A04_Silvio_O_Conte_Fort_River_Trail_SOW.pdf
PDF 122 KB Posted
- Attached to
- MA-FT RIVER DIV OF SOC-TAP-RAIL SUPPORT
- Solicitation number
- 140FS326Q0151
About this file
This is a Statement of Work for the delivery of tap-rail u-channel support posts to the Silvio O. Conte National Wildlife Refuge in Hadley, Massachusetts. The contractor must deliver 2,400 galvanized u-channel posts, each measuring 3 feet 6 inches in length, weighing 7 pounds total, with full-length perforations. These black galvanized posts will support tap-rail sections along an accessible trail that meets ADA accessibility standards. The materials must be delivered to 69 Moody Bridge Road, Hadley, MA 01035 during the August to October 2026 timeframe, coordinated with Refuge staff and Patrick Moffett as the primary point of contact.
The contractor is required to provide delivery tickets for each material type to the on-site Government representative, indicating the type and quantity of materials delivered. The Government representative will sign the tickets and retain copies for Government records. Delivery will be coordinated during general Refuge hours of 7 AM to 5 PM, Monday through Friday, to an area approved by the Refuge Manager/Project Leader. Prospective suppliers should contact Patrick Moffett at 435-695-3166 or Patrick_Moffett@fws.gov for additional information or site-specific requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B03_Wage_Determination.pdf | ||
| Past_Performance_Survey.pdf | ||
| Sol_140FS326Q0151.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
TAP-RAIL U-CHANNEL MATERIALS DELIVERY
FOR
SILVIO O. CONTE NATIONAL WILDLIFE REFUGE -
PART A – GENERAL INFORMATION AND INSTRUCTIONS
GENERAL DESCRIPTION: Provide tap-rail u-channel support posts for the accessible trail at the Fort River Division of Silvio O.
Conte National Wildlife Refuge. The materials will be delivered per Refuge facility schedule.
PART B – PERFORMANCE REQUIREMENTS
Delivery Site:
69 Moody Bridge Road Hadley, MA 01035
Materials requirements list:
Tap-Rail U-Channel Support Posts
The requirement includes the following materials:
• 2,400 galvanized U-channel posts, each measuring 3 feet 6 inches in length, 2 lbs./ft., 7 lbs. total weight, with full-length perforations. These black galvanized 3'6" U-channel posts will be used to support tap-rail sections along the accessible trail.
This material provides a durable, corrosion-resistant solution that significantly reduces both upfront cost and long-term maintenance when compared with alternative post materials. Selection of this product ensures best value while meeting all functional and environmental requirements for the project.
The completed tap-rail will meet ADA accessibility standards and achieves the Refuge’s commitment to providing an accessible trail for visitors.
Material will be delivered to an area approved by the Refuge Manager/Project Leader. The materials will be required around August to October 2026.
Delivery will be coordinated by Refuge staff with Patrick Moffett as the primary POC. General refuge hours are 7AM – 5PM Monday – Friday.
PART C – OTHER PERFORMANCE REQUIREMENTS AND INFORMATION
DELIVERY TICKETS:
For each type of material delivered, delivery tickets shall be provided to the on-site Government representative, who will sign the delivery ticket and keep a copy for Government records. The delivery ticket shall indicate the type and quantity of the materials delivered.
CONTACT INFORMATION: Possible suppliers are encouraged to contact Patrick Moffett; telephone 435-695-3166, Patrick_Moffett@fws.gov for additional information or site specific requirements.
mailto:Patrick_Moffett@fws.gov
File details come from the government source that posted it. Updated .