This Performance Work Statement (PWS) details a non-personnel service contract for repairing a damaged submersible well at Bitter Lake National Wildlife Refuge in Roswell, New Mexico. The project stems from a 200-year flood event in August 2022 that inundated an existing well (NM Permit Number RA-4691), compromising its motor, electrical wiring, and pump assembly. The primary objectives are to repair and modify the well, replace the vertical turbine pump assembly, and conduct a commissioning performance test to confirm flow rates between 200-800 gallons per minute at 150 feet total dynamic head.
The contract requires the contractor to provide all necessary personnel, equipment, and services to replace key well components, including installing a new discharge head assembly, shaft, pump bowl assembly, electrical panel, and variable frequency drive (VFD). The electrical panel must be relocated a minimum of five feet above its current position, with a platform installed for access. The project is to be completed within 100 days of the Notice to Proceed, with the contractor responsible for material acquisition, installation, testing, reporting, and project closeout. The work will be performed at the well site located at latitude 33.456347° and longitude -104.390029°, approximately 7 miles from Roswell, New Mexico.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_-_Technical_Experience_and_References_Form.pdf | ||
| B03_-_Service_Contract_Act_WD_2015-5455_-_Rev_28.pdf | ||
| Sol_140FS225Q0156.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
Repair of 4691 Well at Bitter Lake National Wildlife Refuge
Part 1: General Information
1. GENERAL: This is a non-personnel service contract to repair and modify an existing well and replace the associated pump that were damaged by a 200-year flood event along the Pecos
River in August 2022 on U.S. Fish and Wildlife Service (USFWS) Bitter Lake National Wildlife
Refuge (NWR), located in Roswell, Chaves County, New Mexico.
1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform repair and modification of an existing vertical turbine well (NM
Permit Number RA-4691) near the Pecos River located at Lat. 33.456347o x Long. -104.390029o as defined in this Performance Work Statement. The contractor shall adhere to the performance standards outlined in this Performance Work Statement.
1.2 Background: In August 2022, a 200-year (0.5% annual chance of exceedance) flood event occurred on the Pecos River where 8-11” of rain fell in northern Chaves County then flowed into the Pecos River basin. USGS gage 08386000 on the Pecos River near Acme, NM along the US
70 bridge showed a peak river height of 17.4 feet. Bank height is 10 feet and flood stage is 13 feet. Spatial analysis provided by National Weather Service indicated that the widest extent of the flooding was at least 1.74 miles wide, which occurred on Bitter Lake NWR and Bureau of Land
Management (BLM) Overflow Wetlands to the south of Acme, NM.
Bitter Lake NWR is seeking to repair an existing submersible well that was damaged when it was inundated during the flood event. Flood water covered the electrical panel, pump, and pipes. Due to the level of flooding experienced the existing motor, electrical wiring, and pump assembly are compromised. The existing pump is a Simflo SM10H 3-stage assembly designed to provide 800 gallons per minute at 150 feet total dynamic head. The shaft is approximately 40 feet.
1.3 Objectives:
1. To repair and modify one existing submersible Well (NM Permit Number RA-4691) near the Pecos River located at Lat. 33.456347o x Long.
-104.390029o.
2. Conduct and Submit a Commissioning Performance / Acceptance Test to the COR and Technical points of contact (POCs) to confirm the flow rates of 200 to 800 GPM are obtained and meet requirements.
1.4 Scope:
Task 1: Motor installed and repaired, install new discharge head assembly, shaft, pump bowl assembly, electrical panel, variable frequency drive (VFD).
The Contractor shall replace the vertical turbine pump assembly at Well #4691, to include a new discharge head assembly, shaft, and pump bowl assembly. The existing pump controller shall be replaced with a new variable frequency drive (VFD) that can regulate the well output from 200 to
800 GPM. Total Dynamic Head (TDH) is 150 feet.
The Contractor shall replace the existing electrical panel with an appropriate new panel located a minimum five feet above the existing electrical panel as measured from the bottom of the panel.
A platform shall be installed to provide access to the panel and meet required clearances.
1.5 Period of Performance: All work shall be completed no later than 100 days after Notice to
Proceed. The performance time shall include submitting the material and equipment acquisition, installation, testing, adjusting, reporting, clean-up, final inspection and project closeout.
1.6 General Information
1.6.1 Quality Control: The contractor shall develop and maintain an effective quality control plan to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services.
The contractor’s quality control plan is the means by which they assure themselves that their work complies with the requirement of the contract.
1.6.2 Quality Assurance: The Government shall rely on the contractor to accomplish all inspection and testing needed to ensure the services conform to contract quality requirements before they are tendered to the Government
The Government retains the right to conduct inspections on an as-needed basis during the contract’s period of performance. If a contract discrepancy or poor performance is reported, the contractor, COR, and CO shall meet to address such issues. A mutual effort shall be made to resolve identified issues.
The COR will also review information submitted in the required reports defined in the
PWS (if applicable).
Performance Objective and
PWS
paragraph
Performance Standard Acceptable Quality
Level Method of
Inspection
PWS: 1.4
The contractor shall rehabilitate the existing non-potable production well to supply a minimum of 200
GPM.
Provide flow rate test confirming a minimum flow rate of 200 GPM.
Well flow rate meets minimum requirement.
100% Inspection.
PWS: 1.4
The contractor shall rehabilitate the existing non-potable production well to supply a maximum of 800
GPM.
Provide flow rate test confirming a maximum flow rate of 800 GPM.
Well flow rate meets maximum requirement.
100% Inspection.
PWS: 1.4
The contractor shall rehabilitate the existing non-potable production well to supply a minimum total dynamic head of 150 feet.
Provide a pressure test report showing compliance with design requirements.
Well Total Dynamic Head meets requirement.
100% Inspection.
1.6.4 Hours of Operation: The Contractor is responsible for conducting business, between the hours of 8:00 AM and 4:00 PM, Monday through Friday. The Contractor shall not perform on site on federal holidays unless authorized by the Contracting Officer and coordinated with the
Point of Contact (POC).
1.6.5 Place of Performance: The work to be performed under this contract will be performed at
Bitter Lake NWR at the submersible well near the Pecos River, located at Lat. 33.456347o x
Long. -104.390029o. The project site and Bitter Lake NWR headquarters are located approximately 7 miles from Roswell, NM. The nearest basic facilities are located in Roswell, NM.
1.6.6 Gate Codes: The Contractor shall establish and implement methods of ensuring that all gate codes are not revealed to unauthorized persons.
1.6.7 Post Award Conference: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office.
1.6.8 Key Personnel:
The following personnel are considered key personnel by the government: Project
Superintendent. The contractor shall provide a Contract Manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the Project
Superintendent. The Contract Manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The Contract
Manager or alternate shall be available between 8:00 a.m. to 5:00 p.m., Monday through Friday except Federal holidays or when the government facility is closed for administrative reasons.
PART 2
GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES
2. GOVERNMENT FURNISHED ITEMS AND SERVICES:
2.1. No Government furnished items or services are provided under this contract.
PART 3
SPECIFIC TASKS
3. SPECIFIC TASK: The contractor shall conduct an initial site visit with Bitter Lake NWR staff for access arrangements and to ensure proper identification of the project site and submersible well.
PART 4
APPLICABLE PUBLICATIONS
4. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
4.1. The Contractor shall abide by all applicable Federal and State regulations and laws applicable to this project.
PART 5
ATTACHMENT/TECHNICAL EXHIBIT LISTING
5.1 PROJECT MAP:
5.2 Picture of well in current capped condition:
5.3 Picture of electrical box to be replaced and raised: