REFINISH FIRST FLOOR ADMIN AREA OF HQ
Solicitation number
140P5224R0033
Issued by

About this file

This document is a Statement of Work (SOW) for the Refinish 1st Floor Admin Headquarters project at the Natchez National Historical Park in Natchez, Mississippi. The project scope includes the removal and refinishing of approximately 4,300 square feet of flooring, wall base, and wall paint in the ground level administrative wing of the Natchez Visitor Reception Center. Key requirements include removing existing carpet flooring, preparing the concrete subsurface for new luxury vinyl tile (LVT) flooring, removing existing wall base, patching and painting walls, and installing new 4-inch rubber cove base. The work must be completed within 90 calendar days after contract award. The solicitation, Solicitation Number 140P5224R0033, is a combined synopsis/solicitation for commercial items with a NAICS code of 238330. The selection will be based on an evaluation of cost, technical approach, and relevant experience, with a recommended site visit scheduled for August 15th. Davis-Bacon prevailing wages for Adams County, Mississippi apply.

View the file

Other files

File Type Posted
B04_Wages_Adams_County.pdf PDF
Sol_140P5224R0033.pdf PDF
A05_COMBINED_SPECIFICATIONS.pdf PDF
Solicitation_Clauses.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 1

STATEMENT OF WORK

REFINISH 1ST FLOOR ADMIN HEADQUARTERS

NATCHEZ NATIONAL HISTORICAL PARK

NATCHEZ, MISSISSIPPI

PROJECT INTRODUCTION

Refinish 1st Floor Admin Headquarters Natchez National Historical Park 640 S Canal Street, Natchez, MS 39120

1.1 Scope

In accordance with the terms and conditions of the Contract, the Contractor shall perform the work of this Statement of Work (SOW) for the National Park Service (NPS) as described below.

The work of this SOW shall be performed in accordance with the Denver Service Center (DSC) Construction Workflow Website https://www.nps.gov/dscw/construction.htm. as applicable. In addition there is an “Information” link which provides additional requirements that shall be utilized for completing the work of this contract:

Federal Acquisition Regulations Forms/Templates/Samples/Guidelines Laws/Regulations/Policies/Guidance Quality Assurance Guideline

In case of conflict between this SOW and the DSC Construction Workflow Website, https://www.nps.gov/dscw/construction.htm, this SOW will take precedence over and will be used in lieu of such conflicting portions.

The Contractor remains fully responsible for determining if the standards or provisions cited on the DSC Construction Workflow Website, https://www.nps.gov/dscw/construction.htm, have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO) requesting direction.

1.2 Location

The work as described in the Project Requirements Section of this Statement of Work is located at:

Natchez National Historical Park - Natchez Visitor Reception Center, ground level administrative wing. 640 S Canal Street, Natchez, Mississippi 39120

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 2

1.3 Description

This project includes all equipment, tools, labor, material, and supervision for the selective removal and refinishing of flooring, wall base and wall paint located on the +/- 4,300 sq.ft. ground floor admin wing at the Natchez National Historical Park, Natchez, Mississippi. See Fig. A

Fig. A

1.4 Schedule

The work in this SOW shall be completed in accordance with the following schedule:

Construction:

Construction completed no later than __90__ calendar days after award of the contract.

1.5 NPS Points of Contact:

a) Contracting Officer: TBD West Major Acquisition Buying Office (MABO) Address Address Telephone:

E-mail:

b) Project Manager: Jason Steed

NPS, Interior Region 2 – South Atlantic-Gulf, Facility Support Division 640 South Canal Street Natchez, MS 39120 Telephone: 470-456-9879 E-mail: jason_steed@nps.gov

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 3

c) Park Superintendent: Kathleen Bond NPS, Natchez National Historical Park 640 South Canal Street Natchez, MS 39120 Telephone: 601-442-7049, 13 E-mail: Kathleen_bond@nps.gov

c) Park Facility Manager: Daryl Beck

NPS, Natchez National Historical Park 640 South Canal Street Natchez, MS 39120 Telephone: 769-319-2431 E-mail: Daryl_Beck@nps.gov

PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 PROJECT SUMMARY AND SCOPE OF WORK REQUIREMENTS

The project will refinish the +/- 4,300 sq. ft. ground level floor of the administrative wing of the Natchez Visitor Reception Center located at 640 S Canal Street, Natchez, Mississippi 39120. Work to include removal of all existing carpet flooring (approximately 2,800 sq. ft.), preparation of concrete subsurface for installation of new, government-furnished, luxury vinyl tile (LVT) flooring, removal of existing rubber wall base, patching of existing gypsum board as needed, preparation and application of new wall paint, and installation of approximately 1,000 linear feet of new 4” rubber cove base per specification requirements and/or manufacturers’ requirements and instructions. All existing vinyl composite tile (VCT) / vinyl plank flooring (VPF) flooring will remain in place.

Existing Layout / Floor Plan 1st Level Administration Wing

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 4

Scope of Work Requirements

Remove all existing carpet flooring throughout ground level wing.

Remove all existing wall base throughout area.

Remove and store all wall mounted items such as signage, cover plates, picture hangers, etc.

Prepare wall surface for new finish, which includes cleaning, patching / repair, sanding, touch-up, etc. per attached specifications.

Prime and paint wall per specifications Prepare floor surface for installation of new luxury vinyl tile per attached manufacturer’s instructions.

Provide edge/transition strips as required.

Provide / install new 4” rubber cove base.

Provide final area cleanup.

See floor plan for existing layout.

Contractor to verify all existing conditions and quantities/measurements prior to bidding.

Note: Pre-bid site visits will be allowed upon advanced request through Contracting Officer

2.1.2 Progress Payments

Progress payments during construction will be based on the percentage of work completed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the % complete shall be initiated by the Contractor under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Contractor shall make the computations for payment based on the governments verification of work completed and in place for any periods for which progress payments are requested.

The Contractor shall furnish the originals of all field notes and all other records relating to the basis for payment, to the Contracting Officer Representative, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer Representative.

2.1.3 Project Meetings

Post Award Meeting

The following Project Requirement deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting.

Letter designating your Project Superintendent with contact information Project Schedule with construction portion fully developed Itemized Schedule of Values to be used as basis of progress payments A list of subcontractors for this project Written statements from subcontractors certifying compliance with applicable labor standard clauses.

Evidence of liability insurance coverage and workmen’s compensation for the contractor and all subcontractors.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 5

Preconstruction Meeting

Correspondence procedures Jobsite safety Roles and responsibilities Lines of Authority Progress Payments Submittal process Resolution to comments provided by NPS on the Project Requirements Construction schedule (Provide a minimum of two, color hard copies and electronic copy in .pdf format) Labor standards Payroll reports Modifications Accident reporting Park Rules and Regulations Medical emergency processes, availability, emergency numbers, and contacts.

Park permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, natural and cultural resource concerns.

Access road and site constraints.

Traffic control Visitation and public relations.

Saturdays, Sundays, holidays and night work.

Pre-construction existing site documentation/photography.

Progress Meetings

The Contractor shall participate in weekly telephone conference calls with the Contracting Officer Representative, and other project team members to update them on the following meeting agenda items:

Approval of minutes of previous meetings Submittal status Review of off-site fabrication and delivery Requests for Information (RFI’s) and issues Modifications Work in progress and projected Schedule update (provide updated CPM schedule) Other business relating to work

2.1.4 Project Schedule

General: The Contractor shall provide two (2) color .pdf copies of the schedule after award. The schedule shall include detailed submission dates, review periods as well as a summary construction schedule with important milestones.

Fully develop the construction portion of the schedule and submit to the Contracting Officer Representative before the Preconstruction meeting or any construction begins. The project schedule shall be updated on a monthly basis throughout the entire contract period and until project substantial

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 6

completion. The status date of each schedule update shall be 10 days before the progress payment request date.

Construction work shall not begin until government approval is obtained for all required preliminary submissions.

Purpose: The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of Construction activities of the Contractor. The project schedule will assist the Contractor and the Contracting Officer Representative in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment requests.

Software: The software shall be the latest version of Microsoft Project, or approved equal.

Schedule Development: The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.

The Contractor shall use the Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and the delivery long-lead procurement items) and construction activities.

The Contractor's project schedule shall consist of, but not be limited to, the following for each activity:

Identify each and every activity number with numerical designations (maximum 5-digit).

Numbering of activities shall be in increments of 10.

Concise description of the work represented by the activity (maximum 48 characters). Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.

Activity duration in whole working days with a maximum duration of 15 workdays each, unless otherwise approved by the Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

In developing the project schedule, the Contractor shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.

The project schedule, as developed, shall show the sequence and interdependence of activities required for complete performance of the work. The Contractor shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity. Resource loading of each activity shall list all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown. Include permit requirements and constraints. Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the contract time.

Project Schedule Updates

Monthly updates: The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract. If, in the

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 7

judgment of the Contracting Officer Representative, the Contractor fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the Contractor shall be deemed to have not provided the required information upon which the progress payment may be made, and shall be subject to retainage of a portion of the payment.

Narrative: The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month. Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.

As the Work progresses, indicate Actual Completion percentage for each activity.

If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the narrative with your submission:

Any known delays.

Actions that will be taken to get back on schedule.

Pending modifications.

Impediments or constraints affecting progress.

Progress Payments: The monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the project schedule, the Contractor shall submit to the Contracting Officer Representative a written time impact analysis illustrating the influence of each modification, change, delay, or request on the contract time.

Time Extensions: Activity delays shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the project schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

Float: Float is not for the exclusive use or benefit of either the National Park Service or the Contractor. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.

2.2 Construction Requirements

Minimize Construction Impacts

The following mitigation measures shall be implemented to minimize the impacts of construction activities:

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 8

Visitor Experience: The following mitigation measures shall be incorporated into the action alternatives to minimize the impacts of construction activities on the visitor experience:

Keep project area in clean and neat appearance. Plan work and schedule to minimize duration of time needed for dumpsters and equipment at the location of project.

2.2.2 Schedule of Values

After contract award, submit a schedule of dollar values based on the Contract Price Schedule.

Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. The total costs for the component parts of work shall equal the contract line-item amount for that lump-sum item. The Contracting Officer Representative may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below.

Do not include mobilization, general condition costs, overhead or profit as a separate item.

Do not break down unit price items. Use only the contract line-item amount for unit price items.

The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments.

An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer Representative before the first progress payment is processed.

2.2.3 Construction Support

Staging Areas Construction sites will be limited to the smallest feasible area. Disturbance and site management will be carefully controlled to prevent undue damage to vegetation, soils, and archeological resources and to minimize air, water, soil, and noise pollution.

Staging is not anticipated in construction area(s) for a construction office or trailer. Construction equipment and material storage shall be located in area(s) near the project site. All staging areas shall be documented/photographed and returned to pre-construction conditions once construction is complete.

Standards for this, and methods for determining when the standards are met, shall be developed in consultation with the CO.

Trailers, Storage, Sheds, Staging Area: Plan work to minimize need for staging and storage at the project’s location(s). Location(s) shall be submitted for approval by the Contracting Officer Representative.

Storage Sheds: If used, provide weather tight sheds or other covered facilities for storage of materials subject to weather damage.

If used, all temporary water, sewer, sanitary facilities and electric utilities, shall be completely removed upon project completion.

The locations of the Staging Area for construction equipment will require COR approval.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 9

Construction Zones Protection of Public: Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. Erect and maintain fencing, barricades, and warning signs as required by NPS.

The Contractor shall protect all structures, in or adjacent to work areas. Damages shall be repaired at no additional cost to the Government.

Parking of Construction Vehicles Vehicle parking shall be limited to legally designated areas, and within approved staging area(s).

2.2.4 Submittals During Construction

Construction Submittal Types

Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.

Product Data: Collect information into a single submittal for each element of construction and type of product or equipment Shop Drawings: Prepare floor pattern / seam layouts, drawn accurately to scale. Do not base

Shop Drawings on reproductions of the Contract Documents or standard printed data [, unless submittal of CAD Drawings is otherwise permitted].

Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials

Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

General: Prepare and submit Informational Submittals required by individual Specification

Sections.

Informational submittals include but are not limited to Coordination Drawings LEED™

Submittals Product Data, Certificates, Test reports, Manufacturer’s instructions, Division 01 Management Plans, etc.

Contractors Review Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.

General Submittal Procedures Prepare and submit submittals shown in Part 4.0, Technical Requirements. Details on the specific requirements for each can be found in the individual technical sections.

Contracting Officer Representative reserves the right to require submittals in addition to those called for in individual sections.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 10

Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

Processing Time: Allow enough time for submittal review, including time for re-submittals. Time for review shall commence when the Submittal is received by the Contracting Officer Representative.

When the COR has completed the review, an e-mail notification will be sent to the Contractor indicating the submittal has been processed. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Action Submittals: Allow 10 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

2. Informational submittals: Allow 10 days for review of each submittal.

Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. CM- 16 Transmittal Form: All submittals shall be transmitted using National Park Service form CM- 16 form. No action will be taken on a submittal item unless accompanied by the CM- 16 transmittal form.

a. Complete the general information at the top of the form.

b. Provide all required information based on the submittal type

c. Attach all related documents.

d. Sign the CM-16 form in the contractor section at the bottom of the form and submit when complete.

2. Physical samples: Complete the CM-16 as described above. Deliver the physical sample to the COR and/or designee on site for processing. All comments and actions will be documented on the CM-16 form.

Contracting Officer Representative’s Review

Action Submittals: Contracting Officer Representative will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-16 Transmittal Form. The submittal will be marked in one of three ways as defined below:

1. Approved: Acceptable with no corrections.

2. Approved with Notations: Minor corrections or clarifications required. All comments are clear, and no further review is required. The Contractor shall address all review comments when proceeding with the work.

3. Disapproved – Resubmit: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 11

Informational Submittals: Contracting Officer Representative will review each submittal and will either accept or reject them.

Contracting Officer Representative may require additional submittals.

Use for Construction

Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction

2.2.5 Construction Coordination

Notification: The Contracting Officer (CO) will provide all necessary written notification and/or direction to the contractor. An on-site Superintendent will co-ordinate the contractor’s construction efforts with the park staff’s daily operations and will transmit and receive correspondence between the POC and the Contractor.

The NPS Project Manager, COR and Park POC will have no authority to accept or reject work, or to authorize changes to the terms and conditions of the contracts, or to obligate the NPS for time or money.

2.2.6 Quality Control

General The quality of all work shall be the responsibility of the Contractor. Inspect and verify all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable requirements of contract.

Daily Reports: Submit showing all inspections on the first workday following the date covered by the report.

Off-Site Inspection Reports: Submit prior to shipment.

2.2.7 Working Hour Restrictions

All work and deliveries shall be limited to the weekday hours of 7:00 am to 4:00 pm Monday through Friday, unless otherwise approved by the Contracting Officer or COR. No work shall occur on National Park Service holidays or weekends without prior approval.

2.2.8 Temporary Services:

Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

Fire Protection Equipment: Observe and enforce standards of fire prevention. No open fires shall be allowed.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 12

Vehicles and Equipment: Provide one fire extinguisher on each vehicle or piece of equipment.

Extinguishers shall have a minimum UL rating of 2-A:10-B: C. A capable and qualified person shall be placed in charge of fire protection.

Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.

Smoking: Smoking within buildings or temporary storage sheds is prohibited.

Telephone: The Contractor shall make use of cell phones if needed.

2.2.9 Access

Coordinate construction efforts with the Contracting Officer Representative and the Park POC such that there is minimal impact to the work of the National Park Service personnel and the visiting public.

During construction of the scheduled facilities, the Contractor shall have continuous access to the project’s area during working hours only. Access shall be discussed and agreed at Preconstruction Meeting and any changes shall be submitted for Approval by the Contracting Officer Representative or Park POC during performance of the work.

2.2.10 Preservation of Adjacent Features

Confine all operations to work limits of the project. Prevent damage to natural and built surroundings.

Restore damaged areas repairing or replacing damaged materials, installations, trees and plants, at no additional expense to the National Park Service.

2.2.12 Hauling Restrictions

Comply with all legal and local load restrictions in the hauling of materials.

2.2.13 Accident Prevention

Accident Reporting: Reportable accidents, defined as death, occupational disease, traumatic injury to contractor’s personnel, NPS employees or the public, property damage of any accident in excess of $100 and fires, must be reported within seven days. Complete an Accident/Property Damage Report (attached Form CM-22) and forward to the Contracting Officer.

Quality Assurance: Ensure that all employees are physically qualified to perform their assigned duties in a safe manner. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals and operating instructions, and be capable of operating such equipment.

Accident Prevention Products: Provide the following:

First aid facilities.

Personnel protective equipment: Meet requirements of NIOSH and MSHA.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 13

Emergency instructions, including telephone numbers and reporting instruction for ambulance, physician, hospital, fire department and park police. Place in conspicuous locations at the worksite.

Adequate egress at all times in accordance with the Standard for Safeguarding Construction, Alteration, and Demolition Operations (NFPA 241).

Training: Provide training for first aid and hazardous material handling and storage.

2.2.14 Temporary Controls

Housekeeping: Keep project neat, orderly, and in a safe condition at all times.

The park regularly experiences severe weather, including tornadoes and hurricanes. Should a tornado or hurricane threaten the area, the park shall advise the contractor of park closure or preparations. In case of hurricanes, park and construction site will be secured and closed at least 24 hours before anticipated storm landfall. Follow instructions of Park POC and/or Superintendent.

2.2.15 Project Close-out

Cleaning: Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition.

Remove grease, dirt, stains, foreign materials, and labels from finished surfaces. Thoroughly clean building interiors. Pick up and remove all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.

2.2.16 Substantial Completion and Final Inspection

Submit written certification to the CO that the project is substantially complete and request a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.

When work is determined to be substantially complete, the Contracting Officer Representative will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The Contracting Officer will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the Contracting Officer will notify the Contractor in writing. After completing work, the Contractor shall resubmit certification and request a new final inspection.

If, following final inspection, the work is determined to be substantially complete, Contracting Officer Representative will prepare a list of deficiencies to be corrected before final acceptance and CO will issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs.

Acceptance of the work: After all deficiencies have been corrected, the Contracting Officer will issue a Letter of Final Acceptance.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 14

PERFORMANCE REQUIREMENTS

3.1 Facility Performance

All work performed shall comply with applicable laws, regulations, and NPS policies and guidelines.

https://www.nps.gov/dscw/construction.htm

3.2 Elements and Products

In addition to requirements specified in other chapters, provide products and elements that comply with the following:

Products:

Where a product is specified only by a manufacturer name and model number/brand name, the Contractor shall use only that model/brand product.

Where the properties of a product are specified by description and/or with performance criteria, the Contractor shall use products that comply with the description and/or performance criteria.

Where manufacturers are listed for a particular product, the Contractor shall use a product made by one of those manufacturers that also complies with other requirements.

Where actual brand name products are not identified by either the Contracting Officer or the Contractor, the Contractor shall identify the products to be used.

In the Proposal:

o The Contractor shall identify one or more product types for each system, assembly, or element.

o For each product type, the Contractor shall identify brief descriptive or performance specifications.

o For major manufactured products that are commonly purchased by brand name, and any other products so indicated, we will identify at least one manufacturer that will be used.

During Construction:

o The Contractor shall identify actual brand name products used for every product, except commodity products specified by performance or description.

o Where a product is specified by performance requirements with test methods, and if so specified, the Contractor shall provide test reports showing compliance.

o The Contractor shall provide manufacturer's product literature for each brand name product.

o The Contractor shall provide the manufacturer's certification that the product used on the project complies with the contract documents.

NATC – REFINISH 1ST FLOOR ADMIN HEADQUARTERS 15

Before End of Closeout:

o The Contractor shall provide copies of all manufacturer warranties that extend for more than one year after completion.

o The Contractor shall provide a compilation of all final approved and used material submittal data electronically in .pdf format to Contracting Officer Representative.

END