succulents don't seem to care about orientation. A front end loader or other heavy equipment is necessary for the larger plants. Clonal (clumped) yucca can be salvaged as separate plants with great success (each has its own root system).

5.5 Compliance: The Government will evaluate whether proper salvage has been done for the project. Cost recovery charges for lost or destroyed cacti and yucca will be applied at fair market value. In addition, staff time and vehicle costs for non-compliance will be added.

5.6 Establishment Period: During the plant establishment period, a minimum of 80 percent survival rate per plant species shall be maintained at the end of 1 year. Payment will be directly tied to the survival rate. A payment of 100 percent will be made for a survival rate of 80 percent or greater. Payment will be reduced by 5 percent for each 5 percent drop-in survival rate.

5.7 Transplanting Flora: The work of transplant flora shall consist of salvaging cacti and yucca within the area of the Project limits, transporting, stockpiling and replanting salvaged cactus and yucca in approved area(s). Salvaged cacti and yucca are the property of the Government.

a) Replant each temporarily removed cacti and yucca only after construction activities are completed and applicable grading is completed in its vicinity.

Replant cacti and yucca in locations shown or approved.

b) Excavate cactus and remove in a manner that preserves the root system.

c) Transport cactus to designated nursery locations(s) minimizing damage to any of the roots, stems or any part of the plants.

d) Replant cacti and yucca.

e) Maintain transplanted materials.

5.8 Salvage/Extraction: Coordinate all plant salvage/extraction work with the Government. Reuse top 4-inches of native soil which has been stockpiled.

a) Do not begin cactus salvage activities until areas are enclosed with tortoise proof fencing and cleared of desert tortoise.

b) When not planted in new location directly, transfer the salvaged plants to prepared trenches, 3-foot wide, 12 inches deep of any desired length. If using multiple, parallel trenches, trenches shall be spaced far enough apart to allow heavy equipment access to each trench. Thoroughly water trenches prior to transplanting material.

c) Plant stockpiled plants in trench with native soil. Properly tamp down and compact all soil around roots of plant to remove air pockets. After planting, thoroughly water one time, be sure to remove or minimize any air pockets and assure proper soil compaction.

d) For water harvesting purposes provide depressed basins with channel formed on the uphill/grade side to bring water to the transplanted cacti and yucca. The center of basin at plant base shall be slightly mounded so that water drains away from the base of the plant into the depression.

e) Plants, especially the cacti and yucca shall be planted at the same depth that they were growing in their native environment. Plants shall be planted so that they are slightly mounded and water drains away from the base of the plant, but into the depression. Water should not be allowed to persist or stand at the base of the plant. All plants shall be regularly monitored (every other day for the first 2 weeks, every 15th day thereafter) for soil moisture and thoroughly watered before "dry". In addition, regular watering is to be scheduled at a minimum of every 30 days after replanting plants in stockpiling trenches.

f) Support cacti and yucca immediately after planting to maintain plumb position if necessary. Do not prune cacti and yucca. All cacti and yucca that expire shall be left in place as habitat and mulch. Protect transplant areas against damage for duration of maintenance period.

g) Guying and staking material shall follow standard practice for cacti and yucca.

h) Pesticide and herbicide will not be allowed on project unless specifically approved by BLM during the maintenance period. Fertilizer will not be allowed on transplanted cacti or yucca.

5.9 Watering: There is no irrigation system. All plants shall be watered through the end of the plant establishment period using clean potable water from a portable or temporary source to hand apply water to plants. Individually water all plants. Manually check plants at a minimum of every 2 weeks with a 9-inch spoil moisture probe. If readings indicate "dry" soil conditions, adjust watering frequency as needed. The Contractor shall document probe results and locations where measurements were taken with description of actions taken on a spreadsheet report. Submit probe report every 2 weeks with the water report to the Government. Watering frequency shall be based on probe reading results.

Furnish a watering schedule spreadsheet for the plant establishment period that includes the date and time of day work to be performed. Submit schedule for review and approval prior to the plant establishment period. During plant establishment period, submit a signed watering report every 2 weeks to the Government.

5.10 Maintenance: Commence to maintain plant life immediately after transplanting.

The plant establishment maintained period shall run for a period of 12 months beginning from the date of Substantial Completion.

Maintain cacti and yucca as follows:

a) Cacti and yucca shall be maintained in a manner to retain the vigor and appearance of native plants of the same species growing nearby.

b) Maintain the cacti and yucca species in a manner to avoid rot and so they do not appear wrinkled or shriveled.

c) Maintain by watering, cultivating and weeding as required for healthy growth. Restore planting saucers.

d) Tighten and repair stake and guy support and reset to poorer grades or vertical position as required.

e) Spray as required and approved by the Government to keep cacti free of insects and disease.

f) Remove guys, stakes, and other supports at end of maintenance service.

SOW - Working Copy - April 26 2021
Appendix F – RRCNCA Visitor's Center and Fee Station Potable Water Pipelines - Geotechnical Report
SECTION A – PROJECT DETAILS
A3.0 Geotechnical Report
A4.0 Important Locations
A5.0 Existing Pipeline Operations
A6.0 Existing Three Phase Power
A7.0 Traffic Control and Laydown Area Plans
A8.0 Stormwater Discharge Permit
A9.0 Dust Control Permit
A10.0 As-Built Drawings
A11.0 Fire Safety Concerns
A14.0 Use of Premises
A19.0 Contract Period of Performance
SECTION B – NATIONAL ENVIRONMENTAL POLICY ACT (PROJECT)
B1.0 Nesting Birds
B2.0 Desert Tortoise
B3.0 Landscape Preservation
B4.0 Temporary Roads
B5.0 Transplanted Flora
APPENDIX A
20.10.16_RRNCA Waterline_Bid Set_Signed_R1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
Sheets and Views
Layout1
APPENDIX B
20.10.16_RRNCA Waterline_Bid_Specs_Signed
United State Department of the Interior, Bureau of Land Management, Red Rock Canyon, Visitors Center and Fee Area, Potable Water Supply Pipeline Replacement
00_01_07A_Seals_Page
00_01_10A_Table_of_Contents
SPECIFICATIONS
01100 BLM Rev5 sf - summary
01310 BLM Rev3 sf - project management and coordination
01320 BLM Rev2 sf - construction progress documentation
01400 BLM Rev2 sf - quality requirements
01420 BLM Rev2 sf - references
01500 BLM Rev2 sf - temporary facilities and controls
01600 BLM Rev2 sf - product requirements
01700 BLM Rev2 sf - execution requirements
31_23_16B_Excavation
31_23_23.15B_Trench_Backfill
32_12_16B_Asphalt_Paving
33_05_01B_Conveyance_Piping_General
33_05_01.09B_Polyvinyl_Chloride_Pressure_Pipe_and_Fittings
33_12_16B_Water_Utility_Distribution_Valves
33_13_00B_Disinfection_of_Water_Utility_Distribution_Facilities
DRAWINGS (BOUND SEPARATELY)
APPENDIX C
5011_E_20201124_CL-0006588-20_Approval Ltr
APPENDIX D
Decision Record signed 3.31.16
Decision Record
Decision
Selected Action
Description
Mitigation Measures
Finding of No Significant Impact
Alternatives Considered
Decision Rationale
Administrative Remedies