This statement of work outlines the replacement of garage doors at a contaminated site managed by the U.S. Fish and Wildlife Service. The selected contractor will remove two existing garage doors and concrete curbing, reframe the openings, and install two new 14' wide x 12' tall insulated sandwich doors with openers. Additional tasks include installing openers on two western doors. The point of contact is David Crigger and work must be completed by the specified date while following all safety and environmental requirements. The related federal contract opportunity from the Department of the Interior is soliciting quotes for the garage door updates at the Crab Orchard National Wildlife Refuge as outlined in the statement of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC224Q0008_Amd_0001.pdf | ||
| Sol_140FC224Q0008.pdf | ||
| WD_gov.pdf | ||
| Construction_Contract_Administration.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
for the Crab Orchard National Wildlife Refuge Superfund Project Dec. 6, 2023 Title: CERCLA Warehouse Garage Door Replacement Introduction and Background The Crab Orchard National Wildlife Refuge (Refuge) is located in southern Illinois between the Cities of Marion, Carterville, and Carbondale in Williamson, Jackson, and Union Counties. The Refuge was created in part from a land transfer from the War Department now Department of Defense that included about 22,000 acres of the former Illinois Ordnance Plant. The former Illinois Ordnance Plant manufactured landmines, bombs, and artillery for the WWII effort. The buildings and industrial areas on the Refuge were subsequently leased to private companies and other government agencies. There are now many small locations scattered around the Refuge with contaminated soil and water from the industrial activities that are undergoing cleanup. The general purpose of this Statement of Work (SOW) is to replace existing garage doors with wider doors Please see below for the point of contact at the facility, period of performance dates, deliverables, and an outline of the tasks.
Point of Contact List the name of the staff from the Superfund Project Team that will serve as the point of contact or Contracting Officer Representative (COR) / Contracting Officer Technical Representative (COTR) David Crigger (cell phone 618-944-0958) The local contact person will be available for one day to show interested personnel the nature and extent of the work on TBD at TBD central time.
Period of Performance Start date: TBD Completed date: TBD Working on the weekends and/or Federal holidays is acceptable with advance coordination with the COR.
Tasks, Goods, or Reimbursable Services General All delivery of goods or rendering of services is in or around building IN-5-6 in the Eastern portion of Crab Orchard National Wildlife Refuge.
Access to the Building IN-5-6 is controlled. Keys and a visitor tag can be assigned to workers so that they do not have to be escorted after a facility safety and facility rules orientation. Remember to not block gates and close gates after opening.
The contractor will furnish all of the necessary equipment to complete the tasks below except where indicated for certain materials.
Liability insurance is required by the contractor. Emergencies should be report to 911 immediately. All accidents should also be reported immediately to the local point of contact.
The contractor shall be responsible for all damages to persons or property including infrastructure and natural growths that occur as a result of contractor fault or negligence. The Government will not be responsible for any equipment left on site.
Upon completion of the work, a Government inspector may determine whether the requirements have been met according to the purchase agreement terms, if not it will be considered unacceptable and the area must be re-done at no additional cost to the Government.
Safety and Related Matters Working on the Refuge includes exposure to poisonous plants, biting insects, sun, cold and uneven terrain. The selected vendor is responsible for protecting themselves and their workers from these before mentioned physical hazards.
Contractor personnel must wear appropriate apparel, safety toe footwear, and outwear. All personnel protective equipment deemed necessary for the work performed will be worn and provided by the contractor, and as described in the agency Service Manual 241 FW 3.
Equipment shall be cleaned and free of noxious weed or invasive plant species parts including roots, stems, flowers, or seeds before starting work on the Refuge. Equipment may be inspected by Government personnel.
The contractor agrees to take reasonable precautions to prevent the starting of a fire and spreading of fires. The precautions include, but are not limited to, the placement of fully charge five pound or larger ABC fire extinguishers with a flexible spout. All fires are to be immediately reported to 911.
Equipment and storage containers must be free of leaks. Care shall be taken during refueling or refilling to prevent spills (fuels, oil, herbicide chemicals). Stay away from surface waters during refueling or refilling events. Report all spills to the authorities and to the local point of contact.
Description of Tasks
1. Remove two Existing Garage Doors Remove two existing garage doors and associated hardware and stack carefully in the warehouse for later use. Care should be taken to avoid damage.
| 2. | Reframe opening |
| Reframe openings to accept wider doors. Wrap door jamb with aluminum trim matching existing trim color. Relocate Gutter downspout to the side of the new opening | |
| 3. | Remove concrete curb |
At the base of the existing wall there is a concrete curb that must be removed to match the new opening. The curb is approximately 10” thick and 7” tall. About 2’ of curbing must be removed on each side of each door opening.
4. Install two new doors The contractor will install two new 14’ wide X 12’ tall brown insulated sandwich doors with one brown full vision panel in each door.
5. Install two Garage door openers Install a heavy-duty commercial grade garage door opener on each garage door. Supply three openers and an inside switch for each door.
6. Install two Garage door openers Install a regular-duty commercial grade garage door opener on two western most garage doors. Supply three openers and an inside switch for each door.