STATEMENT OF WORK

Demolition, Removal and Disposal of an abandoned Residence (approx. 912 sq.ft) and the adjacent garage/shed (640 sq. ft). Residence is located within the Klamath Marsh National Wildlife Refuge, 21401 Silver Lake Rd. Chiloquin OR 97624

1. GENERAL:

The U.S. Fish & Wildlife Service, Klamath Marsh National Wildlife Refuge (KMNWR) has a need to demolish and remove a single story 2 BR house and the adjacent garage/shed. The site is approx. 12 miles west of 21401 Silver Lake Road, Chiloquin OR. The buildings were inspected/tested for asbestos on 12/2/21. A single window in the garage was found to have a sealant which contained 1-2 lbs of chrysotile asbestos (2% content). This contract will include the removal of the window/sealant in accordance with Federal/State/County asbestos removal and its proper disposal. In addition to the demolition of both the residence and garage this contract will include removal and proper disposal of all wastes according to State and County regulations. After demolition and debris removal, the site will be returned to a flat, natural landscape with no materials or debris remaining at the site.

The need for this demolition is a Safety Item.

2. SCOPE:

Contractor will provide any equipment and labor for demolition and removal and disposal of all demolition wastes. Access to site is by gravel/dirt roads and is passable for heavy trucks and transports. During fire season, special conditions may occur for accessing the site and doing any demolition or haulage work. In addition, all equipment accessing the site must be cleaned prior to arrival to prevent the spread of noxious weed seed. KMNWR personnel will be available to provide access to the site on will be available during the demolition process.

3. PLACE/DELIVERY AND PERIOD OF PERFORMANCE:

Klamath Marsh NWR 21401 Silver Lake Rd Chiloquin, OR 97624

Work needs to be completed no later than December 31, 2022 preferred time frame would be as soon as possible.

4. INSPECTION AND ACCEPTANCE:

All work included in the contract specifications shall be subject to inspections by the U.S. Fish and Wildlife Service at periodic intervals during performance of this contract. Final acceptance shall be based upon satisfactory completion of the work in accordance with the specifications on a task by task basis.

5. AVAILABILITY:

Normal FWS duty hours are Monday thru Friday, 8:00 AM – 4:30 PM. In the event of emergencies, the Vendor shall provide contact information. FWS Non-duty hours include weeknights, weekends, and Government holidays but FWS personnel can be available if weekend or extended hours are needed by the contractor for job completion.

6. MATERIAL:

Vendor will supply all needed equipment and labor for removal and demolition of the structures and remove/haul all debris/materials to an approved county or state waste disposal site.

7. TECHNICAL COORDINATOR:

Mike Johnson - Refuge Mgr- KMNWR Phone: (541) 783-3380 Email: Michael_r_johnson@fws.gov

Jeremy Welch – WRS, KMNWR Phone: (541) 783-3380 Email: Jeremy_Welch@fws.gov

File details come from the government source that posted it. Updated .