EDIS REPLACE HEAT PUMPS AT GLENMONT MANSION
Solicitation number
140P4526Q0018
Issued by

About this file

This is a Scope of Work document for the replacement of five water source heat pumps at Glenmont Mansion, part of the Thomas Edison National Historical Park in West Orange, New Jersey. The project involves removing five existing 5-ton water source heat pumps that have reached the end of their service life and installing five new medium-efficiency replacement units compatible with the existing geothermal loop system.

The removal phase requires disconnecting electrical, piping, and controls; draining and capping water lines; removing existing units and supports; and disposing of old equipment per EPA and local regulations. The installation phase includes furnishing and installing five new 5-ton water source heat pumps with minimum efficiency ratings of EER 15.0 and COP 4.5 or higher, reconnecting all piping and electrical systems, installing vibration isolation pads, insulating piping, and verifying leak-free connections. The testing and commissioning phase requires functional testing of heating and cooling operations, integration with the KMC building automation system, water flow balancing, and provision of start-up reports and commissioning documentation. Equipment must feature heavy-gauge galvanized steel cabinets with sound insulation and use EPA-approved refrigerants. Contractor must provide operation and maintenance manuals and training for National Park Service staff. The project period is 90 calendar days from Notice to Proceed, with work hours limited to Monday through Friday, 7:30 AM to 3:30 PM. Equipment warranty requires a minimum of five years on compressors and one year on parts, with one year labor warranty on installation workmanship. Work must comply with OSHA safety standards, ASHRAE 90.1 energy efficiency standards, and EPA refrigerant handling guidelines while protecting historic finishes and structures. The Contracting Officer's Representative is Peter Hepp and the Project Manager is Tim Stauffer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work - Replacement of (5) Water Source Heat Pumps at Glenmont Mansion

Location: Glenmont Mansion – Thomas Edison National Historical Park, 119 Park Way, West Orange, NJ 07052.

1. Background The Glenmont Mansion, part of the Thomas Edison National Historical Park, utilizes a geothermal system to provide heating and cooling. (5) water source heat pumps, each rated at 5 tons, have reached the end of their service life and require replacement to maintain system efficiency and reliability.

2. Objectives The objective of this project is to remove and replace (5) existing water source heat pumps with new, medium-efficiency units compatible with the existing geothermal loop system. The work must be completed in compliance with National Park Service standards, local building codes, and environmental regulations.

3. Scope of Work A. Removal

• Disconnect electrical, piping, and controls from existing heat pumps.

• Drain and cap water lines as necessary.

• Remove existing heat pump units and associated supports.

• Dispose of old equipment per EPA and local regulations.

B. Installation

• Furnish and install five (5) new water source heat pumps, each rated at 5 tons.

• Ensure compatibility with the existing geothermal system.

• Reconnect piping, electrical, and controls.

• Install vibration isolation pads and insulate piping.

• Verify leak-free connections and proper mounting.

C. Testing and Commissioning

• Test heating and cooling operation for each unit.

• Integrate into basic control capability to the Building automation system, KMC system

• Balance water flow and verify system performance.

• Provide start-up report and commissioning documentation.

4. Technical Specifications

• Capacity: 5 tons per unit.

• Efficiency: Minimum EER 15.0 and COP 4.5 or higher.

• Refrigerant: EPA-approved

• Controls: Compatible with existing building automation system.

• Construction: Heavy-gauge galvanized steel cabinet with sound insulation.

5. Warranty

• Equipment: Minimum 5 years on compressor, 1 year on parts.

• Labor: Minimum 1 year on installation workmanship.

6. Environmental & Sustainability Compliance

• Meet ASHRAE 90.1 energy efficiency standards.

• Follow EPA refrigerant handling and disposal guidelines.

• Minimize waste and recycle materials where possible.

7. Deliverables

• Equipment submittals prior to installation.

• Operation and maintenance manuals.

• Training for NPS staff on system operation.

8. Period of Performance

• Duration: 90 calendar days from Notice to Proceed.

• Work Hours: Monday through Friday, 7:30 AM to 3:30 PM.

• No work on weekends or federal holidays.

9. Safety and Compliance

• Comply with OSHA safety standards.

• Protect historic finishes and structures during work.

• Maintain clean and secure work areas.

Contracting Officer’s Representative (COR): Peter Hepp Project Manager: Tim Stauffer