This request for quotation (RFQ) solicits proposals to replace the boiler at the Agassiz National Wildlife Refuge (NWR) in Minnesota. The U.S. Fish and Wildlife Service seeks a contractor to remove the existing boiler and install a new high-efficiency boiler and associated equipment at the refuge's bunkhouse and maintenance facility. Responses are due by February 28, 2023. The contract will be awarded by March 31, 2023 and all work must be completed within 60 calendar days of the award date. The contractor will be responsible for demolition of the old boiler, supply and installation of the new boiler and related systems, start-up, and training of refuge staff. Pricing should be quoted as a firm fixed price for the entire scope of work. This is a small business set-aside solicitation open to small businesses only.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B03_Wage_Determination_Marshall_County_MN.pdf | ||
| Sol_140FS223Q0169.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
U.S. Fish and Wildlife Service
Agassiz National Wildlife Refuge
22996 290th Street NE
Middle River, MN 56737
218/449-4115
STATEMENT OF WORK
Bunkhouse and Maintenance Facility Boiler Replacement
Overview:
Seeking to have our current boiler systems in our bunkhouse and maintenance facility replaced.
The Bunkhouse’s current boiler and in-line hot water heater are to be removed and replaced. The replacement boiler must be compatible with current radiant floor heat and air conditioning systems and provide on-demand domestic hot water.
The Maintenance Facility’s current boiler, air handler and hot water heater are to be removed and replaced. The replacement boiler must be compatible with current heat and air conditioning systems and provide on-demand domestic hot water.
Location:
Bunkhouse: Agassiz National Wildlife Refuge, 22996 290th Street NE, Middle River, Minnesota
56737
Maintenance Facility: Agassiz National Wildlife Refuge, 29600 280th Ave NE, Middle River, Minnesota 56737
Contact Information:
Anita Locken
Administrative Assistant
Agassiz National Wildlife Refuge
218-537-7456 anita_locken@fws.gov
Cody Okeson
Deputy Refuge Manager
Agassiz National Wildlife Refuge
320-333-4933 cody_okeson@fws.gov
Timeframe:
• Work will be conducted after contract is awarded. Estimated 09/01/2023.
• Work must be completed by: December 28, 2023
Work Hours:
Normal office hours are 7:00 am to 4:30 pm, Central Standard Time, Monday through Friday, except Federal Holidays. All services shall be performed during normal office hours unless otherwise scheduled/approved.
Federal Holidays:
The following Federal Holidays are observed by Agassiz National Wildlife Refuge:
New Year’s Day, Martin Luther King’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, and Christmas Day.
Character of Work :
The work shall be executed by technical experts in the best and most effective manner by qualified personnel skilled in the trade, and in strict accordance with the contract documents and standards of the industry.
Description of Work to be Completed:
Bunkhouse
• Remove and dispose of current boiler in compliance with EPA regulations.
• Remove the in-line hot water heater.
• Replace the current boiler in the bunkhouse with a high efficiency propane fuel source that is compatible with current hydronic radiant floor heat and air conditioning system.
The system must be able to heat a 32’ x 80’ building. The boiler must also provide on-demand domestic hot water that is sized accordingly to the hot water usage of the bunkhouse.
• The replacement boiler system shall be included in response to the solicitation, to include model and specifications.
• All materials for this work are to be provided by the contractor.
• Test and confirm the functionality of the system.
Maintenance Facility
• Remove and dispose of current boiler in compliance with EPA regulations.
• Remove current air handler.
• Remove hot water heater.
• Replace the current boiler and air handler in the maintenance facility with a high efficiency propane fuel source that is compatible with current heat and air conditioning system. The system must be able to heat a 60’ x 140’ building. The boiler must also provide on-demand domestic hot water that is sized accordingly to the hot water usage of the maintenance facility.
• The replacement boiler system shall be included in response to the solicitation, to include model and specifications.
• All materials for this work are to be provided by the contractor.
• Test and confirm the functionality of the system.
Government Furnished Property:
No government property will be furnished. The contractor and personnel are responsible for safeguarding all government property while on the job site. The contractor shall report the occurrence of any lost or stolen Government property immediately to the designated Government contact person.
Other Requirements:
Bidders must schedule a site visit (walk-through) of the facility by contacting the one of the points of contact listed above. Contractor is responsible for any utility locates that may be needed. A site visit will be considered favorable in evaluation factors.
| A04 RFQ SOW Agassiz NWR Bunkhouse and Maintenance Facility Boiler |
| Bunkhouse Boiler 1 |
| Bunkhouse Boiler 2 |
| Bunkhouse Boiler 3 |
| Bunkhouse Boiler 4 |
| Bunkhouse Boiler 5 |
| Shop Boiler 1 |
| Shop Boiler 2 |
| Shop Boiler 3 |
| Shop Boiler 4 |
| Shop Boiler 5 |
| Shop Boiler 6 |
| Shop Boiler 7 |