This is a Statement of Work for the Colorado River Indian Irrigation Project (CRIIP) focused on the delivery of pre-blended 7 sack dry mix concrete, commonly referred to as Gunite, to support irrigation canal repairs in Poston, Arizona within La Paz County on the Colorado River Indian Tribe (CRIT) Reservation. The Bureau of Indian Affairs (BIA) requires the contractor to provide and deliver Gunite throughout the CRIIP irrigation system on an as-needed basis under an Indefinite Delivery, Indefinite Quantity (IDIQ) contract vehicle. The base required quantity is 1,088 cubic yards, ordered per truck load with each truck load consisting of approximately 8 cubic yards of material. The Gunite mix specification requires a 7:1 ratio of 7 parts Gunite to 1 part Sand Mix Code 80015.

The contractor must supply all required tools, equipment, materials, management, labor, and subject matter experts necessary to successfully process, mix, and deliver the material. Key contractor responsibilities include project management with designated point-of-contact coordination with the Contracting Officer Representative (COR) and Technical Representative(s) to schedule deliveries and inspect material for specification compliance. The place of performance is within the CRIT Reservation boundaries with the main meeting location at the Irrigation Office Building OT-1, 21051-3 E. Poston Road, Poston, Arizona 85371. The period of performance is anticipated to be a maximum of 365 days from notice-to-proceed. The government point of contact is Manuel A. Ramirez Sr., Supervisory Irrigation Maintenance Specialist, Colorado River Agency – Irrigation O&M, reachable at (928)-669-0305 or Manuel.ramirez@bia.gov.

View the file

Other files

File Type Posted
Sol_140A1126Q0082_Amd_0001.pdf PDF
Sol_140A1126Q0082.pdf PDF
IA_-_IEE_Representation_Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Colorado River Indian Irrigation Project (CRIIP) Delivery of Pre-blend 7 sack dry mix (Gunite)

Poston, Arizona - LaPaz County

1.0 NEED

Material (e.g. Pre-blend 7 sack dry mix concrete (Gunite) needed for repair of the CRIIP concrete line irrigation canal system. Due to high summer temperatures, the demand for farmland irrigation water is elevated. Due to the increased need for irrigation water the windows, in between watering cycles, for CRIIP system repair is extremely narrow.

2.0 RISK

The Bureau of Indian (BIA) is obligated by Trust responsibilities to manage and deliver irrigation water for the Colorado River Indian Tribe (CRIT). The BIA also collects pre-payment of irrigation water deliveries from local water users; local water users mainly consist of crop farmers. Due to the Trust responsibilities and collection of pre-payments for irrigation water, the BIA is now morally and legally responsible to complete the mission of delivering the irrigation waters through the CRIIP system. With portions of the irrigation system unable to safely and efficiently deliver irrigation waters, the BIA is open to tort claims from water users for damage to crops and lawsuit from the tribe for violation of Trust responsibilities.

3.0 BACKGROUND

The CRIIP system provides irrigation water for agricultural use on the CRIT Reservation. Construction of the CRIIP irrigation system first started in 1867. The water for the Project comes from the Colorado River through the main canal headworks located at the Headgate Rock Dam (HGRD). CRIT holds approximately 24% of Arizona’s water rights to the Colorado River, which is delivered through the CRIIP system. Farms lands located within the boundaries of the CRIT Reservation total approximately 80,000 acres. The estimated total annual crop value is approximately $144 Million.

4.0 OBJECTIVE

With the Arizona summer heat fast approaching, imminent danger to, and destruction of crops has raised the severity level of the required repairs to extremely high. The safe, reliable, and effective repairs of the CRIIP irrigation canals are an urgent need to prevent damage to farm crops and meet BIA Trust responsibilities. The objective of this effort is for the contractor to provide pre-blended 7 sack dry mix concrete (Gunite), hence forth referred to as Gunite. The identified material is intended to be supplied under an Indefinite Delivery, Indefinite Quantity (IDIQ) contract.

4.0 SCOPE

The scope of this effort is for a contractor to provide and deliver Pre-blend 7 sack dry mix concrete (Gunite) throughout the CRIIP irrigation system, on a as needed basis. Material shall meet identified specifications. The contractor shall supply all required tools, equipment, materials, management, labor, and Subject Matter Experts (SME’s) required to successfully process, mix, and deliver the identified material.

5.0 REQUIREMENTS

5.1 Project Management

5.1.1 The Contractor shall be responsible for ensuring the accuracy, timeliness, and completion of identified requirements in this work statement.

5.1.2 Due to the quick response and reaction required by this project, the contractor shall provide a point of contact (POC) who shall work with the government Contraction Officer Representative

(COR) and the Contracting Officer Technical Representative(s) to,

5.1.2.1 Schedule delivery of requested material (e.g. Gunite Concrete),

5.1.2.2 Inspect delivered material to ensure compliance with identified specifications.

5.2 Pre-blended 7 sack dry mix concrete (Gunite)

Contractor shall prepare, mix and deliver Gunite to CRIIP construction sites. Construction sites may be anywhere throughout the Colorado River Indian Tribal (CRIT) Reservation.

5.2.1 Quantities ordered by the government will be ordered per truck load. Each truck load will consist approximately of 8 Cu. yrd. of material.

5.2.1.1 Base required quantity – 1088 yards

5.2.2 The Gunite mix shall consist of a ratio of 7:1, meaning 7 parts Gunite to 1 parts Sand

Mix Code 80015

6.0 PLACES OF PERFORMANCE

The place of performance shall be within the boundaries of the CRIT Reservation, Poston, Arizona, La Paz County.

• Main Meeting Location:

Irrigation Office Building OT-1

21051-3 E. Poston Road Poston, Arizona 85371 La Paz County

7.0 PERIOD OF PERFORMANCE

7.1 Period of Performance:

The period of performance for this contract is anticipated to be a maximum of three hundred and sixty-five (365) total days from notice-to-proceed.

8.0 POC INFORMATION

Manuel A. Ramirez Sr.

Supervisory Irrigation Maintenance Specialist Colorado River Agency – Irrigation O&M 121241st. Ave.

Parker, AZ. 85344 Cell: (928)-669-0305 Work: (928)-662-4392 E-mail: Manuel.ramirez@bia.gov

1.0 NEED
2.0 RISK
3.0 BACKGROUND
4.0 OBJECTIVE
4.0 SCOPE
5.0 REQUIREMENTS
6.0 PLACES OF PERFORMANCE
7.0 PERIOD OF PERFORMANCE