A04_PDNWR_Scope_of_Work_2024_Understory_Control.pdf

PDF 922 KB Posted

Attached to
HERBICIDE APPLICATION AT FWS PEE DEE NWR Federal contract opportunity
Solicitation number
140FS324Q0123
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document is a Scope of Work for a herbicide application project at the Pee Dee National Wildlife Refuge in Wadesboro, North Carolina. The purpose is to enhance understory herbaceous vegetation by eliminating undesirable woody vegetation, particularly sweetgum, maple, and privet, through foliar herbicide application. The performance period is July 15, 2024 through September 30, 2024. The refuge will supply all required chemicals, and the contractor must provide labor, transportation, supplies, supervision, and equipment. Specific herbicide rates and application methods are detailed. The contractor must follow all safety, health, and environmental regulations. This scope of work is related to a federal contract opportunity with Solicitation Number 140FS324Q0123 for "HERBICIDE APPLICATION AT FWS PEE DEE NWR" issued by the Department of the Interior Fish and Wildlife Service.

View the file

Other files for this federal contract opportunity

Other files attached to HERBICIDE APPLICATION AT FWS PEE DEE NWR, newest first.
File Type Posted
Sol_140FS324Q0123.pdf PDF
B03_-_WD.pdf PDF
Clauses_4Q.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES DEPARTMENT OF THE INTERIOR

Fish and Wildlife Service Pee Dee National Wildlife Refuge

5770 Hwy 52 N

Wadesboro, NC 28170

Scope of Work

Herbicide Application for Forestry Project

1.0 General

The Pee Dee National Wildlife Refuge, Wadesboro, NC is seeking a qualified contractor for the

Scope of Work outlined below. Performance period is July 15, 2024 through September 30, 2024.

The successful bidder must be registered in SAM.gov (there is no charge to register) and invoice through an Internet Payment Platform (IPP). Payment will be via EFT (electronic funds transfer).

Interested Bidders are encouraged to schedule a site visit with the Refuge Forester, Monday-

Friday, 8:00a.m. 4:00 p.m. before providing a quotation.

2.0 Purpose and Specifications

The purpose of this action is to enhance understory herbaceous vegetation by eliminating all undesirable woody vegetation, particularly sweetgum, maple, and privet. Herbicide damage to residual hardwoods and pines shall be avoided.

Understory woody vegetation reduction will be accomplished by applying a foliar application to all undesirable woody vegetation. Applications can be made by broadcast treatments utilizing modified skidder, or by backpack hand crew performing broadcast or spot treatments as needed to control target vegetation. All herbicide specimen labels, and specified rates below shall be followed.

The Refuge will supply all chemicals required for this Scope of Work. The Contractor shall supply all labor, transportation, supplies, supervision, and equipment to accomplish the work described.

Herbicide Rates to be used per acre

Treatment 1 (77ac): Treatment 2 (69 ac):

Triclopyr (Garlon 4 Ultra)- 64 ounces Imazapyr (Chopper Gen 2)- 28 ounces

Aminopyralid (Milestone)- 7 ounces MSO (MES 100)- 38 ounces or 1%

Surfactant (Liberate)- 9.6 ounces or .025%

Prior to application, the successful bidder and the refuge representative will conduct a coordination meeting to ensure the herbicide application-area is clearly defined and understood, and that job expectations are clearly defined.

2.1 Project Location

The project area is located on Pee Dee NWR, 6 miles north of Wadesboro, NC. From

Wadesboro take Hwy 52 north 6 miles to Wildlife Drive. Wildlife Drive will take you to the

Refuge office, ½ mile off Hwy 52. The project location can be accessed by following Wildlife

Drive pass the office through the project area. *Note, Wildlife Drive is a one way road and should not be accessed from the exit points unless authorized for equipment purposes. See

Figure 1 for project area description and Figure 2 for project location.

2.2 Contractor Responsibilities

1. The Refuge Forester or agent must be contacted prior to beginning work.

2. All operations shall be conducted during daylight hours Monday through Friday.

Permission may be granted on a case-by-case basis for conducting operations on holidays or weekends.

3. All refuge wildlife is protected. No type of wildlife will be harmed or harassed.

4. Littering in any manner on the refuge is a violation of Federal Regulations. The entire work area shall be kept free of all forms of litter at all times. Specific attention shall be given to proper storage, maintenance and clean-up of petroleum based products.

5. Vehicles and other equipment will be operated in a safe manner. All state and county laws shall be adhered to.

6. Ensure the application area is clearly defined and understood. Only designated areas within the project area are to be sprayed. No activity is to occur outside of project area without prior approval.

7. Equipment is calibrated prior to application to ensure specified rates are applied.

8. Herbicide spillage will be avoided. Chemical spill kits shall be available during applications. Absorbent pads shall be used where tanks are filled to catch any spillage.

If spillage over 1 gallon occurs the contractor shall notify the refuge immediately. The contractor will be responsible for removing all contaminated materials and disposing of properly.

9. The permittee and employees will take all precautions to prevent forest fires. No open burning is permitted on the Refuge. If a fire does occur immediately call 911 and Refuge contact to report wildfire.

10. North Carolina’s Forestry Best Management Practices will be followed as mandatory practices.

11. The Refuge Forester shall have authority to temporarily close all or part of the operation during inclement weather, a period of high fire danger, refuge hunts, safety reasons or any other reason deemed necessary.

12. All equipment will be removed from refuge property within 3 days of completing final closeout inspection by Refuge Forester.

3.0 Safety, Health and Environmental Compliance

In addition to requirements of these specifications, the contractor shall be responsible for meeting all applicable Federal, State, and local laws, and regulations, codes and similar requirements in relation to safety, personal protection, environmental, and transportation compliance with the Statement of Work.

File details come from the government source that posted it. Updated .