This is a Statement of Work (SOW) for Paper Conservation Services to be provided to the National Park Service (NPS) Northeast Region (Interior Region 1) under the Historic Architecture, Conservation, and Engineering (HACE) division, with an anticipated start date of January 2026.

The contractor must provide a professionally trained conservator with expertise in paper and photograph conservation to perform technical conservation services across Northeast Region national parks and historic sites. The conservator will conduct conservation laboratory projects including examination, testing, and treatment of historic artifacts; develop treatment proposals and comprehensive dossiers with photographic documentation; perform on-site condition assessments and treatments for items too large or fragile to transport; and conduct collection-wide conservation surveys. Six specific projects are identified with defined hour limitations and Not-to-Exceed (NTE) costs for materials, travel, and supplies: FOMC 327680C (450 hours, $4,000 NTE) for paper-based archives; MABI 224902C (325 hours, $4,000 NTE) for engravings and prints; MABI 339863A (250 hours, $4,000 NTE) for watercolors; SAIR 330145A (240 hours, $2,000 NTE) and SAIR 330145B (100 hours, $8,000 NTE) for architectural plans and digitization; and SAMA 216852B (485 hours, $5,500 NTE) for panoramic photographs. The contractor must be a graduate-level conservator with completion of an accredited conservation program or equivalent apprenticeship through the American Institute for Conservation, possess expertise in digital photography documentation, and comply with all NPS security requirements including a NACI background investigation and PIV credential (approximately $350 contractor cost). The primary duty location is Boott Mill in Lowell, Massachusetts with core hours 8:00 A.M. to 4:30 P.M., Monday through Friday, with occasional travel required to Northeast Region parks and sites.

View the file

Other files

File Type Posted
LONG_Repair_Damaged_Scrolls_SOW_final.docx DOCX document
B03-WD-2015-4035-Rev33-12_3_25.pdf PDF
Sol_140P4326Q0026.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Paper Conservation Services January 2026

SCOPE OF WORK

The contractor will provide technical conservation services to National Parks in the Northeast Region (Interior Region 1) under the guidance of the Historic Architecture, Conservation, and Engineering (HACE) division. Services include: historic artifact conservation; the execution of collection-wide preservation and preventive treatment plans and surveys for parks, treatment and research, and training. The contractor will be or will provide NPS with a professionally trained Conservator with experience in the conservation of Paper and Photographs.

WORK ENVIRONMENT

Work performed directly supports the National Park Service Mission to preserve unimpaired… the cultural resources… of the National Park System for the enjoyment, education, and inspiration of this and future generations. Work performed effects personnel throughout the Northeast Region who share in the responsibilities of cultural resource preservation.

Work is performed in an office environment, a conservation laboratory and on-site at various Parks, Sites, and Monuments. Report writing as well as many treatment tasks may include repetition of hand, wrist or shoulder movement. Lifting moderately heavy objects (30-45 lbs) and conservation equipment and supplies is often required. Reagents, solvents and chemicals are used in the laboratory and personal protection apparatus such as gloves, a respirator, and goggles are worn when required. Work using certain solvents is carried out in a fume hood. On-site work may involve exposure to reagents, solvent, chemicals, mold, air-borne allergens. Work hours are typically Monday through Friday for 8 hours/day between 9:00 and 5:30 pm.

TASK DESCRIPTION

Major Duties and Responsibilities

Conservation Laboratory Projects:

· The contractor will be responsible for performing a wide variety of conservation treatments, including difficult and complex technical analysis, testing, and treatment necessary to conserve items of historic and artistic value.

· The contractor will examine artifacts to determine the nature and cause of deterioration, conduct testing where necessary, and select appropriate conservation techniques for treatment.

· The contractor will develop treatments in consultation with the park curators and senior conservators in HACE regarding final appearance and intended use of the object. They will provide written documentation for the examination and condition analysis phase, treatment proposal phase, and, following approval of the object’s custodian (usually the park curator through the park Superintendent), the final treatment phase. All will be contained in a comprehensive dossier for each item treated in the conservation laboratory, with complete photographic documentation before and after treatment, and during treatment, if warranted.

· The contractor will draw from professional experience and practical research in selecting professionally established treatment techniques, and in developing new treatment methodologies, including selection of conservation solvents, reagents, compounds, materials and application techniques. Treatment procedures often involve extremely delicate techniques requiring highly developed hand skills and mature professional judgement in determining the appropriate extent of intervention, and the desired final appearance of extremely valuable and irreplaceable objects.

· The contractor will make contacts with parks for treatment scheduling and proposal review, and to make recommendations concerning collection care in the realm of both preventive and remedial conservation. Contacts are also made with parks as a result of their requests for conservation information or services. Contacts with NPS and non-NPS conservators are usually for the purpose of information acquisition or exchange.

· The contractor will be expected to work collaboratively with other conservation colleagues and interns in the lab as well as provide general guidance in his/her area of expertise when required.

· The contractor will be responsible for compliance with all OSHA and NIOSH regulations in laboratory operations by all personnel working in the laboratory.

On-site treatment projects:

· The contractor will assess the condition and treatment needs of historic artifacts on-site and will develop treatment proposals.

· The contractor will submit written treatment proposals to senior conservators for review.

· The contractor will identify and arrange for procurement and scheduled delivery of conservation supplies necessary for on-site treatments. On-site treatments are primarily, but not limited to, treatment of items too large or too fragile to be transported to the HACE Conservation laboratory.

Conservation Survey Projects:

· As part of a team, or proceeding independently, undertake on-site conservation assessments of museum exhibit and storage facilities, and object-specific surveys of park collections, to include estimates for treatment hours. Results are entered into spreadsheets and documents to be provided to the park.

The contractor will be responsible for the following Projects:

1. FOMC 327680C: Treat Significant FOMC Collection of Archives and Works on Paper

This project will hire a professional Conservator to provide conservation treatment for paper-based items, including books, documents, sheet music, artwork, photographs, and ephemera, from a highly significant collection donated to the park in 2022 and surveyed in 2025.

The work is expected to take no more than 450 hours.

The conservator will conserve and stabilize the artifacts, and prepare Treatment Reports, including "before” and “after" digital images to illustrate the work. The completed Treatment Reports and digital images will be shared with both HACE and with the Park via a secure flash drive. Formatting of reports are to follow established templates available on the HACE computer server.

All travel arrangements, as well as the purchase of conservation supplies required to complete the work will be arranged by the Contract Conservator and will not exceed the NTE CLIN ($4,000).

Though general conservation supplies will be provided at the HACE labs, any materials needed to complete treatment on the artifacts associated with this contract will be the responsibility of the Contractor.

Costs for shipping, materials and equipment, and travel are to be borne by the vendor. Travel-related expenditures for Contractor's personnel are restricted to the limits established for federal employees using GSA guidance. (www.gsa.gov/travel)

2. MABI 224902C: Conserve At-Risk Engravings

This project will hire a professional Conservator to work with HACE to provide conservation treatment for approximately 20 engravings and prints at the Marsh Billings Rockefeller National Historical Park that were surveyed in 2022 where it was determined that conservation was necessary to lessen the risk of additional degradation. Where possible, frame packages will be replaced with preservation-grade framing materials. The collection of prints exhibits damage from light, mold, pests, and acidic mounts, as well as mechanical damage. The work is expected to take no more than 325 hours.

The conservator will conserve and stabilize the artifacts, and prepare Treatment Reports, including "before” and “after" digital images to illustrate the work. The completed Treatment Reports and digital images will be shared with both HACE and with the Park via a secure flash drive. Formatting of reports are to follow established templates available on the HACE computer server.

All travel and shipping arrangements, as well as the purchase of conservation supplies required to complete the work will be arranged by the Contract Conservator and will not exceed the NTE CLIN ($4,000).

Though general conservation supplies will be provided at the HACE labs, any materials needed to complete treatment on the artifacts associated with this contract will be the responsibility of the Contractor.

Costs for shipping, materials and equipment, and travel are to be borne by the vendor. Travel-related expenditures for Contractor's personnel are restricted to the limits established for federal employees using GSA guidance. (www.gsa.gov/travel)

3. MABI 339863A: Conservation of At-Risk Watercolors

This project will hire a professional Conservator to provide conservation treatment for at-risk watercolors at the Marsh Billings Rockefeller National Historical Park surveyed in 2019. The watercolors were prioritized based on condition, significance to the park, or in anticipation of upcoming exhibitions. The Park’s museum collection is a described resource in the National Register and have strong provenance ties to the Billings or Rockefeller family; they are critical artifacts to maintaining the visitor experience. The work is expected to take no more than 250 hours.

The conservator will conserve and stabilize the artifacts, and prepare Treatment Reports, including "before” and “after" digital images to illustrate the work. The completed Treatment Reports and digital images will be shared with both HACE and with the Park via a secure flash drive. Formatting of reports are to follow established templates available on the HACE computer server.

All travel and shipping arrangements, as well as the purchase of conservation supplies required to complete the work will be arranged by the Contract Conservator and will not exceed the NTE CLIN ($4,000).

Though general conservation supplies will be provided at the HACE labs, any materials needed to complete treatment on the artifacts associated with this contract will be the responsibility of the Contractor.

Costs for shipping, materials and equipment, and travel are to be borne by the vendor. Travel-related expenditures for Contractor's personnel are restricted to the limits established for federal employees using GSA guidance. (www.gsa.gov/travel)

4. SAIR 330145A: Conservation Treatment and Digitization of Architectural Plans

This project will hire a professional Conservator to provide oversight for the conservation and digitization of approximately 500 pencil line plans and drawings on tracing paper and blueprints for the reconstruction of Saugus Iron Works between 1949 and 1953. The work is expected to take no more than 240 hours.

The conservator will conserve and stabilize the artifacts, and prepare Treatment Reports, including "before” and “after" digital images to illustrate the work. The completed Treatment Reports and digital images will be shared with both HACE and with the Park via a secure flash drive. Formatting of reports are to follow established templates available on the HACE computer server.

Additionally, the conservator will provide digital reproductions of each artifact, which will then be returned to the original frame packages. The original artifacts will be prepared for long-term safe storage. Both the framed reproductions and the packaged originals will be packed and returned to the park.

All travel and shipping arrangements, as well as the purchase of conservation supplies required to complete the work will be arranged by the Contract Conservator and will not exceed the NTE CLIN ($2,000).

Though general conservation supplies will be provided at the HACE labs, any materials needed to complete treatment on the artifacts associated with this contract will be the responsibility of the Contractor.

Costs for shipping, materials and equipment, and travel are to be borne by the vendor. Travel-related expenditures for Contractor's personnel are restricted to the limits established for federal employees using GSA guidance. (www.gsa.gov/travel)

5. SAIR 330145B: Conservation Treatment and Digitization of Architectural Plans

This project will hire a professional Conservator to provide oversight for the conservation and digitization of the remaining pencil line plans and drawings on tracing paper and blueprints for the reconstruction of Saugus Iron Works between 1949 and 1953. The work is expected to take no more than 100 hours.

The conservator will conserve and stabilize the artifacts, and prepare Treatment Reports, including "before” and “after" digital images to illustrate the work. The completed Treatment Reports and digital images will be shared with both HACE and with the Park via a secure flash drive. Formatting of reports are to follow established templates available on the HACE computer server.

Additionally, the conservator will provide digital reproductions of each artifact, which will then be returned to the original frame packages. The original artifacts will be prepared for long-term safe storage. Both the framed reproductions and the packaged originals will be packed and returned to the park.

All travel and shipping arrangements, as well as the purchase of conservation supplies and digitization required to complete the work will be arranged by the Contract Conservator and will not exceed the NTE CLIN ($8,000).

Though general conservation supplies will be provided at the HACE labs, any materials needed to complete treatment on the artifacts associated with this contract will be the responsibility of the Contractor.

Costs for shipping, materials and equipment, and travel are to be borne by the vendor. Travel-related expenditures for Contractor's personnel are restricted to the limits established for federal employees using GSA guidance. (www.gsa.gov/travel)

6. SAMA 216852B: Conservation Treatment of Panoramic Photographs

This project will hire a professional Conservator to provide conservation treatment for 16 panoramic photographs associated with the Salem Maritime National Historic Site; the photographs are in varying states of condition. The collection was surveyed in 2025 and all photographs are in need of rehousing and treatment; several are stuck to glass. The work is expected to take no more than 485 hours.

The conservator will conserve and stabilize the artifacts, and prepare Treatment Reports, including "before” and “after" digital images to illustrate the work. The completed Treatment Reports and digital images will be shared with both HACE and with the Park via a secure flash drive. Formatting of reports are to follow established templates available on the HACE computer server.

Additionally, the conservator will provide digital reproductions of each artifact, which will then be returned to the original frame packages. The original artifacts will be prepared for long-term safe storage. Both the framed reproductions and the packaged originals will be packed and returned to the park.

All travel and shipping arrangements, as well as the purchase of conservation supplies required to complete the work will be arranged by the Contract Conservator and will not exceed the NTE CLIN ($5,500).

Though general conservation supplies will be provided at the HACE labs, any materials needed to complete treatment on the artifacts associated with this contract will be the responsibility of the Contractor.

Costs for shipping, materials and equipment, and travel are to be borne by the vendor. Travel-related expenditures for Contractor's personnel are restricted to the limits established for federal employees using GSA guidance. (www.gsa.gov/travel)

PROFESSIONAL DELIVERABLES

Contractor will be required to work on various projects that support the preservation of cultural resources in the Northeast Region as needed by the government.

Contractor shall provide treatment proposals, treatment reports and surveys as needed by the government.

Contractor shall arrange for travel, shipping, and materials purchases with costs borne by the Contracting Firm. NTE amounts are specified in individual SOWs.

Contractor shall provide advice to the client on conservation issues (e.g. storage and exhibit questions, object condition observations, etc.) and participate in meetings as needed.

Contractor shall record and maintain records of treatments and surveys in conjunction with NPS guidelines/ protocols.

SKILLS REQUIRED

Prior experience relating to conservation treatment of historic collections located in National Parks is preferred, therefore, any contractor personnel with such experience should be provided, as is reasonable.

Completion of a graduate program in conservation or the equivalent degree of knowledge and skill gained through formal apprenticeship programs with accredited museums and/or professionally recognized conservators through the American Institute for Conservation (AIC). Graduate level degree in a related field such as art history, historic preservation, or fine arts, with coursework in architectural history, preservation, archaeology, or materials conservation.

Full professional knowledge of conservation theory, procedures, and techniques for the conservation of historic works on paper and photographs.

Knowledge and experience in high resolution digital tethered photography of historic works on paper and photographs.

General knowledge of professional standards of historic house museum operations.

Strong verbal and writing skills to enable the transmission of complex information to parks in an accurate, clear and concise manner.

Extensive knowledge of computer software programs such as Microsoft Office, Adobe Photoshop, applications and spreadsheet programs such as Excel for creating and generating reports for conservation documentation and planning purposes.

Contractor Personnel Security and Suitability Requirements

A. National Agency Check and Inquires (NACI) Background Investigation

Before starting work under this contract, the contractor will need to have a basic NACI background investigation. Forms required to initiate this process will be provided to the Contractor by the COR and must be returned to the COR to be provided to the Human Resources Office to being the process. The Human Resources Office will provide the employee fingerprint forms which must be taken to a local police station for fingerprinting and returned to the Human Resources Office. The contractor will not be able to start work until notified that their fingerprints have been cleared. The employee will also need to complete the NPS IT security training and provide a printed copy of the completion certification prior to gaining access to NPS computers. This training takes 1-2 hours to complete.

B. Credentialing (PIV)

In addition to the basic NACI background and investigation, performance of this contract requires the contractor employee to have a Federal government-issued Personal Identity Verification (PIV) credential to perform certain duties (routine, unsupervised access to NPS networks). The cost is paid by the contractor and is approx. $350.00, amount subject to change. Completion of the approval process may take from 4 to 6 weeks.

During performance of the contract, the contractor must keep the COR appraised of changes in personnel to ensure that performance is not delayed by compliance with credentialing processes. Cards that have been lost, damaged, or stolen must be reported to the COR and Issuing Office within 24 hours. If reissuance of expired credentials is needed, the contractor must coordinate with the COR.

At the end of contract performance, or when a contractor employee is no longer working under this contract, the contractor must ensure that all identification cards are returned to the COR.

1. Credentialing Request

The Contracting Officer’s Representative (COR) is the requesting official and will make arrangements through the NPS Access Card sponsor for personal identity verification and DOI Access Card issuance. The contractor must make their personnel available at the place and time specified by the COR or DOI Access Card sponsor in order to initiate the credentialing process. If an individual has already been credentialed by another agency through OPM, and that credential has not yet expired, further investigation may not be necessary. In that case, the contractor must provide the COR with documentation that supports the individual’s credentialed status.

2. Enrollment

When a valid email address has been created for the contractor employee, the process will begin for the DOI Access Card. The COR will request the email account and will notify the HR Specialist to begin the enrollment process in USAccess. The employee should receive an email within 15 to 30 minutes from HSPD- 12 and/or USAccess. When the email is received, the employee will need to follow the instructions to make an appointment and collect the types of identification required. Contractor employees will begin the enrollment process at https://app3.timetrade.com/tc/login.do?url=usaccess to find the most conveniently located enrollment center. Once this process is completed, the employee will receive an email stating that the card is ready for pick-up at the GSA location to certify and activate the card. The Human Resources Specialist (Adjudicator) will provide the information to USAccess to initiate this process.

3. Activation

Once the enrollment process begins, the employee will need to bring two pieces of identification to the Credentialing Center to start the activation process.

Contractor provided personnel will be required to follow all NPS and DOI computer security guidelines and requirements.

Contractor provided personnel will be required to read and sign the NPS document, “NPS Responsibilities for Computer Use”, acknowledging their understanding of NPS computer security requirements.

Contractor and contractor provided personnel will be required to report all computer security related incidents to the NER Security Manager and/or appropriate staff.

All contractor provided personnel will be required to take annual Department of the Interior (DOI) Security Training.

Contractor will also provide resumes or other documentation necessary to reasonably verify the credentials of the assigned personnel upon Government request. The Government reserves the right to approve or to disapprove of the assignment of any contractor personnel to provide services.

Government Furnished Resources

Facilities, Supplies, and Services

The National Park Service will provide office space, equipment, including computer and mobile phone, and software for the task for one contractor provided personnel. All government resources shall be returned to the client upon completion of this task.

Points of Contact

NPS Contracting Officer's Representative (COR):

Angela Campbell Historic Architecture, Conservation & Engineering Center Interior Region 1 115 John St, Lowell Ma 01852 978-970-5152 Angela_Campbell@nps.gov

NPS HACE Representative:

Margaret Breuker Historic Architecture, Conservation & Engineering Center Interior Region 1 115 John St, Lowell Ma 01852 978-483-6978 Margaret_Breuker@nps.gov

Place of Performance

The primary duty location is office at Boott Mill, 115 John Street, Lowell, MA. Occasional site visits will be required to Northeast Region Parks.

Hours

Regular Hours: The contractor shall provide coverage at the specified government sites during the hours of 8:00 A.M. to 4:30 P.M (core hours); Monday through Friday, except Federal holidays.

Overtime: Overtime will be authorized in emergency situations such as natural disasters and/or activation of the Northeast Region Continuity of Operations Plan (COOP). The COR will identify which tasks are necessary during this emergency and what personnel will be required to report to work or work additional hours.

Travel: Occasional travel is required to various sites in the Northeast Region.

Standards and References

NPS standards and procedures will be made available upon task initiation.

All work performed will be within the standards of the American Institute for Conservation (AIC) Code of Ethics and Guidelines