FIRE SPRINKLER INSPECTION(S) Federal contract opportunity
Solicitation number
140L0221Q0008
Issued by
Department of the Interior Bureau of Land Management Alaska Region

View the file

Other files for this federal contract opportunity

Other files attached to FIRE SPRINKLER INSPECTION(S), newest first.
File Type Posted
Sol_140L0221Q0008.pdf PDF
B03 WDOL.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

2021 ANNUAL FIRE SPRINKLER and FIRE ALARM INSPECTIONS

1. GENERAL

1.1. The BLM buildings listed in the Purchase Order require annual fire sprinkler and fire alarm inspections. The Contractor shall provide all necessary labor, equipment, and materials to perform the inspection, testing, and maintenance work required.

1.2. The work locations include Fort Wainwright, Fairbanks, Coldfoot, and Galena, AK.

2. DEFINITIONS

2.1. AAC - Alaska Administrative Code

2.2. AFS - Alaska Fire Service

2.3. AWWA - American Water Works Association

2.4. BLM – Bureau of Land Management

2.5. NFPA - National Fire Protection Association

2.6. NICET – National Institute for Certification in Engineering Technologies

3. REFERENCES

3.1. NFPA 13: Installation of Sprinkler Systems

3.2. NFPA 25: Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems

3.3. NFPA 72: National Fire Alarm Code

3.4. AAC: Title 13 Public Safety; Chapter 50 Codes & Standards; Section 35 Permit Required

4. QUALIFICATIONS

4.1. The Contractor shall be regularly employed in the business of installation, inspection, testing, maintenance and repair of water-based fire protection systems and fire alarm systems. The Contractor shall be a well-established business that has been in existence a minimum of five (5) years. The Contractor shall have on staff a Field Supervisor possessing a current permit issued by the Alaska State Fire Marshal according to 13 AAC 50.13 in the appropriate classifications for the type of work required. The Field Supervisor shall sign all forms utilized for inspection, testing, and maintenance.

4.2. All workmen shall be able and competent to perform the duties assigned to them. In the case of skilled labor, they shall be technicians who are adequately trained and experienced in the trade, who perform satisfactory work, and who have a minimum of two (2) years cumulative experience. All workers shall be under the direct supervision of the Field Supervisor.

4.3. The Contractor shall have on staff, or employ the services of, a technician possessing a Backflow Prevention Device Tester Certificate from the Municipality of Anchorage, or equivalent certificate recognized by AWWA.

5. SCOPE OF WORK

5.1. The Contractor shall conduct one (1) time, at each facility listed in the purchase order, the annual fire sprinkler system inspection and testing as required by NFPA 25. This work includes, but is not limited to, testing backflow prevention devices.

5.2. The Contractor shall perform one (1) time, at each facility listed in the purchase order containing a fire pump, the annual fire pump inspection and testing as required by NFPA 25.

5.3. The Contractor shall post Sprinkler Information Cards on each system and are properly initialed and dated for each facility listed in the purchase order.

5.4. The Contractor shall conduct one (1) time, at the specific facilities listed in the purchase order, an annual fire alarm system inspection and testing as required by NFPA 72.

5.5. The Contractor shall post Fire Alarm Information cards that are properly initialed and dated on each system for each facility alarm system inspected.

6. SCHEDULE

6.1. The Contractor shall prepare a written schedule, broken down by facility. This schedule shall be submitted to the AFS Facility Operations Branch Chief for review and approval a minimum of one week before inspection begins.

6.2. Sprinkler and fire alarm inspections at the Arctic Interagency Visitor Center in Coldfoot, AK shall be completed prior to July 15, 2021, but not before May 17, 2021.

The 6,000 sq. ft. facility contains a dry pipe system, with a 250 gpm fire pump. This system also contains two (2) backflow preventers, and one (1) jockey pump. The facility’s fire alarm system is a Siemens MXL-IQ.

6.3. Sprinkler and fire alarm inspections at the North and South barracks in Galena, AK shall be completed prior to July 15, 2021, but not before May 17, 2021.

North Barracks is 10,370 sq. ft. and contains a dry pipe system.

South barracks is 10,370 sq. ft. and contains a dry pipe system.

6.4. Sprinkler and fire alarm inspections at the Fairbanks District Office, 222 University Ave, Fairbanks, AK, shall be completed prior to July 1, 2021.

The facility is 50,297 sq. ft. and contains a wet pipe system and backflow preventer. The fire alarm system is a Pyrotronic System 3.

6.5. Sprinkler inspections at Ft Wainwright facilities shall be completed prior to July 30, 2021.

Building 1500 is 10,720 sq. ft. and contains a wet pipe system with a backflow preventer.

Building 1513 is 41,419 sq. ft. and contains a wet pipe system with two (2) 50/50 glycol loops for exterior zones and two (2) reducing pressure backflow preventers and (1) double check preventer.

Building 1544 is 25,182 sq. ft. and contains a wet pipe system with a 750 gpm fire pump.

Building 1003 is 90,000 sq. ft. and contains one (1) wet pipe system and one (1) dry pipe system with a backflow preventer.

The Helicopter Base contains one (1) reducing pressure backflow preventer.

6.6. If maintenance or repairs are necessary prior to performing tests or inspections, immediately notify AFS Facility Operations Branch Chief so repairs can be made and tests and inspections continued.

7. SPECIAL CONDITIONS

7.1. The Contractor shall coordinate with AFS Facility Operations Branch Chief as necessary to confirm that the Contractor has access to, is aware of, and is able to inspect and test all required components, devices, and portions of the water-based fire protection and fire alarm systems at each facility listed. Nothing in this statement of work shall be construed as relieving the Contractor of the responsibility, upon the completion of each series of inspections, for the correct operation of all portions of the water-based fire protection and fire alarm systems at the facilities inspected.

7.2. The Contractor shall perform the work described herein to each water-based fire protection and fire alarm systems in the facilities listed regardless of current compliance with NFPA 13 and NFPA 72.

7.3. The Contractor shall NOT perform tests of any systems, equipment, or components that may result in any of the following:

7.3.1. Water damage to any BLM property or

7.3.2. Hazardous conditions at any BLM facility.

8. SUBMITTALS

8.1. Copy of Field Supervisor’s current Alaska State Fire Marshal issued permit.

8.2. Copy of Field Supervisor’s current NICET certification.

8.3. Copy of technician’s Backflow Prevention Device Tester Certificate.

8.4. Work Schedule

8.5. Final Fire Sprinkler System and Fire Alarm Inspection Report including all test results and inspection reports for sprinkler systems, fire pumps, backflow prevention devices and fire alarm devices shall be submitted prior to contract payment.

9. END

4of 4