A04_-_SOW.pdf
PDF 163 KB Posted
- Attached to
- PR VIEQUES NWR HQ/VC BLDG REHAB
- Solicitation number
- 140FHR24R0009
About this file
This document is a Statement of Work (SOW) for construction services to rehabilitate the Headquarters/Visitor Center Building at the Vieques National Wildlife Refuge due to damage from Hurricane Fiona. The key tasks include repairing the roof, detecting and mitigating mold, replacing gates and fencing, repairing and repainting the exterior, designing and replacing the backup water system, replacing security lighting and removing the video system, and replacing the flag poles. The SOW also includes general construction requirements, communication protocols, payment procedures, safety requirements, and closeout procedures. The related federal contract opportunity is solicitation 140FHR24R0009 for the Headquarters/Visitor Center Building Rehabilitation Project, issued by the Department of the Interior's Fish and Wildlife Service. The period of performance is 90 days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FHR24R0009.pdf | ||
| B03_-_DOL_Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vieques NWR HQ Bldg Rehab Project Page 1 of 8
STATEMENT OF WORK
FOR
CONSTRUCTION ONLY SERVICES PROJECT
ON
HEADQUARTERS/VISITOR CENTER BUILDING
AT
VIEQUES NATIONAL WILDLIFE REFUGE
BACKGROUND:
The Vieques National Wildlife Refuge (NWR) requires extensive rehabilitation/repairs on the damaged Headquarters/Visitor Center Building due to Hurricane Fiona of 2022. This Statement of Work (SOW) defines all the required tasks to repair the damages. The material and performance specifications for the Construction Services tasks are incorporated in the project description below. Consult any changes or recommendations with the Contracting Office Representative (COR).
Any dimensions provided below are approximate in nature. The contractor shall verify all dimensions and note such dimensions on the submitted proposal. Product data submittals shall be required for all construction materials proposed herein.
DESCRIPTION OF WORK:
General Requirements: Construction Services Task – Repair Roof
1. Contractor shall inspect and repair damaged fully adhered roof systems, as leaking has been detected in the exhibit hall, restrooms, breakroom, hallways, and back entry.
2. Task shall include re-attaching the firestone roof seams and reseal. Resealing the roof around all protrusions to include the roof-mounted HVAC pedestal system any water-damaged/rotted plywood and re-attaching gutter system.
3. All replacement components shall match to pre-existing roofing materials and color scheme.
General Requirements: Construction Services Task – Perform Mold Detection
1. Task shall consist of conducting a mold evaluation and detection of the interior of the building.
Submit a Mold Detection Plan prior to performing the tests, this should include type of tests, quantity, and areas where tests will be performed.
2. Upon receiving results of the mold evaluation/inspection, Contractor shall notify the Service of the results.
General Requirements: Construction Services Task – Replace Gates and Fencing
1. Task shall consist of inspecting and replacing the 12’ wide slide metal main security access gate (visitor vehicle entry), motor and components.
2. Gate shall be replaced with battery-powered electric gates that utilize solar power.
Vieques NWR HQ Bldg Rehab Project Page 2 of 8
3. Task shall consist of inspecting, patch and replace damaged sections of fencing around HQ building to match existing material, color and design.
General Requirements: Construction Services Task – Repair and repaint Building Exterior
1. Task shall consist of power washing, priming, and painting approximately 4000 SF of building exterior.
2. Task shall include repairing exterior cracks and sanding bubbled surfaces.
3. Task shall include repairing and replace entrance soffit on awning’s underside, to include components, paint and corresponding drainage system.
4. Paint and primer products basis of design shall be Behr Marquee or equal to, 100% acrylic, exterior / interior, mildew resistant, VOC less than 50 g/L, performance data shall comply with ASTM D2486 over 2500 cycles, ASTM D3273 and ASTM D4587. Color to be selected by station.
General Requirements: Construction Services Task – Design & Replace Back-up Water System
1. Task shall consist of removing the inoperable emergency back-up water system.
2. Task shall consist of installing a water system consisting of, minimally, a 600-gallon water storage tank and one pressure pump system rated for 640 gallons, not frequency variable variant.
3. Task shall include the inclusion of a photovoltaic battery backup system exclusively for the water system. Primary power of the system must be connected to the existing power panel.
Secondary power for the new water system shall be the pre-existing generator.
4. Design to consider connecting to potable and roof rain collection systems.
5. Remove existing and install a latched gate and fencing around the new system.
General Requirements: Construction Services Task – Replace Security Lighting and Remove Video System
1. Task shall consist of replacing the security lighting system with a solar powered backup option.
There are two (2) free standing light posts one of which has two extension lighting arms.
2. Task shall consist of inspecting and replacing 12 exterior lights attached to the exterior walls.
Task shall also include the removal of four (4) motion sensors.
3. Task shall consist of removing and not replacing the old exterior security camera system. This old system consists of two (2) non-functional static cameras, one (1) non-functional PTZ camera and three (3) camera motion sensor systems.
4. All installed lighting shall be of a color that minimizes impact to wildlife.
General Requirements: Construction Services Task – Replace Flag Poles
1. Task shall consist of replacing three (3) flag poles with three (3) 15ft tall poles.
2. New poles shall be constructed of commercial grade aluminum able to withstand hurricane force winds.
3. Shall be located on existing cement slab for flag poles in the front side of the building.
General Requirements: Construction Service Task – Exterior security door and interior system.
1. Task shall consist of inspect and replace two (2) exterior security doors (front and side of bldg.).
2. Repair faulted interior door alarm system and associated magnetic door lock system.
OPTION TASK
General Requirements : Construction Services Task – Perform Mold Mitigation (OPTION LINE).
1. Upon receiving results of the mold detection/evaluation/inspection, Contractor shall notify the Service of the results and provide treatment as deemed necessary by the inspection results
Vieques NWR HQ Bldg Rehab Project Page 3 of 8 report.
GENERAL NOTES:
A. The Contractor shall coordinate with the Refuge on appropriate stockpile locations for demolished and/or excess materials.
B. The Contractor is responsible for the security of materials. The Contractor shall provide secured areas deemed necessary for the protection of their materials.
C. Coordinate with refuge staff for safety and operational requirements.
D. PERIOD OF PERFORMANCE: 90 days.
E. DEFINITIONS
1. Commissioning is the act of statically and dynamically testing the operation of equipment and building systems to ensure they operate as designed and can satisfactorily meet the needs of the building throughout the entire range of operating conditions.
2. Construction is defined as, but not limited to, constructing (giving form by combining the parts), altering, repairing, adding to, subtracting from, improving, restoring, moving, wrecking or demolishing any building, highway, road, excavation or other structure, project, or improvement attached to real estate.
3. Contracting Officer (CO) is defined as a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the United States of America. The term includes certain authorized representatives of the Contracting Officer such as the Construction Specialist (CS), Contracting Officer's Representative (COR), Construction Representative (CR) and Site Representative (SR) acting within the limits of their authority as delegated by the Contracting Officer.
4. Day or Days shall mean calendar days unless otherwise specifically noted.
5. “Service” or “FWS” means United States Department of Interior, Fish and Wildlife Service, Region 4 (Southeast Region).
6. Government may also be referred to as the Owner, Contracting Officer, Contracting Officer's Representative, the Service, or Fish and Wildlife Service (FWS).
7. Incident Rate (IR) is the number of recordable incidents resulting in days away from work for each 100 full-time employees per year, based on 2,000 hours worked per employee per year.
8. Local Authority Having Jurisdiction: Duly adopted local code authority, agency, or serving utility governing or serving the location of the project.
9. Management Plan: Contractor's project approach for planning, design, and construction and includes, at a minimum, but is not limited to the following:
- Schedule
- Project Staffing Plan
- Safety Plan
- Subcontracting Plan
- Organization Chart with Roles and Responsibilities
- QA/QC Plan
- Commissioning Plan
10. DOI “Sustainable Building Assessment and Compliance Tool Construction Checklist for
Vieques NWR HQ Bldg Rehab Project Page 4 of 8
New Construction and Major Renovation Projects” and supporting documents. (This checklist will be furnished to the Contractors firm by the USFWS)
11. Notice to Proceed (NTP): There will be one NTP for this project issued by the Contracting Officer (CO) to initiate the construction phase. The NTP will identify any qualifications, limitations, or exceptions to the work.
12. Open Book Accounting is the right of the government to have free and open access to financial and accounting documents that the Contractor has associated with the project being completed.
13. Performance Specifications are specifications that state what the required results will be with measurable or observable criteria for verifying compliance.
14. Public Works is construction performed under a contract with a Federal, State, County, City, or other government entity.
15. Schedule is a chronological layout of the work to be performed prepared using commercially available scheduling software.
16. Subcontractor is any person or entity retained by the Contractor as an independent contractor to perform a portion of the Work and shall include material, labor and suppliers.
17. Sub-Subcontractor is any person or entity retained by a Subcontractor as an independent contractor to perform any portion of a Subcontractor's Work and shall include material, labor and suppliers.
18. Work is comprised of all permitting, construction and other services required by the Contract Documents, including procuring and furnishing all materials, equipment, services and labor reasonably inferable from the Contract Documents.
CONSTRUCTION SERVICES
A. GENERAL
1. Following the Issuance of the Construction NTP, the Contractor shall provide the following items to the COR at the Preconstruction Meeting for approval and amendment into the contract file.
a. A project schedule reflective of the critical path and other phases of the work.
b. A schedule of the planned site visits. The prime Contractor shall periodically, and at appropriate times, visit the site to inspect the construction. They shall prepare a site visit report for each visit and shall submit the reports to the COR within 5 calendar days after the visit. The reports shall include comments about overall quality and accuracy of the construction. The reports shall also note all deficiencies observed.
2. Possess and maintain, for the duration of this project, a state license as a general Contractor in the State the project is located, if required by the state.
3. Provide supervision, labor, materials, equipment, tools, construction equipment and machinery, inspection, testing, start-up, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work.
4. Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.
Vieques NWR HQ Bldg Rehab Project Page 5 of 8
5. Perform all construction activities efficiently and with the requisite expertise, skill, and competence to satisfy the requirements of the Contract Documents. At all times exercise complete and exclusive control over the means, methods, sequences, and techniques of construction.
6. Utilize Subcontractors who are duly licensed and qualified to perform the Work consistent with the Contract Documents. Government may reasonably object to Contractor's selection of any Subcontractor.
7. The Contractor is responsible for quality control of its own work and work performed by its subcontractors and their sub-subcontractors. Provide and pay for the services of an independent construction materials testing laboratory accredited by an acceptable laboratory accreditation authority. Laboratory shall sample and test materials and perform required special inspections. Laboratory shall be authorized to perform work in the state where project is located. Government may reasonably object to the Contractor’s selection of laboratory.
8. Assume responsibility for the proper performance of the Work of Subcontractors and all acts and omissions in connection with such performance. Nothing in the Contract Documents is intended or deemed to create any legal or contractual relationship between Government and any Subcontractor or Sub Subcontractor.
9. Coordinate the activities of all Subcontractors. If Government performs other work on the Project or at the Site with separate contractors under Government's control, Contractor agrees to reasonably cooperate and coordinate its activities with those of such separate contractors so that the Project can be completed in an orderly and coordinated manner without unreasonable disruption.
10. Minimize creation of construction, deconstruction, and demolition waste. Minimize factors that contribute to waste such as over-packaging, improper storage, ordering error, poor planning, breakage, mishandling, and contamination. Develop a Waste Management Plan to ensure that existing site and building materials are reused, salvaged, or recycled.
Unless modified by the CO, divert 50%, minimum, of total project waste from landfills.
Dispose of all materials not salvaged, reused, or recycled legally, off-site, in licensed disposal facilities.
11. Normal working hours are Monday to Friday from 7:00 am to 5:00 pm except for federal holidays, alternate work hours have to be approved by the COR. During normal working hours throughout the duration of the contract, promptly furnish information and provide reasonable facilities and access for obtaining information respecting: the character of the materials, condition of the work-in-progress, number of workers employed, their pay rate, time worked, inspection reports and test results from sampling and testing laboratories, and similar information.
12. Government buildings and other facilities are not available for storage of Contractor's materials, equipment, and tools except for designated staging areas. Government owned equipment is not available for Contractor's use to accomplish any Work.
13. Housing for workers and campsites are not available on site.
14. Furnish all temporary facilities and utilities needed including heat, light, power, water, telephone, sanitary facilities, job offices, material handling equipment, temporary construction aids, and storage enclosures. The Contractor is responsible for all temporary connections and disconnections.
Vieques NWR HQ Bldg Rehab Project Page 6 of 8
15. Permits. It is the responsibility of the Contractor to obtain all permits and pay all permitting fees required for this project. The Contractor is responsible for providing permitting drawings, engineering data and other technical information required by the permitting authority.
B. COMMUNICATION
1. The FWS Project Manager must be in the information loop for Quality Assurance purposes.
a. RFI Process: Unless a more stringent protocol is accepted in the Management Plan, the Contractor shall utilize the following protocol:
(i) Utilize a RFI Form: All supplemental information and answers to questions shall be documented on Request for Information (RFI) forms. The Contractor may use any format they choose for the Request for Information form but all shall be identified with the words “Request for Information” at the top of the form along with the Government Contract Number, Project Location (Vieques NWR) Project Title and the Contractor’s Name.
(ii) Numbering: RFI’s shall be sequentially numbered, logged and filed and shall be part of the Closeout Documents submitted to the Government.
(iii) FWS Concurrence: As RFI’s are generated and answered, submit copies to the COR for review within 2 business days for concurrence via email .pdf format. A non-response from the COR within 4 days of receipt of the RFI will signify concurrence with the RFI answer. If the RFI is sent on a Friday, then Saturday and Sunday do not count as business days.
(iv) RFI Files Onsite: The Site Superintendent shall maintain a file of RFI changes.
This RFI file shall be subject to inspection by the FWS without advance notice.
b. Submittals: Unless a more stringent protocol is accepted in the Management Plan, the Contractor shall utilize the following protocol.
(i) Utilize a Submittal Register: Develop a submittal register and update this register as submittals and logged and processed.
(ii) Numbering: Submittals shall be sequentially numbered. A completed submittal register shall be submitted with the Project Closeout Documents.
(iii) FWS Concurrence: Provide the FWS Project Manager with (1) copy of the approved submittal and provide the FWS Construction Representative (1) copy of the approved submittal within (2) business days of the approval date.
(iv) Site Responsibility: The Contractor’s Site Superintendent shall maintain a file of approved submittals for reference purposes. This Submittal file shall be subject to inspection by the FWS without advance notice.
C. PAYMENT PROCEDURES
1. Measurement: No measurement of the work will be made unless unit prices are included in the project.
a. Note: Undocumented changes which did not follow the RFI process outlined above may be subject to delayed or non-payment.
Vieques NWR HQ Bldg Rehab Project Page 7 of 8
2. Schedule of Values: Prepare a Schedule of Values in the format of the American Institute of Architects (AIA) form number G702/703 Application and Certificate for Payment (or approved equivalent format). Submit a detailed Schedule of Values no less than 7 calendar days prior to the start of on-site construction work.
a. Payment Request Data: In addition to data required by the Contracting Officer: (1) Format the Schedule of Values to match the Schedule of Items and show sufficient additional detail to allow accurate calculation of monthly progress payments; and (2) Submit updated construction schedule identifying actual work complete.
D. PROJECT SAFETY
1. The Contractor shall have the ultimate responsibility for safety on the project site at all times, from issuance of the Notice to Proceed until final completion and acceptance of the project by the Contracting Officer. Ensure that all onsite activities, equipment, and facilities constructed by the Contractor, subcontractor, or supplier conform fully to the standards of the Department of Labor, Occupational Safety and Health Administration (OSHA) 29 CFR 1926 and 1910; and DOI and FWS policies. In addition, the Contractor shall adhere to all current Federal, State and local safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern.
2. Initiate and maintain, throughout the performance of this contract, an effective safety and health program that provides adequate policies, procedures, and practices to protect employees from, and allow them to recognize, job-related safety and health hazards. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections. Each employee (Contractor and subcontractors) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.
3. Provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel. Where project work affects public roads, provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD) as published by the US Department of Transportation, Federal Highway Administration.
4. Rollover Protection and Seat Belts: In addition to the Safety and Health requirements of clause Federal Acquisition Regulation (FAR) 52.236-13 of Part 2, Section I of this Contract, rollover protection and seat belts required by 29CFR 1926 (OSHA) shall be extended to include equipment regardless of the year of manufacture.
E. Protections:
1. Comply with all applicable federal, state, and local environmental laws and regulations.
This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, erosion control, surface runoff, and cultural resources.
2. Provide erosion control methods (such as watering dry soils) and appurtenances (such as silt fence) as necessary to prevent wind-borne dust and water-borne silt from leaving the immediate work area.
3. Immediately stop work if paleontological, archaeological or historical remains (including burials or skeletal material) are encountered, immediately stop the work and notify the
Vieques NWR HQ Bldg Rehab Project Page 8 of 8
Construction Representative, COR, or Contracting Officer. The Contracting Officer will notify the Regional Archaeologist so the provisions of 36 CFR 800.7 (Resource Discovered During Construction) and other relevant laws are followed. Work will cease in the immediate vicinity until permitted to resume by written order from the Contracting Officer.
Work in other areas may proceed as approved by the Contracting Officer.
4. Protect adjacent vegetation, property, structures, and improvements from damage.
5. Heavy equipment operated on FWS roads and parking areas shall comply with highway-legal load limits unless explicitly approved otherwise. Prior to operations, the Contractor and Contracting Officer will document condition of roads and parking. The Contractor is responsible for repairs of damage to roads and parking caused by their own actions.
6. Clearing limits and working limits are as shown on the drawings and approved in the field.
Do not remove any trees without prior COR field review and approval. If no clearing limits are indicated, contact the COR for clarification. Coordinate with the local FWS staff to select a construction staging area. Construction equipment and operations shall be contained within the work limits and staging areas.
F. Closeout Procedures
1. Training: Thoroughly familiarize the local FWS staff with the improvements and train them to be proficient in overall system operation and maintenance.
2. Tools and spare parts: Deliver to the project site all specialty tools, valve handles, fan belts, filters, spare parts, keys and similar devices such that the FWS staff is able to operate and maintain the work.
3. Maintenance Materials: Deliver maintenance materials to Station Manager, coordinate location of storage. (Provide consumable items in such quantities as needed for the first year of operation.)
4. Final Inspection: Submit a request in writing to the CO requesting the Final Inspection.
Notify the COR at least 10 calendar days prior to the anticipated date of completion of all work. The COR will proceed with Final Inspection as promptly as practicable. The time required for such Final Inspection and for making any corrections as a result thereof shall be included in the contract performance time. The Contractor representative responsible for the work shall be present at the Final Inspection and shall submit a preliminary list of unfinished work prior to Final Inspection.
END OF STATEMENT OF WORK