A04_SOW_CRESTED_WHEATGRASS_STUDY_AND_FORB_SEEDING.pdf

PDF 114 KB Posted

Attached to
Crested Wheatgrass Study and Forb Spike Seeding Federal contract opportunity
Solicitation number
140L3623Q0044
Issued by
Department of the Interior Bureau of Land Management

About this file

This document is a statement of work for a federal contract to conduct a crested wheatgrass study and forb seeding project on Bureau of Land Management land in Montana. The contractor will be required to no-till drill seed approximately 235 acres between October 1st and 31st, 2023. The BLM will provide the seed mixture and determine the appropriate timing for seeding. The contractor must furnish all necessary personnel, equipment, transportation, supplies and incidentals to complete the objectives, which include seeding 120 acres with a native seed mix for a research plot and 115 acres with a forb spike seed mix north of the research plot. Payment will be made upon verification that the entire project area has been seeded. The related federal contract opportunity is solicitation number 140L3623Q0044 for the crested wheatgrass study and forb spike seeding project issued by the Department of the Interior Bureau of Land Management.

View the file

Other files for this federal contract opportunity

Other files attached to Crested Wheatgrass Study and Forb Spike Seeding, newest first.
File Type Posted
B08_Past_Performance_Questionnaire.doc DOC document
B03_WD_2015-5395_REV_19_Date12_27_2022.pdf PDF
Sol_140L3623Q0044.pdf PDF
Schedule_of_Items.pdf PDF
A04_Forb_Seeding_Maps.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Interior Bureau of Land Management – Northcentral Montana District

GLASGOW FIELD OFFICE

CRESTED WHEATGRASS STUDY AND FORB SEEDING, 2023

VALLEY COUNTY, MONTANA

STATEMENT OF WORK

I. Introduction and Background

The BLM-Glasgow Field Office is implementing habitat restoration projects to benefit Greater sage-grouse areas in North Valley County. Various management strategies have been used to date across the proposed unit, including prescribed fire, herbicide treatments, and initial native seed mixes. The native seed mixes have not grown to date. The BLM is implementing another native forb spike seeding.

In the fall of 2023, seed the project area with a native seed mix on a study site and a forb “spike” seed mix, via a no till drill, similar to a John Deere no till drill model 1560. The seed will be provided by BLM.

II. Project Locations

The project site is approximately 235 acres and is in T30N, R39E Section 28 S2 and Section 33 NW4. The native seeding will be in a 120-acre research plot, while the forb seeding will be located directly north of the research plot. Both sites are accessed from the same parking area.

III. Objectives

The object of this contract is to no-till drill seed approximately 235 acres of BLM managed public land. The BLM will work with the awardee to determine the appropriate time to seed the project area. The BLM will provide the seed mixture.

IV. Statement of Work

The BLM-Glasgow Field Office contracting officer will work with the awardee to determine the appropriate time to seed the project area. The estimated timeframe to implement the seeding would occur between October 1st - 31st, 2023. The BLM will provide the contractor with seed.

A. Basic field supplies provided by BLM

i. Field map of project area

ii. Seed mixture in 50lb bags

B. The Contractor shall furnish all personnel, equipment, supervision, transportation, supplies, and incidentals, except those indicated as government-furnished, to perform the tasks to complete all objectives detailed in the Statement of Work section.

V. Acceptance

Payment will be paid upon completion of project.

VI. Deliverables

A. The deliverable for this project is the complete seeding of the project area.

VII. Period of Performance

A. Implementation of the seeding shall be between October 1st and October 31st , 2023. The COR will contact the awardee and advise when to implement the seeding.