This document is a Performance Work Statement (PWS) for a federal contract opportunity to provide hazardous fuel reduction services on the San Bernard National Wildlife Refuge (SNBNWR) in Texas.

The key details are:

  • The requirement is for shredding approximately 850 acres of small trees (3 inches or less in diameter) and brush down to 16 inches above mineral soil to reduce hazardous fuels and prevent wildfires.
  • The contract period of performance is approximately September 1, 2024 through February 28, 2025.
  • The contractor must provide all personnel, equipment, supplies, transportation, and supervision to complete the work.
  • Contractors must comply with all applicable environmental regulations, including those related to protecting threatened and endangered species in the treatment areas.
  • Proposals are due by 7 PM ET on May 24, 2024 and will be evaluated on technical experience, technical approach, past performance, delivery timeframe, and price.
  • This is a firm-fixed-price contract set aside for small businesses under NAICS code 115310.

View the file

Other files

File Type Posted
B03_Wage_Determination.pdf PDF
Sol_140FS224Q0120.pdf PDF
B08_-_Past_Experience_and_References_Form.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2024 - 2025 SHREDDING OF HAZARDOUS FUEL CONTRACT

SAN BERNARD NWR

TEXAS MID-COAST

NATIONALWILDLIFE REFUGE COMPLEX

I.GENERAL INFORMATION
II.BACKGROUND
III.SCOPE OF WORK
IV.APPLICABLE DIRECTIVES
V.PERFORMANCE REQUIREMENTS
VI.WORK TIME/HOURS OF DUTY
VII.SUPPLIES, MATERIALS, EQUIPMENT AND UTILITIES
VIII.SUPERVISION
IX.CONTRACTOR PERSONNEL QUALIFICATIONS
X.DELIVERABLES
XI.DELIVERABLES SCHEDULE
XII.QUALITY ASSURANCE PLAN
XIII.MAP

I. GENERAL INFORMATION

1.1 General: This is a non-personal service for the shredding of small trees (3 inches or less in DBH) and brush on 850 acres on San Bernard National Wildlife Refuge (SNBNWR). The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform work services as defined in this Performance Work Statement. The Contractor shall perform to the standards in this contract.

1.2 Introduction: The Contractor will shred identified fuels in units according to specifications that will assist in the prevention of wildfires from destroying/damaging government and private property.

1.3 Period of Performance: On or about September 1, 2024, thru February 28, 2025. This timeframe would account for holidays, weather-days within the contract period and is contingent on funding availability.

1.4 Site Visit Opportunity: The site visit will start from 6801 CR 306, Brazoria, TX 77422 at 0900 on May 20, 2024.

1.5 Place of Performance: The work to be performed under this contract will be within the boundaries of the SNBNWR Figure 1, 2 and 3. This shredding project will be completed as a “mosaic” across the SNBNWR units. SNBNWR operations will be run from Texas Mid-coast Complex Office 2547 County Road 316, Brazoria, TX 77422. Details concerning treatment area are identified in the Scope section of this document.

1.6 Type of Contract: This will be a Fixed Price contract/task order.

1.7 Security Requirements: SNBNWR is a closed refuge so contractor will be required to make arrangements with/notify Contracting Officer Representative and United States Fish and Wildlife Service Law Enforcement of all work details/days.

1.8 Key Control: Contractor will be required to provide a combination lock to be placed on refuge gates solely for the purpose of egress and ingress to complete contract obligations.

1.8.1 Lock Combinations (if applicable). The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Contractor’s Quality Control Plan.

1.9 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend all post award conference or progress meetings convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The Contracting Officer (CO), Contracting Officers Representative (COR), Government Representative (GR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance and/or status of work. At these meetings, the CO or GR will apprise the Contractor of how the government views the Contractor's performance and the Contractor will apprise the Government of problems being experienced, if any. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.10 Contracting Officer Representative /Government Representative: The COR will be identified by either separate letter or other form of notification. The COR/GR monitors all technical aspects of the contract and assists in contract administration. The COR/GR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; conduct inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, and specifications; monitor Contractor performance and notify both the CO and Contractor of any deficiencies and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.11 Key Personnel: The following personnel are considered key personnel by the government: Contract Manager/Administrator, Project Manager/Supervisor. The Contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the CO. The contract manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available Monday – Sunday 7:30 am to 4:00 pm with the exception of Federal Holidays

1.12 Identification of Contractor Employees: All Contract personnel attending meetings and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

II. BACKGROUND

2.1 The mission of the United States Fish and Wildlife Service is working with others to conserve, protect and enhance, fish, wildlife, plants, and their habitats for the continuing benefit of the American people. An important part of this is the protecting the public for wildland fires. Refuges employ a variety of management techniques to reduce fuels; one priority method is through fuel reduction prescribed burns; alternative methods are through the use of mechanical and hand treatments. Refuges prioritize treatments based upon the management objectives and public safety; that is, the ability to meet the objectives of the refuge while keeping the public safe at the same time.

III. SCOPE OF WORK

3.1 Objective: Shredding of vegetation to reduce hazardous fuel in the units of SNBNWR will be completed for a total of 1000 acres. All vegetation with a diameter of (3) inches and smaller must be shredded down to 16 inches above mineral soil inside designated units. Reduction of fuels will allow prescribe fire operations to continue and assit with the protection of private property and endangered flora and fauna.

3.1.1 Treatment Area: The general location of these units is 6801 County Road 306 Brazoria, TX in Brazoria County. The majority of the units are south of County Road 306 and one of the units are east of County Road 457 in Sargent, TX, Matagorda County area. This area has a dominate canopy of Baccaharis, other brush, and tree saplings with diameters ranging from ½ inch to 4 inches and larger hardwood trees are intermixed. The government has the right to move project location to a similar site within the refuge boundary if the original site cannot be accessed due to weather conditions, threaten species activity or a higher priority project is identified.

3.2 Contractor must comply 100% with the agreed-upon plan of work. Preferred method of treatment will be by low ground pressure tracked equipment. The government is open to alternative method of treatment by low ground pressure equipment but must be approved prior to commencement of work. All work must be done according to work statement, equipment capability restrictions and any local and state regulations.

3.3 The Contractor shall provide all personnel, labor equipment, supplies, transportation, tools, materials, supervision and other non-personal services necessary to perform the requirements of this contract and shall plan, schedule, coordinate, and ensure effective performance of required services for the entire duration of contract. Crews must avoid all areas marked as “off limits”; coordinates will be provided to the Project Manager for these locations. Treatment applications shall be performed in such a manner as to protect non-target flora species, the environment, and the public. NOTE: The CO reserves the right to require the Contractor to replace any operating personnel, or equipment used in the performance of this Contract if the personnel, or equipment are violating, or have violated, any state or federal laws; or are unsafe; or for any valid reason. In this event, the Contractor shall as soon as reasonably possible, upon written or verbal notice (to be later reduced to writing) from the CO, provide replacements satisfactory to the CO at no additional cost.

3.4 Work performance shall be defined as 100% of identified area to be treated.

3.5 All personnel and equipment to be used will be appropriately licensed and certificated for the work to be done. The Contractor will be responsible for providing sufficient equipment, fuel, safety items, personnel and their subsistence needs during the project period, as well as checking all work sites for hazards of any type which could affect their ability to accomplish the project.

3.6 The Contractor will provide USFWS with contact information for all ground personnel, vehicles, and equipment, identification information (including make, model, color, name of company, and contact information) at least 48 hours before implementation of the project.

3.7 Public Safety: Public safety must always be ensured. In application areas where there is potential for public interaction, the Refuge shall advise the Contractor of any public use hazards. It shall be the ultimate responsibility of the Contractor to initiate operations GO-NO-GO. Any fines or penalties for damage to public or private property or resultant environmental damage shall be the responsibility of the Contractor.

3.8 The COR/GR must be notified at least 24 hours prior to the start of any operations.

3.9 Only approved equipment will be allowed to operate within the treatment units.

3.10 The Contractor shall avoid any damage to native flora and fauna outside the designated area or clearly marked areas inside the designated area. The Contractor shall not collect, harass, harm, or molest native flora and fauna. The Contractor shall avoid damage to sensitive archaeological sites. The Contractor shall be responsible for the removal of all trash and treatment-related equipment. The Contractor shall be held liable if damage was determined to be the fault of the Contractor (negligence), the result of improper treatment techniques, or the result of Contractor control activities.

3.11 The ground crew supervisor shall be responsible for any data collection, safety procedures, and crew supervision. The COR/GR shall provide technical support concerning species/area treatments for each delineated work area. Under no circumstances shall a non-approved piece of equipment be used without knowledge or permission of the COR/GR. Ground crews accessing the treatment area need be aware that the majority of the acres to be treated contain seasonal wetlands.

IV. APPLICABLE DIRECTIVES

4.1 All Contractor employees performing work directly onsite must adhere to all local regulations, rules, policies relating to the obtainment of proper clearances and site access.

4.2 The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

4.3 OSHA, 29 CFR 1910 (as applicable)

4.4 EPA regulations

4.5 The Contractor is responsible for acquiring and maintaining all federal, state and local licenses, certifications, and permits. The only exception to this requirement is that the SNBNWR will provide the Section 7 permit, if required, for threatened species for this contract if applicable. A copy of the Section 7 permit will be furnished to the Contractor and all conditions will be followed. Threatened species are known to frequently occur in the treatment area and adhering to the Section 7 permit conditions should require minimal effort. Contractor must follow Black Rail Regulation Equipment Operation Criteria. This will be provided to the contractor by the government.

4.6 All of the shredding in the units must be done following best management practices for mowing in black rail habitat. This includes: 1) operating equipment at a slow speed (1-2 mph or the slowest speeds possible) to allow wildlife to escape the mower path; 2) using linear clearing that begins adjacent to and runs parallel with the unit boundary so that the treatments are applied from the edges inward towards areas where rails can take refuge; and 3) driving equipment so that its path does not follow a circular or entrapping pattern. This will lessen the risk of damage to the black rail or its habitat in the unit. The contractor cannot be in the units from March 1 to August 31, which is the black rail breeding season. This also avoids the general migratory bird nesting season.

4.7 The Contractor (or their representatives) will not litter. Litter violations will be handled under Federal Code of Regulations 50CFR27.94 (a), which carries a fine of $100.00 per incident upon conviction.

V. PERFORMANCE REQUIREMENTS

5.1 All vegetation with a diameter at breast height of six (4) inches and smaller shall be shredded to 16 inches above mineral soil.

5.1.1 The Crew Supervisor shall be responsible for notifying the COR /GR within one week of treatment completion so that the area can be inspected. The Contractor shall be responsible for 100% treatment of the identified area.

5.1.2 Contractor must be able to provide a GPS track log of each days shredding accomplishments. It must be emailed to the COR within 24 hours.

5.2 TREATMENT

5.2.3. The Contractor shall canvas 100% of the identified treatment area.

5.2.3The Contractor shall complete the treatment during the specified dates as directed by the COR/GR due to endangered species activity as directed by the refuge biologist and wet soil conditions.

5.2.4 The Contractor shall coordinate with the Government to determine the date(s) and time(s) of treatment to minimize impacts on other Government activities and so refuge staff has time to close roads and trails in the treatment area prior to treatment beginning. Contractor must have work dates and a plan of work approved by the USFWS 48 hours prior to beginning work, preferably established during a face-to-face pre-work meeting.

5.2.5 The Contractor shall clean and wash equipment in accordance with Environmental Protection Agency and refuge guidelines to prevent the introduction of exotic flora and fauna onto the refuge. Refuge guidelines require all equipment to be pressure washed prior to entering refuge property. Prior to leaving the worksite for the day, the Contractor shall remove all equipment and materials associated with contract activities on government property unless approval has been granted by the Refuge Manager, COR or GR and/or a storage site has been identified.

5.2.6 Contractor is responsible for notifying COR/GR at the time of a hazardous spill and the contractor is responsible for cleaning up any spills that may occur.

5.2.7 The Contractor shall avoid any damage to native vegetation and wildlife. The Contractor shall be responsible for the removal of all trash and treatment-related equipment. Trash shall be removed daily. If damage occurs, the Contractor shall be held liable if damage was determined to be because of Contractor negligence, the result of improper treatment techniques, or the result of Contractor control activities.

5.3 SPECIAL CONDITIONS

5.3.1 The COR/GR shall inform the Contractor of the time schedule as work progresses. However, the CO may halt work at any time upon written notice.

5.3.2 Weather and site conditions may interfere with the work completion schedule negotiated at the award conference. The CO may halt work at any time upon written notice for conditions beyond the control of the contractor. If this results in significant time lost, the completion date for the project can be re-negotiated by the COR/GR and must be approved by the COR.

5.3.3 Contractor must be able to provide a GPS track log of each days shredding accomplishments. It must be email to the COR within 24 hours

VI. WORK TIME/HOURS OF DUTY

6.1 Hours of Operation: The Contractor is responsible for conducting business, between the hours of 6:00 am – 7:00 pm Monday thru Sunday except national emergencies, administrative closings or similar Government directives. Work days or hours outside these times must be approved by the COR/GR. For other than firm fixed price contracts, the Contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

VII. SUPPLIES, MATERIALS, EQUIPMENT, AND UTILITIES

NOTE: As a government agency dedicated to “working with others to conserve, protect and enhance fish, wildlife, and plants and their habitats for the continuing benefit of the American people,” the U.S. Fish and Wildlife Service strives to incorporate the most ecologically sound and environmentally beneficial technologies, materials, and practices into all aspects of planning and operations. To help achieve this mission and meet Executive Orders (EOs) and Department of the Interior (DOI) planning requirements, the USFWS has implemented strategies to reduce the environmental impacts associated with procurement, lease acquisition, waste prevention and recycling, facility design, construction, operation and management, contracting and permitted commercial visitor services. These strategies have been collectively referred to as the FWS’s Green Procurement and Waste Prevention & Recycling Program (Greening Program) and are a part of the FWS’s overall approach to environmental management.

7.1 Government-Furnished Property and Services: The Government will not provide any Supplies, Materials, or Equipment to complete this contract.

VIII. SUPERVISION

8.1 In order to ensure performance and accomplishment of the work as outlined herein, the Contractor shall always provide adequate and competent supervision for all work to be accomplished by the Contractor’s employees. When contract work is in progress, supervisory personnel shall be available at all times to receive notices, reports, or requests from the COR/GR or his authorized representative. At no time shall CO/COR/GR direct or supervise the activities of the Contractor’s employees.

8.2 On-site Supervision: An on-site supervisor, with the ability to speak and understand English clearly and with the authority to act for the Contractor on a day-to-day basis and to sign inspection reports and all other correspondence on behalf of the Contractor, shall be always present at the work site when contract work is in progress, unless a contractor employee can act on the supervisor’s behalf.

8.3. Supervisory Responsibilities: Supervisory responsibilities shall include, but shall not be limited to, the following:

8.3.1 Providing an adequate labor force; this includes the immediate replacement of personnel dismissed for cause or leaving employment of their own volition.

8.3.2 Ensuring that Contractor personnel are properly trained to perform their assigned work in a proper, safe, and efficient manner, and ensuring that the proper supplies, materials, and equipment are on hand.

8.3.3 Taking action to prevent general carelessness by employees and/or abuse of government property, flora or fauna.

8.3.4 Establishing an effective and comprehensive safety program.

8.3.5 Indoctrinating employees to report fire, hazardous conditions and damage.

8.3.6 Continually ensuring that the conduct of the Contractor’s employees reflect favorably upon the Contractor’s and Fish and Wildlife Service organization(s). If applicable, supervisory personnel are responsible for ensuring that employees fully support and participate in the energy-conservation program within the facilities.

IX. CONTRACTOR PERSONNEL QUALIFICATIONS

9.1 Supervisory Personnel: All supervisory employees engaged in directing the work to be accomplished under this contract shall possess, at least two years’ experience in directing the subject service-type operations in a supervisory capacity for the approximate size/scope of this contract.

X. DELIVERABLES

10.1 Frequent reporting/accounting of overall progress (i.e. 33%, 66%, 100%) or as determined by the COR/GR.

10.2 Universal Daily Progress Report (U-DPR), to be provided the COR/GR or his/her designee on a bi-weekly basis (minimum).

10.3 Coordination, application, and wrap-up meetings

10.4 A COR/GR will inspect all areas periodically during the contract period.

10.5 Copies of all invoices (signed by the Contractor Crew Supervisor/GR) can be submitted to the Government at completion times of 33%, 66% and 100% complete.

10.6 Contractor must be able to provide a GPS track log of each days shredding accomplishments. It must be email to the COR within 24 hours

XI. DELIVERABLES SCHEDULE

(This technical exhibit lists any reports or documentation that is required as a deliverable and includes the frequency, # of copies, medium/format and who/where it is to be submitted. A deliverable is anything that can be physically delivered but may include non-physical things such as meeting minutes.)

Deliverable
Frequency
# of Copies
Medium/Format
Submit To
Routine reporting/accounting of progress
33%, 66%, 100%
1
Hard/soft copy

COR/GR/Manager

Daily Progress Report
Daily
1
Email Track Log
COR/GR/Manager
Coordination, application, and wrap-up meetings
As directed by the COR/GR
n/a
Meeting
COR/GR/Manager

XII. Quality Assurance Plan

12.1 The Contractor shall institute a complete quality-control program to ensure that the requirements of this contract are provided, as specified. The overall goal of the program should be to identify and correct any problems that may exist before they are identified by or reported to the COR/GR. This will aid in ensuring the contractor meets time schedules, adheres to standard commercial practices, and complies with Performance Work Statement/contract in an efficient, ethical, and productive manner. As a minimum, the program shall include:

12.1.1 An inspection system covering all the services required under Section V (Performance Requirements) with a comprehensive checklist to be used to inspect contract performance during scheduled and unscheduled inspections, and the name(s) of the individuals who will be performing the inspections.

12.1.2 A system for identifying and correcting deficiencies and/or a pattern of deficiencies in the quality or quantity of services provided before the level of performance becomes unacceptable and/or Government inspectors point out the deficiencies.

12.1.3 A file of all inspections conducted by the Contractor and corrective actions taken (at Contractor’s expense). This should include follow-up inspections to ensure that corrective action was appropriate, complete, and timely. This documentation shall be organized in a logical manner, kept current, and made available to the CO/COR/GR during the term of the contract.

12.1.4 When notified of a deficiency, items designated as unsatisfactory or below standard shall be re-performed by Contactor at no additional cost to the Government. All corrective actions must be completed by the next working day of notification of the deficiency. If not, a deduction may be made (as determined from the applicable month’s invoice). Failure of the Government to notify the Contractor of a deficiency does not relieve the Contractor of the obligation to perform services nor does it relieve the Contractor of the responsibility to ensure that quality control measures are adhered to for contract compliance.

12.2 Performance Indicators and Acceptable Quality Levels

12.2.1 Comply with work production/work schedule(s) except for Excusable Delays. 100% compliance

12.2.2 Comply with all work requirements and standards as indicated within the Scope of Work. 100% compliance

12.2.3 Comply with all contract terms and conditions. 100% compliance

12.2.4 Must not damage government resources, fish, wildlife, and/or property. 100% compliance

12.2.5 Maintain safety of workers and work environment at all times. 100% compliance with no deviations

12.2.6 Maintain a Quality Control Plan and immediately disclose/report any problems. 100% compliance

12.2.7 Ensure all equipment is in good working order during the entire period of performance, and safeguard the use and storage of all hazardous chemicals. 100% compliance

12.2.8 The task shall be considered completed following a thorough final inspection of the delineated treatment area by the COR and only if it is determined that the Contractor treated 100% of the project. 100% compliance

12.2.9 The Contractor shall be held responsible for non-target damage (to be determined by the COR). 100% compliance

12.3 Surveillance Methods

12.3.1 Regularly scheduled inspection/review of work

12.3.2 Inspection of equipment. The CO/CO/GR, reserves the right to inspect, at any time upon notice to the Contractor, the Contractor’s procedures and operating personnel. Inspection, however, shall not relieve the Contractor of any obligations or responsibilities, nor shall it transfer any liability to the Refuge.

12.3.3 Contractor logs/reports

12.3.4 Final payment shall be held until 100% of the project is completed as determined by a final inspection conducted by COR/GR.

12.4 Incentives

12.4.1 Non-compliance with Performance Work Statement will result in negative performance evaluation/rating.

12.4.2 A positive performance rating will be given for overall satisfactory work and compliance related to the contract.

Figure 1. Map of Shredding Units

Figure 2. Map of Shredding Unit

Figure 3. Map of Shredding Unit image1.jpg image2.jpg image3.jpg