| DIVISION 15, | SECTION 15193 |
| MECHANICAL | HEATING OIL TANK SYSTEM |
PART 1 - GENERAL
WORK DESCRIPTION. Contractor shall provide:
1. Tank:
One (1) new double walled 500 gallon heating oil tank system shall be constructed to meet Steel Tank Institute F921, Appendix D and UL 142 and UL 2080 requirements. Tank shall comply with NFPA 30A fire resistive performance. Tank shall be cylindrical in shape and mounted on structural steel beam skids that are an integral part of the tank with the proper nameplates for a supported tank system.
Tank shall have ports that are raised and broadened such that there are no depressions around port openings, to prevent ice, snow or liquids from pooling around tank openings. Several items listed in these specifications may be deviations from your standard tanks and therefore careful review of these specifications and close contact with the CO are very important. Provide ports for filling, suction, fuel quantity gauge, interstitial leak detection, , one for normal venting of the primary tank, two for emergency venting of the primary and secondary tank and one spare port for the primary tank plugged with an approved cast iron plug and a frost proof drain valve.
Appurtenances:
1. Marine grade coating system, gray color
2. One (1) each normal vent pipe long enough to be twelve (12) feet above ground level.
3. One (1) each normal vacuum pressure vent set below the pressure of the emergency vents
4. Two (2) each emergency vent pipes long enough to be two feet above the top of the tank
5. Two (2) each emergency vacuum pressure vents for the emergency vents.
6. One (1) each overfill containment basin with a flow back drain
7. One (1) each OSHA approved end mounted ladder
8. One (1) each anti siphon valve sized for this tank system
9. One (1) each interstitial leak detection indicator
10. One (1) each clock type battery powered alarming fuel quantity gauge
11. Fill and suction tubes
12. System shall arrive as completely assembled and as ready for use as possible.
2. All services and labor to remove and dispose of the existing 500 gallon dw heating oil tank system. Provide a work plan as to how this will be accomplished complete with cost proposal. The existing tank system will have approximately 20-25 gallons of fuel in it.
3. All services and labor to install the new heating oil tank system in the designated place at 1412 Airport Way, Fairbanks, Alaska 99701 and connect this system to the building heating system. Run an operational test and provide the government with manufacturers instructions. Provide a work plan as to how this will be accomplished, complete with cost proposal.
DELIVERY REQUIREMENTS: The delivery site is The availability of equipment in interior Alaska and surrounding remote areas is unknown. The government has no equipment or resources to transport or deliver the tank system and no government furnished equipment is part of this contract. The Contractor has full responsibility for the tank until it is delivered FOB to the site. Contact with the US Fish and Wildlife Service Contracting Officer is encouraged before submitting proposal package.
CONTACTS:
Contracting Officer (CO):
Contracting and General Services 1011 East Tudor Road Anchorage, Alaska 99503
SUBMITTALS:
Contractor shall submit shop drawings for the tanks and all appurtenances for approval prior to manufacture. Show:
1. Principal dimensions
2. Color
3. Markings
4. Weight
5. Warranty information
6. Port locations
7. Port markings
8. Vents
9. Vent piping
10. Ladders and
11. Skids
12. Maps
13. Installation documents Provide one hard copy on 2’X3’ paper and one electronic copy. When comments are made to initial submittal, Contractor shall highlight those changes in subsequent submittals.
Contractor shall submit product data to include manufacturer's literature, printed installation instructions, diagrams, test results and parts lists. Descriptive literature shall be exact, no assumptions are made and no substitutions are allowed without prior written approval. Provide data to include but not be limited to the following:
1. Coating system
2. Anti-siphon valve 3 Interstitial leak detection indicator
4. Clock type fuel quantity gage
PART 2 - PRODUCTS
Tank:
UL listed, aboveground, double wall heating oil fuel storage tank.
Ports:
1. A fill port
2. A suction port
3. A fuel level gauge port
4. An interstitial leak detection port
5. One (1) normal vent port for the primary tank.
6. Two (2) emergency vent ports, one for the primary tank and one for the secondary tank...
7. One spare port for the primary tank, locate near the fuel level gauge port
Markings: Mark each tank with the manufacturer's name, trade name, or trademark or other descriptive marking by which the organization responsible for the product can be identified. If a manufacturer produces tanks at more than one factory, each tank shall have a distinctive marking by which it can be identified as the product of a particular factory. Each tank shall also be marked with:
| DIVISION 15, | SECTION 15193 |
| MECHANICAL | HEATING OIL TANK SYSTEM |
15193-3
"NO SMOKING" signs on each side
“TYPE (HEATING OIL)” signs on each side
“SIZE (500 Gallons)” signs on each side
UL 142 and UL 2080 nameplates permanently attached to the tank system
NFPA Chemical hazard label
The required markings shall be embossed, etched, stamped on a nameplate of corrosion resistant metal, or as described below. The markings shall be in a size and style of type corresponding to 18 point Franklin Gothic [1/4 inch high letters] or the equivalent. The nameplate shall be attached by welding or brazing or by attaching it by drive screws, rivets, welding, or brazing to a bracket or holder that is then welded or brazed to the tank.
If a pressure-sensitive label, ink or paint stenciling, or other method is used, it shall comply with the requirements in the Standard for Marking and Labeling Systems, UL 969; be suitable for outdoor use and exposure to fuels and gasoline; and have a minimum surface temperature rating of 140o F.
The nameplate shall be secured to the primary and secondary tank.
All ports shall be marked.
APPURTENANCES:
All materials used in fabrication shall be compatible with the base tank, flammable and combustible liquid, and the physical and atmospheric conditions where the device is used. Polymerics and elastomers shall be evaluated for compatibility with fluids, surface, or atmospheric conditions with which the part comes in contact. These materials shall comply with the requirements for gaskets and seals, UL 157. All accessories shall be constructed to minimize the stresses on the base tank.
Vents:
Provide two vacuum emergency vents sized to fit and operate with the vent pipes.
Provide one normal vacuum vent sized to fit band operate with the vent pipe.
Vent pipes:
Tank vent pipes for emergency venting shall be of a length to terminate a minimum of two (2) feet above the top of the tank or as code allows. Vent pipes shall be properly sized.
The vent pipe shall be of a length to terminate a minimum of twelve (12) feet above grade or as code allows. Vent pipe shall be properly sized.
Spill containment basin:
Containment basin shall be attached to tank system. It shall hold a minimum of seven (7) gallons. It shall have a push-type access drain for spilled product and a lockable lid. The overfill sump shall not extend into the top of the main tank such that filling of the main tank is restricted from normal fill rates. Sump shall be less than 12" above top of the tank.
| DIVISION 15, | SECTION 15193 |
| MECHANICAL | HEATING OIL TANK SYSTEM |
15193-4
Access ladder and/or platform: Ladders shall comply with the construction requirements in accordance with the current edition of Occupational Safety and Health Standards, Title 29 of the Code of Federal Regulations, Part 1910, Subpart D, Section 1910.27 - Fixed Ladders. Ladders shall support a static load of 1000 pounds.
Coating System:
Apply coatings according to manufacturer’s recommendations. Paint shall be for use in an extreme marine environment. Primer to be high solids primer compatible with finish paint. Final color shall be Amershield 1046 (desert sand) or approved equal.
Anti-siphon devices:
EBW Anti-siphon valve, OPW 199ASV Anti-siphon valve or equal. Valve shall have adjustable head pressure range and include an internal pressure relief valve. Provide installation instructions. Provide isolation valves for ease of maintenance.
Interstitial leak detection indicator:
Krueger Sentry Gauge model K-2 or equal. Vertical type leak monitor to detect leaks in the interstitial/annular space of a double wall tank.
Clock type fuel quantity gauge with alarm:
Morrison 918F or equal. Clock type gauge and alarm. Gauge shall read in feet and inches with built in battery powered high level warning alarm. Gauge can be rotated 360 degrees after mounting. Place ports for gauge to be convenient to view from fill port.
Fill/Suction tubes:
Provide fill and suction tubes of aluminum material, located at opposite ends of the tank. The fill pipe shall be provided with a means for making a direct connection to common fuel truck apparatus, so the delivery of fuel is not exposed to the open air during the filling operation. The fill tube shall extend to within 6" of the tank bottom.
Piping Systems:
Piping, joints, valves, and fittings shall comply with NFPA 30. Joints shall be made liquid tight and shall be threaded, except that listed flexible connectors may be used when installed in accordance with NFPA 30. Piping systems shall contain a sufficient number of valves to operate and protect the system. Piping systems in connection with pumps shall contain a sufficient number of valves to properly control the flow of liquid in normal operation and in the event of physical damage.
REFERENCES:
| ANSI B31.4 | - | Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids • |
| ASTM A36 | - | Standard Specification for Carbon Structural Steel. |
| ASTM A395 | - | Standard Specification for Ferritic Ductile Iron Pressure-Retaining Castings for Use at Elevated Temperatures |
| ASTM A569 | - | Standard Specification for Steel, Carbon (0.15 Maximum, Percent), Hot-Rolled Sheet and Strip Commercial (Withdrawn 2000) |
| NFPA 30 | - | Flammable and Combustible Liquids Code |
| STI 921 | - | Fabrication Instructions for Double Walled Aboveground Tanks |
| STI F941 | - | Thermally Insulated Aboveground Storage Tanks |
| UFC 79 | - | Flammable and Combustible Liquids |
| UL 142 | - | Aboveground Tank for Flammable Liquids on Supports |
| UL 157 | - | Standard for Gaskets and Seals. |
| UL 525 | - | Standard for Flame Arrestors for Use of Vents of Storage Tanks for Petroleum, Oil, and Gasoline |
| UL 2080 | - | Fire Resistive Tanks for Flammable and Combustible Liquids |
| 40 CFR 112 | - | Oil Pollution Prevention and Response; Non-Transportation-Related /Onshore and Offshore Facilities |