A04__SOW_Monte_Vista_Well_Batch.pdf

PDF 315 KB Posted

Attached to
CO MONTE VISTA NWR WELLS REHAB
Solicitation number
140FGA25R0005
Issued by

About this file

This Statement of Work outlines requirements for well repairs at Monte Vista National Wildlife Refuge in Colorado. The project involves repairs and improvements to five wells (Well #4, #7, #57, #60, and Clayton Well #C-72) with specific requirements for each location.

The contractor must provide all materials, equipment, and labor for installing/repairing water wells and appurtenances. Key requirements include: installation of new pumps, motors, and associated equipment; well cleaning and rehabilitation; electrical work; flow meter installations; and specific production capabilities ranging from 1300-2000 gpm depending on the well. The work must be completed within 120 calendar days from Notice to Proceed. The contractor must have well certification to work on wells exceeding 20 HP motors and provide examples of similar work from the past 3 years. The site lacks electricity, sanitary sewer, and drinking water access, requiring the contractor to provide temporary facilities. All work requires compliance with federal, state and local regulations, with typical working hours of 7:30 am to 4:00 pm Monday through Friday. The contractor must provide warranties, submit detailed documentation, and coordinate with the Refuge Manager and Contracting Officer Representative.

View the file

Other files

File Type Posted
Sol_140FGA25R0005_Amd_0001.pdf PDF
Monte_Vista_Well_repair_RFI_0001.pdf PDF
Wage_Determination.pdf PDF
Sol_140FGA25R0005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

TO

24-001F WELL REPAIRS PHASE 1

AT

MONTE VISTA NATIONAL WILDLIFE REFUGE

I. GENERAL CONDITIONS

A. The Contractor shall provide all material, equipment, and labor required to install and/or repair water wells and all appetences outlined in Section VIII.

B. The Contractor shall be responsible for installing all materials described in Section

VIII.

C. The Contractor shall have all certificates and licenses required by law for the execution of the work, and shall comply with all Federal, State, or local laws, ordinances, rules, regulations, and codes relating to performance of the work.

D. Typical working hours are 7:30 am to 4:00 pm Monday through Friday. Any work that deviates from this schedule or during a holiday requires Contracting Officer approval. These times can be negotiable during the pre-construction meeting.

E. Any conflict or overlap of Colorado Department of Environmental Quality, EPA, OSHA, and other applicable Federal, State, and local regulations, the Contractor shall follow the most stringent provision.

F. Safety

1. The Contractor shall assume full responsibility and liability for compliance with all applicable Federal, State, and local regulations pertaining to the protection of workers, visitors to the site, and persons occupying areas adjacent to the site, including the provisions of 29CFR1910 and 29CFR1926 of the Code of Federal Regulations. The Contractor shall hold harmless the

Government for failure to comply with any applicable safety or health regulations on the part of himself, his employees, or his subcontractors.

2. Every Contractor employee shall be responsible for complying with applicable safety requirements, wearing prescribed safety equipment, and preventing avoidable accidents and property damage.

3. The Contractor shall provide and maintain a basic first aid kit for use of the workers. The kit shall contain first aid supplies in type and quantity commensurate with type and size of project and the work force, with items necessary for first aid treatment of all injuries. The Contractor shall advise all workers of the location of first aid supplies.

4. The Contractor shall post the telephone numbers of nearest hospital, ambulance service, and fire station in a conspicuous location. The

Contractor shall advise all workers of the location of telephone numbers.

Communication devices shall be made available and be ready at the work site to alert others in case of emergencies.

5. The Contractor shall provide at least one nonfreezing type fire extinguisher in each field office, workshop, work site, and storage shed at the work site. These fire extinguishers shall be placed in locations readily accessible by workers.

II. WORK SITE CONDITIONS

A. The site of the work is at Monte Vista National Wildlife Refuge.

B. The Contractor is responsible for following all federal, state, and local laws.

C. Environmental Litigation

1. Time lost due to work stoppage because of failure of the Contractor to comply with these requirements may not be the subject of a claim for extension of time or for costs or damages.

D. Fossils and Cultural Materials:

1. Should the Contractor discover any fossils or cultural materials during construction operations, such objects shall become the property of the

Government. The Contractor shall cease construction operations in the area of the "find," and immediately notify the station manager of such discovery.

Construction operations may proceed in other areas not affected by this clause. Care shall be exercised by the Contractor not to damage or collect fossils or cultural materials uncovered during excavation operations.

2. Failure to comply with this requirement may be considered a violation of the

Archeological Resources Protection Act of 1979 as amended. Destruction of historic and prehistoric sites and/or unauthorized collection of cultural materials can result in criminal and/or civil penalties. Penalties can include fines, prison sentences, and/or confiscation of equipment.

III. TEMPORARY FACILITIES AND CONTROLS

A. Temporary Utilities

1. The site does not have access to electricity, sanitary sewer, or drinking water.

The Contractor shall supply a porta-john.

2. The Contractor shall be responsible for the daily removal and disposal of all debris from demolition and construction activities.

B. Site access and equipment storage areas

1. All Contractor operations (including storage of materials) upon

Government premises shall be confined to areas authorized or approved by the Refuge Manager, or her designee.

2. The Contractor shall restore all work and storage areas and areas disturbed by construction to their original condition, or as approved by the Refuge

Manager, or her designee, upon completion of the work

3. The Contractor shall observe all laws and regulations of the local, county, and State authorities in the use of all public roads and highways for the transportation of materials and equipment in connection with work on the project.

4. The Contractor shall observe all overhead obstructions such as bridges, cables, ect. The Contractor shall repair damage to roads, highways, overhead obstructions, and similar items, resulting from operations performed in connection with this project.

C. Protection and Restoration:

1. The Contractor shall protect all structures and vegetation during the progress of the work and remove all debris and unused materials from the site.

2. Upon completion of the work, the Contractor shall restore, at their expense, all vegetation to its original condition, including the replacement any facility or landscaping which has been damaged.

3. The Contractor shall limit removal of any vegetation to that which interferes with the construction, and shall seed any disturbed soil with native grass. The Contractor shall obtain the seed mix from the Refuge Manager.

D. Traffic Regulation

1. If traffic regulation is required at the jobsite, the Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient flasher lights, flagmen, danger signals and signs, and shall take all necessary precautions for the protection of the work and the safety of the public.

2. Roads closed to traffic shall be protected by effective barricades on which shall be placed acceptable warning signs.

a. All barricades and obstructions shall be illuminated at night and all lights shall be kept burning from sunset until sunrise.

3. Install appropriate traffic signs at crossroads and approaches to site as needed to direct all affected traffic. Specific sign and barricade requirements are detailed in ANSI D61, "Manual on Uniform Traffic Control Devices."

E. Delivery and Storage: Material shall be delivered to the site in a dry and undamaged condition and stored out of contact with the ground. Materials shall be covered with weather tight covering and kept dry. Storage accommodations shall provide good air circulation and protection from surface staining, when appropriate.

IV. MEANS AND METHODS

A. Means and methods of construction shall be such as the Contractor or subcontractors may choose; subject, however, to the Contracting Officer's right to reject means and methods proposed which:

1. Constitute a hazard to the work, persons, or property.

2. Will not produce finished work according to the terms of the contract.

3. Are contrary to specified means or methods included in the contract.

B. The right to reject means and methods of the Contractor or subcontractor shall not be construed or interpreted as acceptance of control of means and methods by the

Contracting Officer.

C. The Contracting Officer's approval of means and methods or failure to exercise right to reject means and methods shall not relieve the Contractor of the obligation to complete the work required by the contract.

D. Total responsibility for control of all means and methods lies with the Contractor for all work.

E. Final Inspection

1. The Contractor shall request a final inspection in writing at least ten (10) days prior to the anticipated date of completion. If, as the anticipated date of completion approaches and it becomes apparent that the date will not be met, the Contractor shall inform the Contracting Officer at the earliest possible moment, but in any case not later than 2 business days prior to the anticipated completion date.

2. Work will not be considered READY FOR FINAL INSPECTION until all the work has been completed and the Contractor has certified that all items are properly operating and in strict compliance with all contract terms and conditions.

3. The Contractor and/or his project supervisor shall be at the job site during the final inspection.

F. Final Cleanup: The Contractor shall clean the site and remove from the site all construction debris.

G. Final Payment: The Contractor shall submit the following prior to final payment:

evidence of completion, guarantees, warranties, O&M manual, certificates, certified payrolls, and as-builts.

V. CONTRACTOR QUALIFICATIONS

A. The Contractor and all subcontractors shall have all Federal, State, and local licenses, and/or certifications, etc., necessary to perform work in Rio Grande

County, Colorado. All licenses and/or certificates must be current from start to finish of the project.

B. The contractor working on the well must be provide their well certification to work on wells this size. The contractor shall provide the past 3 years example of wells that exceed 20 HP motors.

VI. SUBMITTALS

A. The Contractor shall provide copies of all required permits, clearance, and licenses obtained to perform this work to the Contracting Office.

B. If alternatives to the means and materials described in these specifications are offered, the submittal must contain a written description of the proposed means and materials comparing all features, options, and codes (if any), in detail. A detailed explanation of why the proposed alternative should be accepted must also be submitted.

D. The Contractor shall submit manufacturer's warranties, guarantees, and certificates for all installed equipment listed on the Project Submittal List.

E. Timing of Submittals/Unapproved Work: As specified above, the Contractor shall submit all deliverables, copies of all required permits, and all product data sheets to the Contracting Officer for review. These submittals must be approved PRIOR to the installation of any purchased or fabricated components. THE PURCHASE AND/OR

INSTALLATION OF ANY UNAPPROVED COMPONENTS SHALL BE AT THE CONTRACTOR’S

RISK. Contract performance time shall not be extended due to delays caused either directly or indirectly by the purchase and/or installation of unapproved components.

F. All items in Section VIII shall be submitted for approval.

G. The attached submittal form shall be used.

VII. PERFORMANCE

A. The pump, piping, and all other materials shall be installed according to the manufacturer’s instructions.

B. The pump shall be protected against freezing conditions during installation.

C. The Contractor shall coordinate the construction start date with the Contracting

Officer. The project shall be completed and available for use within 120 calendar days from the date the Notice to Proceed (NTP) is issued. Additional time will be allowed, if needed, to obtain permits and lead times for materials. Construction will not continue on Saturdays, Sundays, or Federal Government holidays without prior permission of the Contracting Officer.

D. During the performance period of the contract, the Contractor shall be available for conference calls as needed with the Contracting Officer, the Contracting Officer’s

Representative (COR), and the Government On-Site Inspector to discuss project progress and/or problems.

E. The Contractor shall obtain all permits and licenses, pay all fees and taxes, and give the notices necessary to perform the services of the contract. The Contractor shall submit all permits and licenses, and receipts for all fees and taxes paid.

F. The Contractor shall be liable for damages to roads, utilities, structures, and property, due to any act, omission, neglect, or misconduct during the period of performance of the services of this contract, unless the Government provided that portion of work that directly damaged one of these items.

G. The Contractor is responsible for completing the job to the specifications outlined in this document. The presence of an inspection does not preclude the Contractor from following this document and the specifications outlined.

VIII. PROJECT REQUIREMENTS

A. Any removal of materials not outlined in this project shall be placed in a condition the same, or better, prior to the start of the project.

B. All materials and workmanship shall have a one-year warranty of work.

C. All estimated quantities can be found in the bid schedule and/or reports.

D. All materials that are replaced or removed is the property of the Contractor. If

USFWS wants any parts, the contract will be modified to incorporate the change in the contract.

E. All specific materials listed in the reports are considered or equal.

F. Well permits provided after award, upon request from contractor.

G. All wells

1. Target maximum production capability listed below

2. Install meter on pipeline and certify the meter, which requires a bump to ensure full pipe

3. Test all wells with a test run to ensure all equipment is properly installed. The test run should be recorded and shared with local staff or be inspected by local staff.

H. Well #4

1. Well is 437 feet

2. Pump setting is 112 feet

3. Static water level is 36.8 feet

4. Maximum production is 1400gpm

5. Install:

a. High efficient motor – 60HP

b. Seal plate

c. Modify open line shaft pump

d. Replace 10LF of 10” column pipe

e. 10x10x16 Flowise discharge head with mechanical seal and discharge bearing

f. Waterlube spiders, 4 dry run x 9 standard

g. Head nipple

h. 5LF of top column

6. Repair:

a. Gould 12DHHC bowl assembly and bearings

I. Well #7

1. Well is 782 feet

2. Pump setting is 34 feet

3. Static water level is 15 feet

4. Maximum production is 2000gpm and needed minimum is 1,000gpm

5. Remove free flow plumbing and valve cap of flange

6. Install

a. New pump with VFD

b. Seal plate

c. Pump column with 3/16 stainless steel shaft with 10” drop pipe

d. 4 dry run bearing spiders

e. 6 standard spiders

f. 10” discharge pipe with Glotech meter with pulse output

g. Pump controller in NEMA2 enclosure with 3% load reactor

h. Motor

7. Repair

a. Can pump with open line shaft and mechanical seal with water lube

J. Well #57

1. Well is 172 feet

2. Pump setting is 70 feet

3. Static water level is 50 feet

4. Maximum production is 1300gpm

5. Install

a. New pump motor and pump

b. Well has a collapsed 63 feet beyond 172. Clean out well, install gravel pack, and install liner.

c. 8” pump column along with modification above ground to accommodate pipe size change.

d. Repair discharge structure

6. Replace

a. Electrical leads and conduit to pump from service panel

K. Well #60

1. Well is 1401 feet

2. Pump setting is 66 feet

3. Static water level is 16 feet

4. Maximum production is 2000gpm

5. Do not modify meter, bump, and piping.

6. Install

a. VFD

b. Open lineshaft pump, size 12 ¾ in column and 1-3/16” stainless steel

c. 3 dry run spiders 1-3/16x12”

d. 4 standard spiders 1-3/16x12”

e. Discharge head 12x12x16”

f. 50 HP motor

g. Mechanical seal with discharge bearing FW12x1-3/16”

h. Pipe support

i. Pressure tight seal plate

L. Clayton Well #C-72, excludes all well section (VIII.F)

1. Located at Baca NWR

2. Extend height of top of pipe by 2 feet

3. Pipe will need pipe supports

4. Flow is strictly artesian flow

5. Replace shutoff valve on 4” pipe

6. Photos shown below of well

IX. POINTS OF CONTACT

A. Refuge Manager

1. Suzanne Beauchaine (719-588-3473)

B. Contracting Officer Representative / Technical Representative

1. Michael Wandersee (720-813-8224)

END OF STATEMENT OF WORK