A04_-_SOW_-_Requirements_for_Cubicle_Changes_at_NCPTT.docx
DOCX document 14 KB Posted
- Attached to
- Raising cubicle height NCPTT Federal contract opportunity
- Solicitation number
- 140P2121Q0075
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A04_-_images.zip | ZIP file | |
| A04_-_floorplan_v2.pdf | ||
| Sol_140P2121Q0075.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Requirements for cubicle upgrades at NCPTT In NCPTT’s headquarters building there are 10 cubicles that will be raised in height by adding a 15” stacker to the 64” height Knoll Ref that exists.
Stackers will be both glass and cloth. Cloth stackers will be used where the cubicle wall is next to a building wall, and those cloth stackers will match existing cloth stackers. Glass stackers will be used everywhere else to allow natural light in the space.
79” doors will be installed in the openings in each of the cubicles being modified. These doors will match the doors already installed in 4 end cubicles that have been previously raised to the ceiling.
Approximate cubicle dimensions are:
1) 9’ X 6’
2) 9’ X 6’
3) 9’ X 9’
4) 9’X 9’
5) 12’ X 9’
6) 9’ X 9’
7) 9’X 9’
8) 9’ X 9’
9) 9’ X 9’
10) 6.5 X 8’ Please see the attached floorplan for locations of cubicles and doors.
Contractor will remove all trash generated by the project.