This is a Statement of Work (SOW) for design/build services to replace two existing water wells and associated infrastructure at the Pahranagat National Wildlife Refuge (PNWR) in Lincoln County, Nevada. The project requires designing and constructing replacement North and South Wells, as the existing wells from 1962 and 1970 are deteriorating and operating at only 5% and 23% of their original capacities respectively.
The contractor must provide comprehensive design/build services including well drilling, casing, development, pump testing, water sampling, quality testing, installation of vertical shaft pumps with variable frequency drives, and tie-in piping/electrical connections. Optional tasks include installing ground-mounted photovoltaic arrays to partially power the well pumps. The initial drilling depth is estimated at 350 feet for both wells, with options to extend up to 450 feet if needed. The wells must be located within 250-300 feet of the existing wells to maintain water rights compliance. Key requirements include using corrosion-resistant stainless steel casing and achieving target production rates of 600-800 gallons per minute. The period of performance is 2 years and 4 months from Notice to Proceed, with construction limited to June-September and October-February windows. Work hours are Monday-Friday 7:30 AM to 4:00 PM Pacific Time.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Design/Build Services for New Replacement North Well and New Replacement South Well
And All Associated Appurtenances
U.S. Fish and Wildlife Service Pahranagat National Wildlife Refuge (PNWR) – Lincoln County, Nevada
Revised: October 24, 2024
1.0. GENERAL INFORMATION.
1.1 Summary:
The selected awardee Contractor shall provide Design/Build Services for the Design and Construction of a New Replacement North Well and New Replacement South Well and All Associated Appurtenances. The New Well Construction is to include drilling, casing, development, pump testing, water sampling, and water quality testing of the two (2) New Wells, installation of permanent New Well Pumps (Vertical Shaft Pumps or similar), and installation of tie-in discharge piping connections and electrical connections to result in a Design/Build Contractor’s Turnkey Installation, 100% Fully Functional and Operational.
Lastly, the USFWS requests to include Option Items for the Construction / Installation of Photovoltaic (PV) Arrays to power the Variable Frequency Drive (VFD) Vertical Shaft Pumps.
The PV Arrays shall be installed as ground mounted solar systems.
The Existing North Well delivers water to a water delivery system from which the water can be diverted to flow through Black Canyon or be delivered to the Refuge’s piping system.
The Existing North Well was constructed in 1962 and is suffering from material related deterioration. When the North Well was originally constructed, the initial well test showed the well could pump 800 gallons per minute (gpm). The Existing North Well in its current state is now pumping 45 gpm or roughly 5% of its previous maximum sustained capacity.
The Existing South Well delivers water to the Refuge’s concrete delivery ditches, which connect to the meandering stream, which passes through the Visitor Center Trail Area, the Dove Unit, the WHIN Unit, and the marshes ultimately feeding the Lower Lake. The Existing South Well was constructed in 1970 and is similarly suffering from material related deterioration. When the South Well was originally constructed, the initial well test showed the well could pump 420 gpm. The Existing South Well in its current state is now pumping between 100 and 115 gpm or roughly 23% of its previous maximum sustained capacity.
Water Rights.
The Refuge currently has water rights to extract and pump up to 1,685 acre-feet per year of water for the Existing North and South Wells.
Primary Objectives.
The Project is to accomplish the following Primary Objectives. The Contractor shall include the Primary Objectives noted below into their Scope of Work for Design/Build Services.
Design/Build Services to include All Design Services, Permitting Services, Construction, and Construction Support Services for the following Project Planning, Design, Permitting, and Construction Elements:
Review Existing North Well Project Site and the surrounding Site Vicinity.
Review Existing South Well Project Site and the surrounding Site Vicinity.
Review Well Logs and Well Reports for the North Well and South Well.
Review Well Logs and Well Reports for other wells constructed in the area surrounding the Existing North Well and South Well Project Sites. (Note, the North Well and South Well are located at two (2) distinct Project Sites.)
After receiving input from USFWS and after receiving USFWS Review Notes / Comments, select Potential Locations for drilling a New North Well and a New South Well.
The selected locations for drilling should be based on water availability and where it would be expected and anticipated water would be located below ground surface and readily available for extraction.
Determine which of the Potential Locations noted are to be selected for the New Replacement North Well.
Determine which of the Potential Locations noted are to be selected for the New Replacement South Well.
Develop, prepare, and submit 100% Construction Documents for the North Well Construction.
Develop, prepare, and submit 100% Construction Documents for the South Well Construction.
After receiving the 100% Construction Documents from the Architect-Engineer (A-E), Approved for Construction Set, perform necessary Mobilization and De-Mobilization to and from the Project Sites.
Drill, case, develop, pump test, water sample, and water quality test a New Replacement North Well in accordance with 100% Construction Documents.
Please note, It is expected and anticipated, the Design/Build Contractor and the Design/Build Contractor’s Well Driller may have to Field Adjust the New Replacement North Well dimensions and deviate from the 100% Construction Documents during the course of construction and depending on the locations of the aquifer(s).
Field changes shall be documented in the 100% Record Construction Documents and as a separate follow-up submittal package after construction. Changes to requirements shall be submitted to the Contracting Officer and Contractor’s Representative prior to implementing changes and for CO and COR’s review and approval / disapproval.
Drill, case, develop, pump test, and water sample a New Replacement South Well in accordance with 100% Construction Documents.
Please note, it is expected and anticipated, the Design/Build Contractor and the Design/Build Contractor’s Well Driller may have to Field Adjust the New Replacement North Well dimensions and deviate from the 100% Construction Documents during the course of construction and depending on the locations of the aquifer(s).
Field changes shall be documented in the 100% Record Construction Documents and as a separate follow-up submittal package after construction. Changes to requirements shall be submitted to the Contracting Officer and Contractor’s Representative prior to implementing changes and for CO and COR’s review and approval / disapproval.
1.2 Contractor’s Certifications and Qualifications:
Refer to Section L and M of the Solicitation for specific requirements.
1.3 Section L – Instructions and Section M – Evaluation Factors:
Refer to Section L and M of the Solicitation for specific requirements.
1.4 Regulatory Requirements:
It is the Contractor’s responsibility to construct the Project in compliance with applicable requirements of federal and state laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, those outlined below. Contractor shall have copies available of applicable codes and regulations for ready reference. These shall include, but are not limited to:
- State and Local Regulatory Requirements
- Federal Regulatory Requirements
- Occupational Safety and Health Administration (OSHA) Codes and Standards
- FWS Policies
- All Codes and Standards Not Referenced, but Governing Work under this Project / Contract.
- NFPA 101 Fire and Life Safety Code, latest edition
- International Building Code as adopted by the Local Authority Having Jurisdiction.
- International Plumbing Code
- International Mechanical Code
- National Electrical Code
- Architectural Barriers Act (ABA)
- American’s With Disabilities Act (ADA)
1.5 In the event of a conflict, the most stringent laws, codes, regulations, standards, and provisions shall apply.
2.0. WORK LOCATION AND PERIOD OF PERFORMANCE.
2.1 Work Location: Pahranagat National Wildlife Refuge (PNWR), Mile Post 32, Highway 93, Alamo, Nevada 89001.
Project Location Coordinates.
Existing North Well is located at: 37°16'58.8"N 115°07'19.2"W Existing South Well is located at: 37°16'19.2"N 115°07'04.8"W The Project Location Coordinates show the Project Area where the Existing North and South Wells are located within Pahranagat National Wildlife Refuge. The Entire Project Area is detailed on a separate attachment from this Statement of Work document. Refer to separate attachment.
The USFWS does not know the exact coordinates for the construction of a New North Well and New South Well because this will depend on the Design and Engineering performed by the Design/Build Contractor and/or Well Driller, and Their Assembled Team.
The Design/Build Contractor and/or Well Driller and their Assembled Team will be required to tie-in to the Existing Piping where the Existing North Well and Existing South Well is currently located. This will require disconnecting the Existing North Well and Existing South Well’s discharge piping to re-establish New Piping to Existing Piping Connections for the New Replacement Wells.
2.2 Period of Performance:
Start Date: Refer to Solicitation and Contract Forms for Estimated Start Date.
End Date: Refer to Solicitation and Contract Forms for Estimated Start Date.
Construction Work Window:
(June – September, October – February, of each calendar year).
In the event of damage to government property resulting from construction, the contractor shall return the damaged area to its original or improved condition. The contractor will also be instructed where to access the Construction Site to minimize potential damage to the existing resources.
The Period of Performance for this Contract is 2-years and 4-months from the actual date of Notice to Proceed (NTP) Letter. Anticipated Delivery Date for NTP Letter is 30 Days Following Initial Contract Award Date. Above dates shown are tentative and subject to change. Contractor shall coordinate with the Refuge Manager and/or Project Leader for a Proposed Construction Work Window. The Final Accepted Construction Work Window will be mutually agreed to between the Contractor and USFWS Pahranagat NWR prior to Construction.
2.3 Normal Business Hours for the Refuge, Monday thru Friday 7:00 a.m. - 5:00 p.m. Work Activities shall be performed during Normal Business Hours. Limited accommodation to an alternate schedule maybe possible with coordination with on-site FWS staff. In the event of emergencies, Contractor shall provide contact information.
csalazar Underline csalazar Highlight
2.4 Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin Luther King JR.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).
3.0. DEFINITIONS.
Not Used.
4.0. BACKGROUND.
The Pahranagat National Wildlife Refuge (PNWR) is owned, operated, and maintained by the U.S. Fish and Wildlife Service (USFWS). The Refuge is located approximately 9.1 miles southeast of Alamo, Nevada. Note, the next nearest town after Alamo, Nevada is Ash Springs, Nevada located approximately 15.8 miles northwest from the Refuge. The nearest major City/Town is Las Vegas, Nevada located approximately 87.0 miles southwest of PNWR.
The Future Awarded Contract is to result in Design-Build of a New Replacement North Well and New Replacement South Well and All Associated Appurtenances. For the new well construction, the Design/Build Contractor shall perform drilling, casing, development, pump testing, water sampling, and water quality testing of the two (2) New Wells, installation of permanent New Well Pumps (Vertical Shaft Pumps or similar rated for exterior applications) to include Variable Frequency Drives (VFDs), and installation of tie-in discharge piping connections and electrical connections to result in a Design/Build Contractor’s Turnkey Installation, 100% Fully Functional and Operational.
Select Option Items, which may or may not be Exercised and Awarded during the Full Duration of the Project / Contract include:
Construction / Installation of New Photovoltaic (PV) Arrays to power the New Well Pumps.
(1) New PV Array at New North Well.
(1) New PV Array at New South Well.
5.0. SCOPE OF WORK.
Design Permits. Development, preparation, and submittal of Permit Applications and Supporting Documents to the Permit Agencies / Permit Authorities for Review and Approval / Disapproval detailing the Project Improvements on 100% Final Draft Construction Documents.
Contractor shall be responsible for Identification of Design Permits through a Permit Registry.
After identifying permits, the Contractor shall apply for, Pay, and Secure Permits to result in successful project delivery.
Please note, a Notice of Intent and New Well Construction Permit would be anticipated for this Project / Contract. The Design/Build Contractor and/or the Design/Build Contractor’s Well Drilling Contractor either in-house or under subcontract shall develop, prepare, and submit the necessary permit applications and pay all permit fees for the Project Work to be performed.
Pre-Demolition and Pre-Construction Permits. Development, preparation, and submittal of Permit Applications and Supporting Documents to the Permit Agencies / Permit Authorities for Review and Approval / Disapproval.
The Design/Build Contractor shall be responsible for Identification of Pre-Demolition and Pre- Construction Permits through a Permit Registry. After identifying permits, the Design/Build Contractor shall apply for, Pay, and Secure Permits to result in successful project delivery.
To reiterate, the Scope of Work for this contract shall include the Planning, Design, Permitting Construction, and Installation of the Following Project Design Elements:
Planning, Design, and Permitting Services – Base Items:
Perform Field Verification Site Visit.
Develop, prepare, and submit Field Report – Technical Memorandum, Includes preparation of Conceptual Design Drawings (15 – 20% Detail).
Develop, prepare, and submit 100% Draft and Final Draft Construction Documents signed, stamped, and sealed by a Professional Engineer registered in the State of Nevada.
Construction – Base Item:
Mobilization and De-Mobilization to and from the Project Site.
Establish Lay Down Areas / Storage Areas and Work Areas.
Provide and Install Site, Sediment, and Erosion Control Measures.
Drill and Case a New Well. (New North Well Replacement).
Construction – Option Items:
North Well – Major Features of Work.
Fully Develop, Pump Test, Water Sample, and Water Quality Test a New Well (i.e. New
North Well).
Provide and Install New Permanent Well Pump at New North Well (if the New Well is found to be productive).
Provide and Install New Discharge Piping Tie-In Connection from New North Well to the
Existing Water Delivery Pipe.
Provide and Install Exterior Electrical Utility Connections at New North Well.
Provide and Install a New Ground Mounted Solar Photovoltaic (PV) System at New North
Well to power the New Permanent Well Pump.
Provide and Install New Security Fencing and Safety Signage around New North Well and
PV System.
Decommission, Seal, Cut, and Cap-Off Existing North Well.
South Well – Major Features of Work.
Drill and Case a New Well (South Well Replacement).
Fully Develop, Pump Test, Water Sample, and Water Quality Test a New Well.
Provide and Install New Permanent Well Pump at New South Well (if the New Well is found to be productive).
Provide and Install New Discharge Piping Tie-In Connection from New South Well to the
Provide and Install Exterior Electrical Utility Connections at New South Well.
Provide and Install a New Ground Mounted Solar Photovoltaic (PV) System at New South
Well to power the New Permanent Well Pump.
Provide and Install New Security Fencing and Safety Signage around New South Well and
PV System.
Decommission, Seal, Cut, and Cap-Off Existing South Well.
The Contractor shall accomplish the following Tasks if awarded this contract:
5.1. TASK 1. Field Verification Site Visit. Review of Existing Site Features and Existing Site Conditions. Document Review, Planning, Development, Preparation, and Submittal of Project Documents.
(BASE TASK).
Review Drawing Pages (If Available) and All Associated Contract Documents.
Perform a Field Verification Site Visit and Review Existing Site Features and Existing Site Conditions. [The General Contractor Management Team and their Design Team shall be required to Attend this Field Verification Site Visit with USFWS.]
After Performing the Field Verification Site Visit, Develop, Prepare, and Submit General Requirement Specification Submittals under Division 01.
Develop, Prepare, and Submit Technical Specification Submittals under All Remaining Division Sections.
As New Technical Specifications are included during the Development of 100% Construction Documents, the Contractor shall revise their Submittal Registry and Submittals as Necessary and to meet Project Specific Requirements.
Deliverables:
(1) Electronic Copy of the Design-Build Contractor’s Field Verification Site Visit Notes.
Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available.
5.2. TASK 2. Field Report – Technical Memorandum, Preparation of Conceptual Design Drawings (15 – 20% Detail Drawings).
(BASE TASK).
Develop, prepare, and submit a Field Report – Technical Memorandum. The Field Report – Technical Memorandum is to include Concept Drawings, Narrative Descriptions, and an Engineer’s Opinion of Probable Construction Cost.
As part of the Field Report – Technical Memorandum submit Conceptual Design Drawings.
The Conceptual Design Drawings to consist of 15-20% Detail Concept Drawings and Specifications defining and describing the New North Well and New South Well to be designed, constructed, and installed at Pahranagat National Wildlife Refuge. Lastly, the Field Report – Technical Memorandum is to discuss Review of Well Logs and Well Reports for other wells constructed in the area surrounding the Existing North Well and South Well Project Sites and is to discuss how the New Locations for the Replacement North and South Wells were selected for this Replacement Project.
Conceptual Design Services to include requisite Biology, Hydrogeology, and Engineering disciplines (e.g. Fish Biologists, Wildlife Biologists, Hydrologists, Geotechnical Consultants, Civil Consultants, Structural Consultants, and Permitting Consultants). Architect-Engineer (A- E) shall verify coordination with TERO, NEPA, Cultural Resources, and other required Project Participants through the USFWS Project Leader and/or Project Manager. Further, the A-E shall identify FWS directorates and contacts participating in this project, descriptions of required functional requirements, and descriptions of required connections for the Project Improvements.
For the Permit Registry, the A-E shall provide a list of All Federal, State, County and Local Permits required for this specific Project/Contract.
The objective of this deliverable shall be to provide USFWS with Conceptual Design Drawings detailing Project Improvements for further Design Development.
The potential Task Breakdown is as follows:
A. Review existing drawings, well logs, well reports, aerial photographs, project photographs (if available), boundary surveys (if available), and topographic surveys (if available) for Pahranagat NWR provided at Solicitation.
B. Perform a Field Verification Site Visit (TASK 1) to review Existing Refuge Drawings and Project Conditions and develop an understanding of the existing North Well, existing South Well, water delivery systems, appurtenant piping, piping tie-in connections, and water delivery structures.
C. Develop, prepare, and submit a Field Report – Technical Memorandum, Conceptual Design Drawings, Topographic Survey Background Base Map, Geotechnical Investigation and Report, Engineer’s Opinion of Probable Construction Cost, and a list of All Federal, State, County, and Local Permits Required for the New Well Construction and Project Activities.
D. Please note, there are no previous Topographic Surveys preformed within the (2) separate and distinct Project Areas at North Well and at South Well. It is expected, the Design/Build Contractor and the Design/Build Contractor’s Professional Land Surveyor Consultants either In-House or under Subcontract will perform a Topographic Survey of the (2) Project Areas.
E. The Design/Build Contractor is to use the Topographic Survey and Background Base Map developed, prepared, and submitted by their Team to further define site topography and specific arrangements and layouts for site improvements.
Deliverables:
(1) Electronic Copy of the Field Report – Technical Memorandum.
(1) Electronic Copy of the Conceptual Design Drawings.
(1) Electronic Copy of the Topographic Survey Background Base Map.
(1) Electronic Copy of the Geotechnical Investigation Report.
(1) Electronic Copy of the Engineer’s Opinion of Probable Construction Cost.
(1) Electronic Copy of the List of All Federal, State, County, and Local Permits Required for the Project Activities (Permit Registry).
Deliverables to be submitted in PDF File Extension and DOCX File Extension (if available).
Drawing Deliverables to be submitted in PDF and DWG File Extension. Construction Cost Deliverable to be submitted in PDF and XLSX File Extension.
5.3. TASK 3. 100% Draft and Final Draft Construction Documents (Drawings and Specifications).
(BASE TASK).
Following TASK No. 1 Field Verification Site Visit and TASK No. 2 Field Report – Technical Memorandum, and after receiving USFWS Review Notes / Comments, the Design/Build Contractor and the Design/Build Contractor’s Architect-Engineer Company shall develop, prepare, and submit 100% Draft and Final Draft Construction Documents consisting of Drawings, Specifications, Design Summary / Project Narrative, Engineering Design Calculations, Permit Registry, Engineer’s Opinion of Probable Construction Cost, and the Contractor’s Opinion of Probable Construction Schedule. The Contractor shall provide Review Copies of the 100% Draft Construction Documents to the USFWS within 60 to 90 Calendar Days after Receipt of Review Notes concerning the Field Verification Site Visit and Field Report – Technical Memorandum Submittals.
Deliverables:
(1) Electronic Copy of 100% Draft Drawings and Specifications (to include topographic survey background base maps, plans, elevations, sections, and construction details) for Review and Approval.
(1) Electronic Copy of 100% Final Draft Drawings and Specifications (to include topographic background base maps, plans, elevations, sections, and construction details).
(1) Printed 22 x 34 Inch Size Drawings and (1) Printed 8.5 x 11 Inch General and Technical Specifications Manual mailed to Pahranagat National Wildlife Refuge.
(1) Electronic Copy of the 100% Draft Design Summary / Project Narrative for Review and Approval.
(1) Electronic Copy of the 100% Final Design Summary / Project Narrative.
(1) Electronic Copy of the 100% Draft and Final Draft Engineering Design Calculations for Landscape Architecture, Fish Biology, Wildlife Biology, Civil, Water Resources, Environmental, and Structural Engineering Design Elements.
(1) Electronic Copy of the 100% Permit and Submittal Registry, which includes a Minimum Listing of Required Submittals to be submitted Prior to, During, and After Construction. The Submittal Registry shall incorporate the Permit Registry Prepared and Submitted in previous Work Tasks.
As-Built Record Drawings. The Contractor shall work with the Site Superintendent and Foreman during Construction to Document any Field Changes and provide CAD As-Built Record Drawings at the Closeout of the Project.
Deliverables:
(1) Electronic Copy of As-Built Record Drawings.
(1) Printed Mark-Up 22 x 34 Inch Size Drawings and (1) Printed Mark-Up 8.5 x 11 Inch General and Technical Specifications Manual mailed to Pahranagat National Wildlife Refuge.
Electronic Drawing Deliverables shall be submitted in DWG and PDF File Extensions and include the Color Table (CTB) File Extension for accurate plotting of the line weights in CAD. Deliverables other than Drawing Deliverables shall be submitted in PDF File Extensions and DOCX File Extensions when available. Registries (Registers) for Permits and Submittals shall be submitted in XLSX File Extensions.
5.4. TASK 4. Drill and Case a New Well.
(New North Well Replacement).
(BASE TASK).
Mobilization and De-Mobilization.
Mobilize All Labor, Materials, Equipment, and Tools onto the Project Site.
De-Mobilize All Labor, Materials, Equipment, and Tools from the Project Site.
Lay Down Areas / Storage Areas and Work Areas.
Refer to Design/Build Contractor’s 100% Final Draft Construction Documents for Specific Requirements on Lay Down / Storage Areas and Contractor's Work Areas. Design/Build Contractor shall modify and adjust Lay Down / Storage Areas and Work Areas to meet
Construction Functional Requirements and shall closely coordinate any Proposed Adjustments to these Areas with the Refuge prior to Performing On-Site Work.
Site, Sediment, and Erosion Control Measures.
Provide and Install Site, Sediment, and Erosion Control Measures in accordance with the Design-Build Contractor’s 100% Final Draft Construction Documents (Drawings and Technical Specifications) (TASK 3).
Remove Site, Sediment, and Erosion Control Measures after Construction if considered Temporary Measures. Permanent Site, Sediment, and Erosion Control Measures shall remain In-Place.
To include but not be limited to the following:
Temporary Soil Stabilization Measures.
Permanent Soil Stabilization Measures.
Bare Ground Protection Measures.
All Erosion and Sediment Control Measures (e.g. Sediment Fences, Straw Wattles, Stockpile
Covers, Construction Fences).
All Re-Vegetation Measures.
Down Gradient Sediment Control Measures.
Bio Bags and Other Barrier Protection Measures.
Submittals:
Develop, Prepare, and Submit a Storm Water Pollution Prevention Plan and Established Best
Management Practices (BMPs).
Develop, Prepare, Submit, and Maintain an On-site Written Spill Prevention and Response
Procedure.
Develop, Prepare, Submit, and Maintain Toxic and Hazardous Materials Storage, Application, and Disposal Procedures.
Refer to Design/Build Contractor’s 100% Final Draft Construction Documents for Specific Requirements on Site, Sediment, and Erosion Control Measures.
Drill and Case a New Well. (New North Well Replacement).
The Design/Build Contractor and their Well Drilling Contractor either in-house or under subcontract shall drill and case a New Well (New North Well Replacement) to replace the Existing North Well located at approximate coordinates 37° 16' 58.8" N, 115° 07' 19.2" W.
The New North Well shall be located within a 250- to 300-Feet radius from the Existing North Well to allow for a Water Rights Transfer to the New North Well (i.e. if a water rights transfer is applicable under Nevada State Water Rights Law). The initial drilling depth for the New North Well shall be estimated as 350-Feet below ground surface or approximately equal to the drilling depth of Existing North Well to be replaced, whichever is greater.
The Design/Build Contractor shall note, the drilling depth may require adjustments in the field and based on water availability and location of the existing aquifer below ground surface.
Refer to separate Option Task, which would be used if funds become available and if recommended by the Design/Build Contractor, Design/Build Contractor’s Well Driller, and Design/Build Contractor’s Architect-Engineer to advance the bore hole depth up to 100- Feet beyond the 350-Feet initial well drilling depth.
Further note, during the drilling and casing of the New Well (i.e. North Well Replacement), the Design/Build Contractor in consultation with their Well Drilling Contractor shall assess the New Well to determine whether or not the New Well would approximately meet the Refuge’s Well Production Target of 800 gallons per minute (gpm).
Casing Material.
The casing material for the New North Well Replacement shall be a corrosion resistant material.
For the purposes of this Work Task and Design/Build Contractor estimating, the selected material will be assumed to be stainless steel. The Design/Build Contractor may present alternative corrosion resistant casing materials for consideration, but the pricing on the Proposal Schedule shall reflect stainless steel casing, and the USFWS has final determination on acceptance or rejection of the alternative materials presented.
Refer to below excerpt of Nevada State Water Rights Law for specific requirements. For the Full Text, visit the Nevada State Website.
NRS 534.065 Replacement well: Application to change place of diversion not required in certain circumstances; notice.
1. If a person is seeking to sink or bore a replacement well to divert groundwater already appropriated and:
(a) The original site of the well and the site of the replacement well are on property owned by the same person for whom the groundwater has already been appropriated; and
(b) The site of the replacement well is located not more than 300 feet from the original place of diversion described on the permit to appropriate water, the person is not required to file an application to change the place of diversion pursuant to NRS 533.345.
2. If a change to the site of a replacement well meets the requirements of subsection 1, the site of the replacement well must be located anywhere on the property of the person who holds the permit to appropriate water that is not more than 300 feet from the original place of diversion described on the permit to appropriate water.
3. The person who holds the permit to appropriate water must:
(a) Record the site of the replacement well in the office of the county recorder of each county in which the water is applied to beneficial use and in each county in which the water is diverted from its natural source; and
(b) Inform the State Engineer of the site of the replacement well.
Compliance with the provisions of this subsection shall be deemed to impart notice of the site of the replacement well to all persons.
(Added to NRS by 2019, 2525)
5.A. TASK A. Finish Well Construction and Provide and Install Water and Electric Utility Connections.
This Task includes but is not limited to:
Fully Develop, Pump Test, Water Sample, and Water Quality Test a New Well (i.e. New North Well).
Provide and Install New Permanent Well Pump at New North Well (if the New Well is found to be productive).
Provide and Install New Discharge Piping Tie-In Connection from New North Well to the Existing Water Delivery Pipe.
Provide and Install Exterior Electrical Utility Connections at New North Well.
(New North Well Replacement).
(OPTION TASK).
The Design/Build Contractor and their Well Drilling Contractor either in-house or under subcontract shall fully develop, pump test, water sample, and water quality test the New Well (New North Well Replacement) to replace the Existing North Well located at approximate coordinates 37° 16' 58.8" N, 115° 07' 19.2" W.
If the New Well is shown to meet the Refuge’s Approximate Well Production Target or is found to be at least 75% of the Refuge’s Approximate Well Production Target (e.g. 600 gpm), the Design/Build Contractor and their Well Drilling Contractor shall finish all remaining development and pump testing of the New Test Well and collect a water sample or samples for follow-up water quality testing for select water quality parameters.
If the pumping capacity is below the minimum flow rate of 600 gpm, the USFWS may decide and at the USFWS’ discretion, to have the well construction and permanent well pump installed by the Design/Build Contractor despite the reduced flow rate and pumping capacity.
The Design/Build Contractor shall meet the requirements of the following under Nevada State Water Rights Law:
The Design/Build Contractor, on behalf of the Owner – USFWS, shall record the site of the replacement well in the office of the county recorder of each county in which the water is applied to beneficial use and in each county in which the water is diverted from its natural source; and The Design/Build Contractor, on behalf of the Owner – USFWS, shall inform the State Engineer of the site of the replacement well.
Note, the Project Documents shall be submitted to the County Recorder, State Engineer, and USFWS by the Design/Build Contractor, on behalf of the Owner – USFWS.
Permanent Well Pump.
The Design/Build Contractor and their Well Drilling Contractor either in-house or under subcontract shall provide and install a New Permanent Well Pump if the New Well (New North Well) is found to be productive. The New Permanent Well Pump shall consist of a sufficiently sized Vertical Shaft Pump or Vertical Turbine Pump with Variable Frequency Drive (VFD) capable of pumping and extracting water at a minimum and maximum flow rate of 600 to 800 gpm respectively unless a reduced pumping capacity range is required because of lower yields within the aquifer.
Discharge Piping Tie-In Connection.
The Design/Build Contractor shall provide and install a New Discharge Piping Tie-In Connection from the New North Well to the Existing Water Delivery Pipe. The location of the existing water delivery pipe and logical point for a tie-in connection shall be verified and validated by the Design/Build Contractor prior to installation and to result in a 100% Design/Build Contractor Turnkey Installation (i.e. a Fully Functional and Operational System).
As part of the New Discharge Piping Tie-In Connection, the Design/Build Contractor shall provide and install a New Flow Meter and New Check Valve directly downstream of the New Vertical Shaft Pump.
Following Exterior Electric Utility Connections, the Design/Build Contractor shall operate the New North Well Replacement to commission and test the system and ensure the New Vertical Shaft Pump, VFD, Flow Meter, and Check Valve operate correctly.
Exterior Electrical Utility Connections.
The Design/Build Contractor shall provide and install All Exterior Electrical Utility Connections at the New North Well to include buried electrical cables and wiring from the Transformer to the New North Well and Pump. The electrical cables and wiring shall be placed and installed in correctly sized electrical conduit to protect the conductors.
Note, the Design/Build Contractor shall coordinate and submit All permits and pay All fees / assessments required by the Public Utility District (PUD). Where required, the Design/Build Contractor shall pay for and schedule with the serving Utility any work required by the serving Utility and to result in a 100% Turnkey Installation.
5.B. TASK B. Solar System and Security Fencing / Signage.
This Task includes but is not limited to:
Provide and Install a New Ground Mounted Solar Photovoltaic (PV) System at New North Well to partially power the New Permanent Well Pump.
Provide and Install New Security Fencing and Safety Signage around New North Well and PV System.
(New North Well Replacement).
(OPTION TASK).
New Ground Mounted Solar Photovoltaic (PV) System.
The Design/Build Contractor shall provide and install a New Ground Mounted Solar Photovoltaic (PV) System at the New North Well to power the New Permanent Well Pump.
The New Ground Mounted Solar Photovoltaic (PV) System Design shall be designed and documented in the 100% Draft and Final Draft Construction Documents developed, prepared, and submitted under TASK 3 of this Statement of Work.
The New Ground Mounted Solar Photovoltaic (PV) System size and layout as determined by and at the discretion of the Design/Build Contractor. The PV System size shall be as required to fully partially power the New North Well Permanent Well Pump during the Refuge’s seasonal usage.
For partial power, the Refuge is requesting a Solar PV System, which is potentially capable of offsetting power usage for a permanent well pump operating at roughly 50 to 100 gpm and up to
20 to 30 minutes at a time. The USFWS does not expect to be able to fully offset power usage at the Project Well Site given project budgetary constraints.
For example, at higher volume and higher flow rates exceeding either 50 to 100 gpm and at lengthier durations, when USFWS is delivering water to wetlands and delivering water through the standpipe for equipment or firefighting, then the Refuge would disconnect the Solar PV System from Off-Grid Power with a Manual Transfer Switching device and start-up the Permanent Pump on On-Grid Power and run the pumps to generate higher volumes of flow.
The Manual Transfer Switch device shall be incorporated into the Electrical System Design for this project / contract allowing the Refuge to seamlessly switch between Off-Grid and On-Grid Power and when operating the Permanent Pump. For Net Metering Purposes, the Electrical System Design should incorporate a method for supplying surplus power to the Electrical Grid using the Manual Transfer Switch device.
The PV System Arrays shall be anchored into cast-in-place concrete slab-on-grades or an Alternative Foundation System meeting the requirements of the PV System manufacturer and to result in a secure installation. Note, the Design/Build Contractor shall comply with All Structural Load Requirements, Building Codes, and Building Standards to result in a 100% Contractor Turnkey Installation.
The Design/Build Contractor shall develop, prepare, and submit the Net Metering Application or Equivalent to the Public Utility District (PUD) to authorize connection of the PV System to the Existing Electrical Grid. The Design/Build Contractor shall pay all permits, fees, assessments, and costs as required by the PUD for the establishment of a connection.
Security Fencing and Signage.
The Design/Build Contractor shall provide and install New Security Fencing and Safety Signage around New North Well and PV System.
The quantity, size, spacing, placement, and dimensions for the New Security Fencing and Safety Signage (including Foundation Systems) as determined by and at the discretion of the Design/Build Contractor.
The Construction and Installation of the New Security Fencing and Safety Signage shall be in accordance with All Applicable Codes and Standards to result in a 100% Design/Build Contractor’s Turnkey Installation.
5.C. TASK C. Decommission, Seal, Cut, and Cap-Off Existing North Well.
(Existing North Well).
(OPTION TASK).
The Design/Build Contractor and their Well Drilling Contractor shall Decommission, Seal, Cut, and Cap-Off Existing North Well in accordance with all Federal, State, County, and Local requirements.
The Existing Pump and Well Casing at North Well shall be removed, recycled, and/or disposed of offsite at a licensed and permitted Waste Disposal Facility.
The requirements for this TASK shall include but not necessarily be limited to all laws, codes, rules, regulations, standards, and provisions.
Criteria.
Laws and Regulations.
All Well decommissioning must comply with all applicable governmental regulations, laws, permits, licenses, and registrations.
Roles and Responsibilities.
A water well must be decommissioned by a licensed water well driller. When allowed by State and local regulations, hand-dug wells less than 60-feet deep and without steel or plastic casing, may be decommissioned by the landowner, engineer, geologist, licensed pump installer, or licensed water well driller. The person decommissioning the well is responsible for submitting the well closure report to all applicable government entities.
Data Collection.
Collect and review All As-Built Record Construction Documents, Maintenance Records, and Other Available Data for the Existing Well. Include this information in the Existing Water Well Decommissioning Plan.
Well Preparation.
Remove all equipment, material, and debris, which may obstruct access to the bottom of the well. Sound the well to verify all obstructions were removed.
Remove casing by either pulling or over drilling (over-reaming) according to ASTM D5299, “Standard Guide for Decommissioning of Groundwater Wells, Vadose Zone Monitoring Devices, Boreholes, and Other Devices for Environmental Activities,” and American Society of Agricultural and Biological Engineers (ASABE), EP400.3 Section 8.0, “Designing and Constructing Irrigation Wells.”
If portions of or all of the equipment and casing resists removal by pulling or over drilling, the casing must be ripped, perforated, or cut off a minimum of 2.0 feet below the ground surface.
Disinfection.
Prior to filling and/or sealing, disinfect the well with a minimum chlorine solution concentration of 50 mg/L (50 ppm), or the minimum chlorine solution concentration specified by the regulating authority, whichever is greater. After adding the chlorine solution, agitate the well water to distribute the solution, and keep the well undisturbed for a minimum of 12 hours to allow for disinfection.
Sealing Materials.
All sealing materials shall conform to ASTM D5299 and State regulatory requirements.
Sealing materials do not require disinfection. Select sealing materials that have an in-place hydraulic conductivity equivalent to, or less than, ground surface soil surrounding the well head. Water quality used for mixing with sealing materials must meet or exceed ASTM D5299 criteria.
Fill (coarse-grained) Materials.
When allowed by State regulations, fill materials, such as sand, pea gravel, and sand-gravel mix; crushed rock; or agricultural lime can be used to fill the well, if sealing material zones conform to ASTM D5299 and State regulatory requirements. Select a soil gradation and a filling process, which will not cause bridging during installation. Fill materials require disinfection prior to placement.
Sealing / Filling Procedures.
When well disinfection is required by State law, do not place sealing or select fill materials until after disinfecting the well. Place sealing materials from the well bottom to ground surface. If allowed by applicable regulations, backfill with select fill materials, according to ASTM D5299. Use installation methods that avoid segregation, dilution, or bridging of fill or sealant, such as a pump and hose, or tremie pipe. Use boring logs to identify zones for fill and sealant placement. In the absence of a boring log, use a downhole camera to identify sealant placement. Downhole cameras are not required for wells where sealing material is used for the entire well column.
For grouting ratios and placement procedures, follow American Water Works Association (AWWA), A100-15, “Water Wells Standard,” and ASTM D5299.
Sealing Collapsible Formations.
When casings are within a collapsing formation, install sealing material concurrently with casing removal whereby the bottom of the casing remains submerged in the grout.
Well-Head Seal.
Seal the interval between the ground surface and the top of the cut-off casing or last-sealed layer with materials that conform to guidance in ASTM D5299. These materials may be an extension of the sealing materials used below this depth. The Sealing thickness must comply with all applicable Federal and State requirements.
Mound or crown the native soil to compensate for settling and to prevent ponding of water directly over the well site.
Control of Artesian Pressure.
When a well is under artesian pressure (flowing or not flowing), pressure grout from the bottom of the well to ground surface. Procedures for balancing formation pressures during grouting operations must conform to ASTM D5299.
Considerations.
When feasible, consider adding a metal “target” to the top 3-inches of the Well-Head Seal whereby the decommissioned well may be easily located with a metal detector.
5.D. TASK D. Drill and Case a New Well.
(New South Well Replacement).
(OPTION TASK).
The Design/Build Contractor and their Well Drilling Contractor either in-house or under subcontract shall drill and case a New Well (New South Well Replacement) to replace the Existing South Well located at approximate coordinates 37° 16' 19.2" N, 115° 07' 04.8" W.
The New South Well shall be located within a 250- to 300-Feet radius from the Existing South Well to allow for a Water Rights Transfer to the New South Well (i.e. if a water rights transfer is applicable under Nevada State Water Rights Law). The initial drilling depth for the New North Well shall be estimated as 350-Feet below ground surface or approximately equal to the drilling depth of Existing South Well to be replaced, whichever is greater.
The Design/Build Contractor shall note, the drilling depth may require adjustments in the field and based on water availability and location of the existing aquifer below ground surface.
Refer to separate Option Task, which would be used if funds become available and if recommended by the Design/Build Contractor, Design/Build Contractor’s Well Driller, and Design/Build Contractor’s Architect-Engineer to advance the bore hole depth up to 100- Feet beyond the 350-Feet initial well drilling depth.
Further note, during the drilling and casing of the New Well (i.e. South Well Replacement), the Design/Build Contractor in consultation with their Well Drilling Contractor shall assess the New Well to determine whether or not the New Well would approximately meet the Refuge’s Well Production Target of 800 gallons per minute (gpm).
Casing Material.
The casing material for the New South Well Replacement shall be a corrosion resistant material.
For the purposes of this Work Task and Design/Build Contractor estimating, the selected material will be assumed to be stainless steel. The Design/Build Contractor may present alternative corrosion resistant casing material for consideration, but the pricing on the Proposal Schedule shall reflect stainless steel casing, and USFWS has final determination on acceptance or rejection of the alternative materials presented.
Refer to below excerpt of Nevada State Water Rights Law for specific requirements. For the Full Text, visit the Nevada State Website.
NRS 534.065 Replacement well: Application to change place of diversion not required in certain circumstances; notice.
1. If a person is seeking to sink or bore a replacement well to divert groundwater already appropriated and:
(a) The original site of the well and the site of the replacement well are on property owned by the same person for whom the groundwater has already been appropriated; and
(b) The site of the replacement well is located not more than 300 feet from the original place of diversion described on the permit to appropriate water, the person is not required to file an application to change the place of diversion pursuant to NRS 533.345.
2. If a change to the site of a replacement well meets the requirements of subsection 1, the site of the replacement well must be located anywhere on the property of the person who holds the permit to appropriate water that is not more than 300 feet from the original place of diversion described on the permit to appropriate water.
3. The person who holds the permit to appropriate water must:
(a) Record the site of the replacement well in the office of the county recorder of each county in which the water is applied to beneficial use and in each county in which the water is diverted from its natural source; and
(b) Inform the State Engineer of the site of the replacement well.
Compliance with the provisions of this subsection shall be deemed to impart notice of the site of the replacement well to all persons.
(Added to NRS by 2019, 2525)
5.E. TASK E. Finish Well Construction and Provide and Install Water and Electric Utility Connections.
This Task includes but is not limited to:
Fully Develop, Pump Test, Water Sample, and Water Quality Test a New Well.
Provide and Install New Permanent Well Pump at New South Well (if the New Well is found to be productive).
Provide and Install New Discharge Piping Tie-In Connection from New South Well to the
Provide and Install Exterior Electrical Utility Connections at New South Well.
(New South Well Replacement).
(OPTION TASK).
The Design/Build Contractor and their Well Drilling Contractor either in-house or under subcontract shall fully develop, pump test, water sample, and water quality test a New Well (New South Well Replacement) to replace the Existing South Well located at approximate coordinates 37° 16' 19.2" N, 115° 07' 04.8" W.
If the New Well is shown to meet the Refuge’s Approximate Well Production Target or is found to be at least 75% of the Refuge’s Approximate Well Production Target (e.g. 600 gpm), the Design/Build Contractor and their Well Drilling Contractor shall finish all remaining development and pump testing of the New Test Well and collect a water sample or samples for follow-up water quality testing for select water quality parameters.
If the pumping capacity is below the minimum flow rate of 600 gpm, the USFWS may decide and at the USFWS’ discretion, to have the well construction and permanent well pump installed by the Design/Build Contractor despite the reduced flow rate and pumping capacity.
The Design/Build Contractor shall meet the requirements of the following under Nevada State Water Rights Law:
The Design/Build Contractor, on behalf of the Owner – USFWS, shall record the site of the replacement well in the office of the county recorder of each county in which the water is applied to beneficial use and in each county in which the water is diverted from its natural source; and
The Design/Build Contractor, on behalf of the Owner – USFWS, shall inform the State Engineer of the site of the replacement well.
Note, the Project Documents shall be submitted to the County Recorder, State Engineer, and USFWS by the Design/Build Contractor, on behalf of the Owner – USFWS.
New Permanent Well Pump.
The Design/Build Contractor and their Well Drilling Contractor either in-house or under subcontract shall provide and install a New Permanent Well Pump if the New Well (New South Well) is found to be productive. The New Permanent Well Pump shall consist of a sufficiently sized Vertical Shaft Pump or Vertical Turbine Pump with Variable Frequency Drive (VFD) capable of pumping and extracting water at a minimum and maximum flow rate of 600 to 800 gpm respectively unless a reduced pumping capacity range is required because of lower yields within the aquifer.
Discharge Piping Tie-In Connection.
The Design/Build Contractor shall provide and install a New Discharge Piping Tie-In Connection from the New South Well to the Existing Water Delivery Pipe. The location of the existing water delivery pipe and logical point for a tie-in connection shall be verified and validated by the Design/Build Contractor prior installation to result in a 100%…