A04_FINAL_ABLI_and_CUGA_DOE_SOW.docx

DOCX document 23 MB Posted

Attached to
MISSION 66 DOES FOR ABLI AND CUGA Federal contract opportunity
Solicitation number
140P5122Q0019
Issued by
Department of the Interior National Park Service Southeast Region

View the file

Other files for this federal contract opportunity

Other files attached to MISSION 66 DOES FOR ABLI AND CUGA, newest first.
File Type Posted
B03_Larue_county_wage_rates.pdf PDF
B03_Clairborne_County_tn_wage_rates.pdf PDF
B03_Lee_County_va_wage_rates.pdf PDF
B03_Bell_and_Harlan_wage_rates.pdf PDF
Sol_140P5122Q0019.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FINAL

SCOPE OF SERVICES

DETERMINATIONS OF ELIGIBILITY

FOR THE NATIONAL REGISTER

FOR

ABRAHAM LINCOLN BIRTHPLACE NHP AND

CUMBERLAND GAP NHP

MISSION 66 DISTRICTS

SCOPE

In accordance with the terms and conditions of the Contract, the Contractor shall perform the work of this award for the National Park Service (NPS) as described below. This project will provide Determinations of Eligibility for the National Register of Historic Places for Mission 66 cultural resources within Abraham Lincoln Birthplace National Historical Park, located in LaRue County, Kentucky, and Cumberland Gap National Historical Park, located in Bell and Harlan counties in Kentucky, Claiborne County in Tennessee, and Lee County in Virginia.

CONFIDENTIALITY

The information developed under this awardis the property of the U.S. government and shall be kept in strict confidence.

PERFORMANCE PERIOD

Time is of the essence. The two parks included in this project need clarity on the National Register status of the subject resources in order to plan for their maintenance and rehabilitation. The work shall begin promptly following the issuance of the delivery/task order, shall proceed in accordance with the schedule for submittals, and shall be completed no later than 12 months after award. A two-month window is provided at the outset of the project during which field survey work should occur; the two-month window should be sufficient to schedule field work in conjunction with travel cautions due to COVID19.

INTRODUCTION

Sections 110 and 106 of the National Historic Preservation Act (NHPA) provide to all Federal agencies a legal mandate to maintain a preservation program for the identification, evaluation, and nomination of properties owned or controlled by them that may qualify for the National Register of Historic Places, and to consider in planning processes the preservation of historic properties that may be affected by federal actions.

This project will specifically focus on Mission 66 era NPS park site developments at Abraham Lincoln Birthplace National Historical Park (ABLI) in Hodgenville, KY and the Cumberland Gap National Historical Park (CUGA) headquartered in Middlesboro, KY. To accommodate soaring post-war visitation to national parks, the Mission 66 initiative (1945- 1973) of the National Park Service sought to improve parks through building new roads and facilities; including visitor centers, campgrounds, park housing, and interpretive infrastructure. This project will utilize the themes, trends, and patterns of history shared by the properties, and it provides the National historical context and the registration requirements for the work being contracted to execute this scope of work. The existing Multiple Property Documentation Form (MPDF) for “National Park Service Mission 66 Era Resources” provides the specific historic context and registration requirements for the work. All requirements for any eligible properties still apply for those determined eligible under the MPS.

This documentation effort will provide a list of contributing and non-contributing resources by applying the MPDF. The field survey will collect current information on approximately ninety-five (95) buildings and structures in two parks (see Appendix A).

BACKGROUND INFORMATION ON ABLI AND CUGA

Abraham Lincoln Birthplace National Historical Park was administratively listed in the National Register of Historic Places with the passage of the National Historic Preservation Act in 1966. National Register documentation was accepted by the Keeper of the National Register on December 13, 1977 (NRIS 66000066).

The Abraham Lincoln Birthplace National Historical Park was established to preserve, for the benefit and inspiration of ensuring generations, the traditional birthplace cabin, the Memorial Building enclosing the cabin, and a part of the original site (farm) where the 16th President was born and spent the first 2-1/2 years of his life.

The Lincoln’s bought 300 acres of land on Nolin Creek near Elizabethtown in 1808. Abraham was born to Tom and Nancy Lincoln February 12, 1809. They lived there 2-1/2 years; at which time they ware forced to move due to a defective land title.

The cabin in the completed Memorial Building stands as an example of the hardships of early American settlement and strengths of character such life developed in Americans, especially Abraham Lincoln. It illustrates the beginning of a man who directed politician and military changes dur the upheavals of the Civil War and who, more than any other president, exemplified the American political and humanitarian image.

Cumberland Gap National Historical Park was administratively listed in the National Register of Historic Places with passage of the National Historic Preservation Act in 1966. National Register Documentation was accepted by the Keeper of the National Register on December 28, 1980 (NRIS 66000353).

Cumberland Gap is a notch in a narrow section of Cumberland Mountain, part of the Appalachian chain encompassing the southwestern tip of Virginia, the southeastern corner of Kentucky, and a portion of the northeastern corner of Tennessee. The Gap is the result of a block fault running perpendicular to the axis of the mountain. The ridge of the mountain runs generally from northeast to southwest and the Gap is delineated by two peaks: to the northeast is the Pinnacle, and to the southwest is the Tri-State Peak where Kentucky, Tennessee and Virginia meet.

Cumberland Gap has been for centuries a passageway for people, being the only easily accessible pass through the Appalachian Mountains. It has witnessed the movement of peoples from Native Americans to modern travelers and played an important role in the westward expansion of EuroAmerican settlement. Its importance as a natural pass was emphasized during the Civil War by its fortification by both the Union and Confederate armies. During the nineteenth century, Cumberland Gap was a locally important commercial passage, used by stockmen and merchants.

Between 1955 and 1965, both parks were developed under the Mission 66 program. These developments are now more than fifty (50) years old and will be evaluated for National Register eligibility under this scope.

REQUIRED CONSULTANT QUALIFICATIONS

The selected contractor must have demonstrated experience in survey, architectural history, and architecture and have successfully prepared NR DOEs and NR nominations. Ideal candidates will also possess the following desired qualifications:

a) One or more principal staff in this project team that meet the qualifications of historian, historical architect, or architectural historian who meet the Secretary of the Interior’s Professional Qualifications Standards as specified under Department of the Interior's regulations 36 CFR Part 61.

b) Demonstrated experience in preparing determinations of eligibility that have resulted in these properties being successfully evaluated by the State Office of Historic Preservation.

If the consultant comprises a firm or organization, then a Principal Investigator must bedesignated for the project. The Principal Investigator must agree to be responsible for all work conducted by other contractor personnel for the project. The individual selected as the Principal Investigator may not change during the project without the prior written approval of the NPS.

PROJECT DESCRIPTION

The work to be conducted under this contract will consist of:

Preparation of a Determination of Eligibility for Mission 66 cultural resources within Abraham Lincoln Birthplace National Historical Park. Documentation must be submitted on Form 10-900, which may be downloaded from: http://www.nps.gov/nr/publications/forms.htm.

The existing nomination (NRIS 66000066) can be found at:

https://npgallery.nps.gov/NRHP/AssetDetail?assetID= 12b74201-9122-4aec-b9bf-82795f45d6c2

The majority of structures at the site were constructed during the Mission 66 development era of the park and are not included in the current NRNF that was listed in 1977.

The Determination of Eligibility will address the Mission 66 theme only. Original construction documents for the Mission 66 structures will be made available in support of this project.

Preparation of a Determination of Eligibility for Mission 66 cultural resources within Cumberland Gap National Historical Park. Documentation must be submitted on Form 10-900, which may be downloaded from: http://www.nps.gov/nr/publications/forms.htm.

The existing Cumberland Gap Historic District nomination (NRIS 66000366) can be found at:

https://npgallery.nps.gov/NRHP/AssetDetail?assetID= 108f1b1e-a4de-41d2-8601-79eed413bd3b Note that the park as a whole has never been documented in a National Register Nomination Form.

The majority of structures at the site were constructed during the Mission 66 development era of the park and are not included in the current NRNF that was listed in 1980.

The Determination of Eligibility will address the Mission 66 theme only. Original construction documents for the Mission 66 structures will be made available in support of this project.

A team approach, entailing the disciplines of history and historic structures, will be required. The team will need to integrate information about the properties’ physical and cultural history in order to evaluate park resources under the Mission 66 criteria and to assess integrity to that period of significance. The Multiple Property Documentation Form for “National Park Service Mission 66 Era Resources” can be found at: https://www.nps.gov/nr/feature/places/pdfs/64501248.pdf The Contractor shall provide all materials, supplies, labor, supervision, coordination, and management necessary to complete the work as and when required, as specified in this scope of services.

SPECIFIC TASKS

1) Orientation Meeting via Video Call

2) Monthly Progress Calls via Video Call. On the monthly call after completion of each field survey, contractor team shall be prepared to discuss integrity of the Mission 66 resource at the site and National Register eligibility.

3) Field survey work at each park.

4) Prepare Determination of Eligibility (DOE) Documentation:

· Consultant shall use all readily available primary and secondary source material, including NPS reports, and perform physical investigations as necessary, to complete documentation.

· The consultant shall prepare DOE documentation that includes descriptions which classify Mission 66 resources within each park as contributing or non-contributing.

· The documentation shall be based on National Register criteria for significance and the integrity of resources, and it shall consider the Mission 66 historic context. The information must be submitted on National Register Form 10-900.

· Follow the guidelines for counting contributing and noncontributing resources in National Register Bulletin: Guidelines for Completing National Register of Historic Places Forms. The resource count shall conform to the Rules for Counting Resources (page 17).

· Specifically account for all buildings, structures, sites, and objects, historic and non- historic, that are associated with Mission 66 in both National Register Form 10-900 Section 7 (description) and on the district data sheet (inventory). Specifically, reference all contributing resources described in both National Register Form 10-900 Section 7 and Section 8.

· Distinguish countable resources from their associated features in both the narrative in Section 7 and the associated data sheet. Organize the data sheet by resource type and include associated features for specific resources. In addition to other identifying information, include the area(s) of significance with which they are associated. Include also a separate list of non-contributing resources.

· Consultant must include photographic views representing each resource. Views must include the buildings and structures and important landscape features and patterns. The consultant must adhere to the National Register Photo Policy Fact Sheet. http://www.nps.gov/nr/publications/guidance/Photo_Policy_final.pdf

· The consultant should propose historic property boundaries for the districts, contributing and noncontributing elements and any property found to be individually eligible. Consultant shall create and notate a scaled map identifying all contributing and non- contributing resources by name and number. Mapping shall be compatible with NPS GIS standards. (See STIPULATIONS, no. 10, and Appendix A – GIS Standards)

· A list of structures that are already entered in the NPS Cultural Resource Inventory System (CRIS) for the two parks shall be provided and will serve as a reference, whether or not countable for purposes of the Mission 66 focus of the current project.

· NPS Segment maps with GPS polygons for each tract managed by NPS shall be made available to the consultant for purposes of establishing the Mission 66 district boundaries. Expectation is that the NPS land holdings at the time of the Mission 66 project will determine the district boundary.

Consultant shall review as-built plans, Superintendent Annual Reports, historic photos, and other pertinent documents available in the park archives (e.g. Tract Files) or in ETIC from the period the structures were originally constructed. These documents will be used to determine if significant alterations have occurred since that time that diminishes the integrity of these structures from their original design intent.

5) Prepare Structure Photographs The contractor shall include a minimum of four representative photographic views of each structure. While the NRNF only requires 1-2 images per structure, the remainder of the images will be provided to NPS for use in entering the structures into the Cultural Resources Inventory System (CRIS).

Views shall include:

· Front, rear, and side elevations of all contributing and non-contributing buildings and structures, including one view that places the structure in its context.

· Views of primary interior spaces (where possible)

· Views of additions, alterations, intrusions, and dependencies.

· In no case may a graphic file have a lower resolution than specified on the National Register photography standards. Therefore, use of screen grab imagery is not acceptable. Where digital images exist only in low resolution format, the subject shall be reacquired to achieve an acceptable resolution.

· Modern photographs included in the report shall clearly render the subject, shall not exhibit muddiness, excessive light or deep shadow that obscures detail, and shall be framed with vertical constructed or landscape elements parallel to the frame of the image consistent with best practices for documentary photography.

· Photo composition: Level the camera to avoid distortion when shooting basic centered views such as the primary view of a setting or landscape.

· Photo composition: Make appropriate use of panorama and wide-angle lens views to document context and spatial relationships.

· Then/Now Photos: Contractor shall re-photograph historic and current views as paired images in the DOEs to demonstrate continuity or change over time.

· Image files should be named as follows: PARK ALPHA CODE_Structure Name_Year taken_ description phrase.

6) Prepare Structure Detail Spreadsheet The contractor shall provide NPS with an Excel spreadsheet containing the structure-by-structure information collected for all the assets listed in Appendix A. Minimally this will include the following data fields:

Resource Primary Name Other Names Structure ID (Park Building Number) FMSS Location/Asset Number Contributing/Non-Contributing per the Mission 66 MPDF Condition (use the CRIS assessment criteria) Condition Impacts (Example: weather, visitation, flooding, vegetation, etc.)

Chronology

Year built
Year rehabilitated, altered

Short Physical Description Materials

Foundation
Walls
Roof
Other

Latitude/Longitude expressed as a decimal value (see Appendix B – GIS Standards). Provide a metadata statement addressing as a minimum equipment used, projection used, accuracy of GPS recordation, date and time.

Use, current Use, original

FORMAT

· The DOE documentation shall follow all formatting guidance established under the National Register program.

· Final electronic deliverables will be provided to NPS on a hard drive.

· NPS will be provided electronic versions of all deliverables.

· NPS will be provided hard copy or electronic versions of all research materials collected from non-NPS repositories.

PROJECT SCHEDULE AND SUBMISSION OF DELIVERABLES

1. Project Schedule The NPS will provide comments to the contractor on all submittals within 4 weeks of receipt of the submission.

DELIVERY ITEM
DATE
1. Start-up Meeting Video Call
Within 3 weeks post-award. Contractor shall provide a draft project schedule one week prior to the start-up video call.
2. Field Survey ABLI, collection of background materials, meeting with park staff and use of park archives.
Within 8 weeks of project start, working with the park on COVID-19 cautions.
3. Field Survey CUGA, collection of background materials, meeting with park staff and use of park archives.
Within 8 weeks of project start, working with the park on COVID-19 cautions.
4. Initial Draft DOE documentation for NPS review: Cover sheet (Sections 1-6), draft of Section 7, Section 8 narrative and preliminary Data Sheet listing Contributing and Non-Contributing resources, Section 11 (GIS maps, and photographs.)
Due 8 weeks after surveys are completed.

[NPS review period: 4 weeks]

5. Draft Structure Detail Spreadsheet, draft Structure Photographs.
Same schedule as Initial Draft
6. Revised Final Draft DOE documentation for NPS review: Cover sheet (Sections 1-6), Section 7, Section 8 narrative and preliminary Data Sheet listing Contributing and Non-Contributing resources, Section 9, Section 10, Section 11 (GIS maps, and photographs.)
Due 4 weeks after NPS comments are delivered.
7. Final Structure Detail Spreadsheet, draft Structure Photographs incorporating response to NPS comments.
Same schedule as Revised Draft
8. Final Determination of Eligibility documentation for SHPO review.
Due 4 weeks after NPS comments are delivered.
9. Final DOE documentation for KY, TN, and VA State Offices of Historic Preservation (SHPOs) for comment.
Due 4 weeks after NPS comments are delivered.

[SHPO review period: 6 weeks]

10. Final DOE documentation for submission to the KY, TN, and VA SHPO for signature.

Due 3 weeks after KY-SHPO, TN-SHPO, VA-SHPO comments are delivered.

11. Project Close-out, including delivery of external hard disk with all digital files, delivery of hard copy version of research in non-NPS repositories (if any) and final invoice.
Due 2 weeks after delivery of final DOEs (National Register Nomination Forms)

STIPULATIONS

1. The contractor and key team members will meet the requirements specified in 36 CFR Appendix A, Professional Qualification Standards and the intent of Section 112 (a)(1)(of the National Historic Preservation Act of 1966, as Amended through1992. http://www.nps.gov/history/local-law/arch_stnds_9.htmB)

2. The Contractor shall coordinate with the Contracting Officer’s Representative (COR) as necessary to complete the work as and when required and determine park point of contact. This may include participating in conference calls and product review meetings.

3. All work must be technically and legally defensible. Consultant must utilize the guidelines the National Register of Historic Places bulletins including: 15, How to Apply the National Register Criteria for Evaluation; 16A, How to Complete the National Register Registration Form; 21, Defining Boundaries for National Register Properties (with Appendix, Definition of National Register Boundaries for Archeological Properties). http://www.nps.gov/nr/publications/index.htm#bulletins. Consultant shall also utilize the guidelines contained in NPS-28 (Cultural Resource Management Guideline): Appendix Q, “Preparing a National Register Registration Form.” https://www.nps.gov/parkhistory/online_books/nps28/28contents.htm

4. Level of Effort - Research will meet NPS standards for a thorough investigation, i.e., research will be done in selected published and documentary sources of known or presumed relevance that are readily accessible without extensive travel and that promise expeditious extraction of relevant data. Findings will be presented in no greater detail than required by this scope of work (NPS 28 chapter 2.A)

5. All digital photography, including printing on acceptable ink and paper combination for digital images, shall be accomplished in accordance with the March, 2010 National Register of Historic Places and National Historic Landmarks Survey Photo Policy Expansion (http://www.nps.gov/history/nr/policyexpansion.htm).

6. The Contractor's quality control efforts shall ensure that all draft and final deliverables are completed documents, as specified, that have been reviewed for academic excellence, professional and copy quality, and technical accuracy. Documents not displaying such efforts will not be accepted.

7. The contractor is advised that Section 9 of the Archeological Resources Protection Act of 1979 (as amended) prohibits the release of information concerning the nature or location of archeological properties unless specifically authorized by the Federal Land Manager. Unauthorized release may result in penalties described in Section 7 of that Act. Section 304 of the National Historic Preservation Act also applies. Documentation of restricted information will adhere to National Register of Historic Places Bulletin 29, Guidelines for Restricting Information and Historic and Prehistoric Resources. http://www.nps.gov/nr/publications/index.htm#bulletins If possible, sensitive information will be separately reported.

8. Research files, negatives and photographs, and other material produced as a result of this project shall be delivered to and become the property of NPS upon completion of the contract.

9. The Chicago Manual of Style, 17th edition or later, guidelines will be used for citations and as a general guide to style.

10. The consultant shall be required to meet the NPS GIS data collection and mapping standards detailed in Appendix B.

REQUIRED CONTENTS OF PROPOSAL

1. Title Page

2. Table of Contents

3. Statement of the proposal / Project approach

a. Contractor must indicate how they will manage COVID-19 travel cautions.

b. Contractor must confirm their capacity to meet the project schedule.

4. Project team: identify assigned key personnel, with brief resumes confirming that relevant disciplines are part of the team and that key personnel meet The Secretary of the Interior’s Professional Qualification Standards.

a. Professional experience of key personnel in undertaking the evaluation of architecturally and historically significant districts of similar magnitude, significance and complexity. Resumes of project team members, examples of similar projects and references should be provided for purposes of evaluation.

b. Provide contact information (owner’s name, contact and telephone number) and description for 3-5 similar projects completed within the last five years.

5. Cost Proposal: Project fees must include the entire scope of work and final deliverables, in matrix format with hourly rates for assigned staff, noting tasks and subtasks.

a. Fees shown shall include all costs and expenses (copying, mileage, photographs, etc.) to complete the scope of work and resulting report.

b. Organize the cost proposal spreadsheet as follows:

i. Roles organized across columns and grouped by discipline.

ii. Cost/hour for each role, row below.

iii. Tasks/subtasks listed in rows.

iv. Do not insert staff names in lieu of roles.

FEE AND PAYMENT

Progress payments to the Contractor shall be made on the basis of proper and acceptable invoices submitted consistent with the quality requirements described in Stipulation 3 above, for the actual percentage of services completed by the Contractor and shall be made in accordance with the provisions of Section I Contract Clauses except as follows:

All submittals under this agreement must be approved by the COR prior to any interim or final payment. Invoices will be submitted first to the COR and may be submitted monthly.

A. Invoices shall include an itemized cost summary of staff work and direct expenses in a level of detail that matches the task agreement proposal, with invoicing based on percent complete for each task and subtask line.

B. Following COR acceptance of the invoice, submittal to the Invoice Processing Platform (www.IPP.gov) is required.

C. When an invoice is not associated with a required submittal, the invoice shall be accompanied by a brief (one paragraph) narrative of the work represented by the invoice.

POINTS OF CONTACT:

Contractual: Contracting Officer (CO): TBD Contracting Officer’s Representative (COR) and Project Manager: Barbara Judy, (229) 591-5350, Barbara_Judy@nps.gov ABLI Point of Contact: Stacy Humphreys, Chief of Interpretation and Resource Management, ABLI, 2995 Lincoln Farm Road, Hodgenville, KY, 42748, (270) 358-3137, stacy_humphreys@nps.gov CUGA Point of Contact: Jessica McNeil, Cultural Resource Program Manager, CUGA, 91 Bartlett Park Road, Middlesboro, KY, 40965, jessica_mcneil@nps.gov

APPENDIX A - MISSION 66 STRUCTURES/FEATURES

During proposal preparation as well as during performance of the work, the Contractor should make use of the Technical Information Center (TIC) at the NPS Denver Service Center (DSC), which is the oldest and largest information system in the National Park Service. TIC has a newly launched public website: pubs.etic.nps.gov that has made more than 32,000 NPS records, drawings and documents in a convenient, user-friendly, digital way available to the public and researchers. The COR will separately provide researchers with a list of all TIC records for the resource, as not all records are publicly released. Based on Contractor selection, these non-public records will be retrieved.

Abraham Lincoln Birthplace National Historical Park Between 1955 and 1965, the Abraham Lincoln Birthplace National Historical Park was developed under the Mission 66 program. Following approval of a Master Plan, structures including the Visitor Center, Employee Residences, Sanitary Facilities, Offices, Workshops and Equipment Buildings, Utilities, Roads and Trails, and planting plans were constructed. Park staff advise that the Visitor Center has been extensively altered in prior years.

Contractor should assume that up to twenty-five (25) structures will be assessed.

Identified ABLI Mission 66 Structures

Location Name
FMSS Number
Building/Location Type
Exterior Construction Type
Unit of Measure
Date Built
1
Birthplace Picnic Area Restrooms
66945
Comfort Station
Masonry/CMU
360 SF
1970
2
Visitor Center Bldg.
67236
Visitor/Interp
Masonry/CMU
8064 SF
1959
3
Maintenance Shop
67250
Serv/Shop/Maint
Masonry/CMU
2880 SF
1959
4
Q-00000008 67260 Three Bedroom House
67260
Housing-Single Family
Wood/Wood
1428 SF
1959
5
Q-00000009 67263 Three Bedroom House
67263
Housing-Single Family
Wood/Wood
1428 SF
1959
6
Quarters Parking Area
102449
Paved
Ashalt
1,620 SF
1959
7
Overflow Parking
102541
Gravel
Gravel/Rock
10,675 SF
1958
8
Old Quarters Road
102542
Paved
Ashalt
0.03 Mi
1959
9
Birthplace Water Distribution System
110795
Potable
NA
1,201 GPD
1959
10
Birthplace Picnic Area Water Distribution
110796
Potable
NA
450 GPD
1970
11
Birthplace Wastewater System
110799
Sanitary Sewer
NA
35 GPD
1959
12
Birthplace Picnic Area Pads
66918
Maintained Landscape
Concrete
0.40 AC
1968
13
Birthplace Picnic Area Trails
66952
Class lll Trail
Gravel/Rock
5,444 LF
1970
14
Birthplace Picnic Area Loop Road
66953
Paved
Ashalt
0.19 Mi
1968
15
Boundary Oak Trail
67002
Class lll Trail
Gravel/Rock
1332 LF
1970
16
Birthplace Picnic Area Parking Lot
74794
Paved
Ashalt
6,989
1968
17
V.C. Landscape Land Surface
1512667
SURFACE \ LANDSURF
Grass
696,960 SF
1958

From the IRMA data store: (https://irma.nps.gov/DataStore/)

Code
Title
Date Of Issue
2185522
Abraham Lincoln Birthplace National Historic Site, National Park Service. Cultural Landscape Report.
01/01/2004
2214908
Lincoln Boyhood Home at Knob Creek: Cultural Landscape Report, Abraham Lincoln Birthplace National Historic Park, National Park Service.
01/01/2013
2188595
Abraham Lincoln Birthplace Memorial Landscape: Cultural Landscape Inventory, Abraham Lincoln Birthplace National Historic Site
07/22/2008
2185292
Abraham Lincoln Birthplace National Historic Site: Cultural Landscape Report, Abraham Lincoln Birthplace National Historic Site
01/01/2004

From ETIC

TIC#
Title
Type
Date
41901
Aerial Photograph Index
F-TIC Aerial
05/31/1955
FL01
Aerial Photography - Park General
F-TIC Aerial
05/01/1955
2015
Replacement Of Stair Landings & Walks
E-TIC Drawing
04/01/1955
2007-E
General Development Plan - Part Of The Master Plan (Revision E)
E-TIC Drawing
10/30/1957
3002
Proposed Slope Design Sketch : Relocation Of U.S. Highway 31E
E-TIC Drawing
05/01/1957
3008
Employees Residences
E-TIC Drawing
02/01/1958
3008-A
Employees Residences
E-TIC Drawing
03/01/1958
3014
Entrance Gate & Sign - Park Entrance
E-TIC Drawing
01/01/1958
2007-D
General Development Plan - Part Of The Master Plan (Revision D)
E-TIC Drawing
03/26/1958
3012-A
Layout & Grading Plan - Visitor Center & Residences - Sewer & Water System
E-TIC Drawing
04/01/1958
3009
Visitor Center - Headquarters
E-TIC Drawing
03/01/1958
3004-B
Residences Road & Visitor's Center Parking
E-TIC Drawing
03/01/1958
3007
Residential Area Layout And Grading Plan
E-TIC Drawing
02/01/1958
3007-A
Residential Area Layout And Grading Plan
E-TIC Drawing
03/01/1958
3009-A
Visitor Center - Headquarters
E-TIC Drawing
03/01/1958
3013
Planting Plan - Visitor Center & Parking Area
E-TIC Drawing
03/01/1958
2016-A
Location Plan : Sign System Plan
E-TIC Drawing
11/17/1958
3005
Master Plan - Existing Conditions Map - 1957
E-TIC Drawing
01/01/1958
3006-A
Master Plan - General Development
E-TIC Drawing
04/01/1958
3003
Master Plan - Road And Trail System Plan
E-TIC Drawing
11/01/1958
3011-A
Part Of The Master Plan - Utility Layout Plan
E-TIC Drawing
04/01/1958
3010-A
Sewer & Water System - Visitor Center
E-TIC Drawing
03/01/1958
3014-B
Entrance Gate & Sign - Park Entrance
E-TIC Drawing
04/01/1959
2017
Museum Benches -- Headquarters
E-TIC Drawing
02/01/1959
3015
Entrance Planting
E-TIC Drawing
12/01/1959
P5
Visitor Center
V-TIC Visual
01/01/1960
3003-A
Master Plan - Road And Trail System Plan
E-TIC Drawing
09/01/1960
P19
Visitor Center
V-TIC Visual
01/01/1960
MPNAR
Mission 66, Volumes 1 & 3
D-TIC Document
01/01/1961
3011-C
Part Of The Master Plan - Utility Layout Plan
E-TIC Drawing
12/01/1962
3003-B
Master Plan - Road And Trail System Plan
E-TIC Drawing
11/21/1962
3011-D
Part Of The Master Plan - Utility Layout Plan
E-TIC Drawing
10/22/1963
3006-B
Master Plan - General Development
E-TIC Drawing
12/02/1963
3016
Part Of Master Plan - Climatological Base Map
E-TIC Drawing
07/16/1963
3020
Part Of Master Plan - Existing Conditions : Architecture - Memorial Building
E-TIC Drawing
08/01/1963
3018
Part Of Master Plan - Highway Access & T.V.A. Reservoirs
E-TIC Drawing
10/01/1963
3017
Part Of Master Plan - Historic Information - Photographs
E-TIC Drawing
08/01/1963
3017-A
Part Of Master Plan - Historic Information - Photographs
E-TIC Drawing
10/01/1963
3021
Part Of Master Plan - Narratives
E-TIC Drawing
12/02/1963
3019
Part Of Master Plan - Plan Of Interpretation
E-TIC Drawing
10/22/1963
3010-Z1
Part Of The Master Plan - Existing Conditions Architecture
E-TIC Drawing
08/01/1963
MPNAR-Z1
Master Plan, Chapters 1-3
D-TIC Document
01/01/1964
3006-C
Master Plan - General Development
E-TIC Drawing
08/01/1965
3006-D
Master Plan - General Development
E-TIC Drawing
10/05/1965

TYPICAL MISSION 66 VIEWS (CURRENT VIEWS):

TYPICAL MISSION 66 VIEWS (PERIOD VIEWS):

Cumberland Gap National Historical Park Between 1955 and 1965, Cumberland Gap National Historical Park was developed under the Mission 66 program. Following approval of a Master Plan, structures including the transportation infrastructure, campgrounds, landscaping, Visitor Center, employee residence and equipment storage, entrance road and parking, utilities, an amphitheater were constructed. Park staff advise that the Visitor Center has been extensively altered in prior years.

Contractor should assume that up to seventy (70) structures will be assessed.

Identified CUGA Mission 66 Structures

FMSS No.
Asset name
Date of Construction
Primary Latitude
Primary Longitude
1
101824
Little Yellow Creek Bridge #1, 5230-002P
1970
+36.6035
-83.691638
2
106546
Little Yellow Creek Culvert #1, 5230-003P
1961
+36.6035
-83.691694
3
101825
Sugar Run Road Bridge, 5230-001P
1958
+36.610972
-83.678277
4
38599
Banner Field Trail
1955
+36.57975
-83.682194
5
45484
Brush Mountain Trail
1955
+36.672555
-83.5275
6
38908
Chadwell Gap Trail
1960
+36.654361
-83.502055
7
106555
Colson Trail
1955
+36.604731
-83.637115
8
38917
Ewing Trail
1960
+36.652583
-83.435916
9
45488
Fort McCook Trail
1860
+36.608333
-83.674277
10
45491
Ft Lyon Trail
1860
+36.60575
-83.667583
11
38913
Gibson Gap Trail
1960
+36.603416
-83.629944
12
38905
Green Leaf Nature Trail
1958
+36.603583
-83.631722
13
38907
Honey Tree Spur Trail
1960
+36.606694
-83.633027
14
38918
Indian Rockhouse Trail
1960
+36.669611
-83.534638
15
38906
Lewis Hollow Trail
1960
+36.603888
-83.632333
161
38952
LMU Trail
1955
+36.576611
-83.680166
7
38882
Pinnacle Loop Trail and Overlook
1956
+36.606333
-83.666972
18
38887
Ridge Trail
1956
+36.607138
-83.667444
19
38909
Sand Cave Trail
1960
+39.667805
-83.45883
20
38904
Skylight Cave Trail
1958
+36.615861
-83.64375
21
45487
Tennessee Trail (Old Iron Furnace Trail)
1955
+36.601166
-83.668305
22
38760
Tri State Trail
1860
+36.606694
-83.673611
23
43482
Sugar RunPicnic Area
1960s
+36.636196
-83.668598
24
25107
Wilderness Road Campground Maintained Landscape
1960
+36.601777
-83.630583
25
25308
Wilderness Road Picnic Area Maintained Landscapes
1960
+36.609517
-83.637941
26
242913
CUGA-Corn Crib
1967
+36.6725
-83.5255
27
242351
CUGA-Sugar Run Pump House
1968
+36.636645
-83.668986
28
93435
Cupp Cabin (Martins Fork)
1966
+36.671384
-83.513401
29
25596
Fire Use Module Building
1964
+36.60476
-83.6328
30
99964
Group Shelter @ TW Civic Park
1970
+36.652593
-83.435789
31
25909
Gym Storage Building
1965
+36.597916
-83.694757
32
25263
Headquarters Building
1966
+36.599098
-83.694168
33
25269
Interp/RM/Artifact Storage Building
1966
+36.599975
-83.693
34
114101
Law Enforcement Fire Cache
1967
+36.599876
-83.692836
35
109854
LE Ranger Fuel Storage Building
1965
+36.599981
-83.692743
36
25915
Maintenance Equipment Storage #1
1966
+36.598337
-83.69512
37
25916
Maintenance Equipment Storage #2
1966
+36.598547
-83.695309
38
25265
Maintenance Shop
1966
+36.598981
-83.695174
39
93434
Maintenance Fuel Storage Building
1968
+36.598592
-83.695003
40
25306
Pinnacle Comfort Station
1956
+36.606573
-83.666489
41
25658
Pinnacle Pump House
1964
+36.606132
-83.672636
42
25262
Ranger Station
1966
+36.600147
-83.692761
43
25264
Resource Management Office
1966
+36.598275
-83.694739
44
25268
Roads and Trails Building
1966
+36.599133
-83.694964
45
25304
Sugar Run Comfort Station
1968
+36.636046
-83.668923
46
101199
Tri-State Peak Shelter
1964
+36.600772
-83.675339
47
25266
Visitor Center Building
1956
+36.602743
-83.695289
48
25267
Welding and Paint Shop
1966
+36.598755
-83.69528
49
109638
Wilderness Road Picnic Area Group Shelter
1960
+36.609203
-83.638605
50
25271
WRCG Comfort Station #1
1960
+36.60275
-83.631682
51
25272
WRCG Comfort Station #2
1960
+36.601879
-83.630761
52
25273
WRCG Comfort Station #3
1960
+36.600913
-83.629335
53
25601
WRCG Entrance Station
1964
+36.604188
-83.63281
54
109637
WRCG Group Shelter
1960
+36.600854
-83.628309
55
25910
Wilderness Road Campground Amphitheater
1960
+36.604085
-83.630862

Note: Assess whether older trails such as Piney Branch and Woodson’s Gap were revised during the Mission 66 development period.

From the IRMA data store: (https://irma.nps.gov/DataStore/)

Code
Title
Date Of Issue
2278817
Hensley Settlement Cultural Landscape Report, Cumberland Gap National Historical Park
08/01/2020
2229817
Recreating Appalachia: Cumberland Gap National Historic Park, 1922-1972
05/01/2015
106868
Restoration of Cumberland Gap and the Wilderness Road - Development Concept Plan, Environmental Assessment, Interpretive Prospectus
10/01/1990

From ETIC

TIC#
Title
Type
Date
60070
Davis Tavern Site
E-TIC Drawing
01/01/1955
60069
Iron Foundry Site, Furnace Chimney
E-TIC Drawing
01/01/1955
60069-A
Iron Foundry Site, Furnace Chimney
E-TIC Drawing
01/01/1955
60112
Pinnacle Overlook Area, Elevations
E-TIC Drawing
01/01/1955
60064
Topographic Map
E-TIC Drawing
01/01/1955
80014
Water System, Wilderness Road Campground
E-TIC Drawing
01/01/1955
3002
Existing Conditions
E-TIC Drawing
03/01/1955
60060
Parking Area - Pinnacle Overlook
E-TIC Drawing
08/01/1955
60080
Pinnacle Entrance Area
E-TIC Drawing
08/01/1955
60067
Pinnacle Overlook Area
E-TIC Drawing
08/01/1955
60068
Pinnacle Road Entrance Area
E-TIC Drawing
08/01/1955
60061
Skyland Road
E-TIC Drawing
09/01/1955
3001-B
Interim Development Plan
E-TIC Drawing
09/09/1955
3008
Existing Conditions
E-TIC Drawing
09/27/1955
2001-A
Boundary Map
E-TIC Drawing
10/01/1955
2004
Entrance Sign
E-TIC Drawing
10/01/1955
3008-A
Existing Conditions / Suggested General Development Overlay
E-TIC Drawing
10/01/1955
60079
Proposed Administration Area
E-TIC Drawing
10/01/1955
60071
Utilities, Timber And Miscellaneous, Proposed Administration Area
E-TIC Drawing
10/01/1955
3003-A
Development Plan
E-TIC Drawing
11/01/1955
2002
Log House Rehabilitation
E-TIC Drawing
11/01/1955
60084
Proposed Water Line - Log Cabin - Pinnacle
E-TIC Drawing
11/01/1955
2050-Z1
Proposed Administrative Area, Cumberland Mountain Hotel Site
E-TIC Drawing
11/25/1955
7150-A
Park Boundaries
E-TIC Drawing
01/01/1956
60081
Park Boundaries, Kentucky-Tennessee-Virginia Total Acreage
E-TIC Drawing
01/01/1956
60065
Top Soil Material
E-TIC Drawing
01/01/1956
2005
Boundary Sign
E-TIC Drawing
02/01/1956
3014
Entrance To Skyland Road & Midway Parking Overlook
E-TIC Drawing
02/01/1956
3001-A
Interim Development Plan
E-TIC Drawing
02/01/1956
3011
Parking, Overlook, And Trails
E-TIC Drawing
02/01/1956
3001-C
Interim Development Plan
E-TIC Drawing
02/08/1956
60063
Interim Interpretive Tour Plan
E-TIC Drawing
03/23/1956
3016
Pinnacle Comfort Station - Sewerage System
E-TIC Drawing
06/01/1956
3013-A
Pinnacle Comfort Station Water
E-TIC Drawing
06/01/1956
2006-A
Planting & Entrance Sign-Kentucky
E-TIC Drawing
06/01/1956
2006
Planting&Entrance Sign-Kentucky
E-TIC Drawing
06/01/1956
3018
Us Hwy. 25E & 58 Relocation
E-TIC Drawing
06/01/1956
3017
Water Supply & Sewer Disposal
E-TIC Drawing
06/01/1956
3012-A
Information Shelter & Comfort Sta.
E-TIC Drawing
07/01/1956
60075
Overlook Terrace Wall
E-TIC Drawing
07/01/1956
60066
Cross Sections Of Borrow Pit
E-TIC Drawing
07/09/1956
2009-A
Boundary Map
E-TIC Drawing
08/01/1956
3012-B
Information Shelter & Comfort Station
E-TIC Drawing
08/01/1956
7150
Park Boundaries
E-TIC Drawing
08/01/1956
60081-A
Park Boundaries, Kentucky-Tennessee-Virginia Total Acreage
E-TIC Drawing
08/15/1956
60085
Park Boundaries, Tennessee - Kentucky - Virginia Acreage
E-TIC Drawing
08/15/1956
3003-B
Development Plan
E-TIC Drawing
08/21/1956
3008-B
Existing Conditions
E-TIC Drawing
09/01/1956
3003-C
Development Plan
E-TIC Drawing
10/01/1956
2003
Headquarters Sign
E-TIC Drawing
10/01/1956
2007
Virginia Entrance Sign
E-TIC Drawing
12/01/1956
3003-D
Development Plan
E-TIC Drawing
01/01/1957
60062
Development Plan, Cumberland Gap Area, Part Of The Master Plan
E-TIC Drawing
01/01/1957
1448
Entrance Station Entrance
E-TIC Drawing
01/01/1957
2000
Topographic Base Map
E-TIC Drawing
01/01/1957
20052
Site Studies-Us Rte 25E-Scheme A&B
E-TIC Drawing
01/03/1957
3015
Planting,Parking,Overlook & Trail
E-TIC Drawing
02/01/1957
3019-A
Skyland Road
E-TIC Drawing
02/01/1957
3020
Skyland Road&Overlooks
E-TIC Drawing
02/01/1957
3023
Cover Sheet For 3015 & 3024
E-TIC Drawing
03/01/1957
3015-A
Planting Plan - Pinnacle Parking,Overlook & Trails
E-TIC Drawing
03/01/1957
3025
Repair Pinnacle Parking
E-TIC Drawing
03/01/1957
3022
Standard Drinking Fountain
E-TIC Drawing
03/01/1957
3027-A
Ridge Trail Overlook Shelter
E-TIC Drawing
06/01/1957
3026-A
Tri-State Peak Shelter
E-TIC Drawing
06/01/1957
60073
Midway Parking Area Cross Sections
E-TIC Drawing
06/05/1957
D97
Master Plan Development Outline
D-TIC Document
08/21/1957
3003-G
Development Plan
E-TIC Drawing
09/04/1957
3015-B
Completing Planting Plan - Pinnacle Parking, Overlook, Trails
E-TIC Drawing
09/25/1957
3028
Planting Plans - Suger Run Road And Midway Parking Areas
E-TIC Drawing
09/25/1957
61144
Completing Planting Plan - Pinnacle Parking, Overlook, Trails
E-TIC Drawing
09/26/1957
60087
Map Of Property Claimed By Robert Pearman Heins And Treadway Within Park Boundaries
E-TIC Drawing
10/17/1957
60926
Tubular Column Details For Ridge Trail Overlook Shelter
E-TIC Drawing
11/22/1957
3029
Visitor Center & Utility Develop
E-TIC Drawing
01/15/1958
3032
Loop Trail & Skyland Planting
E-TIC Drawing
02/01/1958
3028-A
Planting - Skyland & Sugar Run
E-TIC Drawing
02/01/1958
3024-A
Planting Plan
E-TIC Drawing
02/01/1958
3030
Layout And Grading Plan, Visitor Center Parking Area
E-TIC Drawing
02/07/1958
3033
Visitor Center
E-TIC Drawing
03/01/1958
3030-B
Entrance Road & Visitor Center Parking Area
E-TIC Drawing
04/01/1958
3035
Picnic Table & Garbage Receptacle
E-TIC Drawing
04/01/1958
3029-A
Visitor Center & Utility Develop
E-TIC Drawing
04/01/1958
3036
Skyland Road
E-TIC Drawing
05/01/1958
3037
Us 25E Bridge
E-TIC Drawing
05/01/1958
3038
Grading Plan
E-TIC Drawing
06/01/1958
3031-A
Water & Sewer System
E-TIC Drawing
07/01/1958
60111
Skyland Road Portion - Original Cross Sections
E-TIC Drawing
07/24/1958
3033-B
Visitor Center
E-TIC Drawing
08/01/1958
3039
Connect Entrance Rd To Us 25E
E-TIC Drawing
09/01/1958
3029-B
Visitor Center & Utility Develop
E-TIC Drawing
10/01/1958
60106
Revision Of Sewer Line, Plan And Profile
E-TIC Drawing
10/07/1958
60088
Map Showing Pearman And Treadway Tracts In Claibourne Co. Tenn. And Location Of Original And Corrected Park Boundary Lines
E-TIC Drawing
11/18/1958
60920-A
Plan And Profile Of Proposed State Highway, Lee County Route 25
E-TIC Drawing
01/01/1959
3040
Planting,Grading & Seed
E-TIC Drawing
01/01/1959
3046-A
Wilderness Road Developed Area
E-TIC Drawing
01/18/1959
60920-B
Plan And Profile Of Proposed State Highway, Lee County Route 25
E-TIC Drawing
02/27/1959
3040-A
Planting,Grading & Seed
E-TIC Drawing
04/01/1959
3043
Projection Screen Vallances
E-TIC Drawing
04/01/1959
3041
Walk Scoring Pattern
E-TIC Drawing
04/01/1959
3042
Topographic Base Map, Part Of The Master Plan
E-TIC Drawing
04/27/1959
3042-A
Topographic Base Map, Part Of The Master Plan
E-TIC Drawing
04/27/1959
3042-B
Topographic Base Map, Part Of The Master Plan
E-TIC Drawing
04/27/1959
3042-C
Topographic Base Map, Part Of The Master Plan
E-TIC Drawing
04/27/1959
3042-D
Topographic Base Map, Part Of The Master Plan
E-TIC Drawing
04/27/1959
30003
East 10Th Street Property Map
E-TIC Drawing
06/01/1959
3046-B
Wilderness Road Developed Area
E-TIC Drawing
09/29/1959
3045
Fort McCook Parking
E-TIC Drawing
12/01/1959
3044
Sign, Gates & Miscellaneous Work
E-TIC Drawing
12/01/1959
3047
Campground - Wilderness Road
E-TIC Drawing
01/01/1960
80013
Drain Flume And Drop Inlets, Station 31+40 Of Skyland Road
E-TIC Drawing
01/01/1960
41960
Floor Plan, Visitor Center
E-TIC Drawing
01/01/1960
80006
Observation Deck Floor Plan, Headquarters Area
E-TIC Drawing
01/01/1960
60089
Plan And Profile Of Proposed Access To Standifer, Smith & Malone Farm And Russell Farm Across National Park Easement
E-TIC Drawing
01/01/1960
60074
Plan And Section Showing Subsurface Drainage Around Footings Of Mechanical Room
E-TIC Drawing
01/01/1960
80005
Service Entrance Vestibule, Visitor Center
E-TIC Drawing
01/01/1960
60015
Visitor Center Main Lobby
E-TIC Drawing
01/01/1960
60013
Visitor Center Patio Pots
E-TIC Drawing
01/01/1960
80006-A
Observation Deck Floor Plan, Headquarters Area
E-TIC Drawing
02/01/1960
30001
Land Acquisition Map
E-TIC Drawing
05/01/1960
3046
Wilderness Road Developed Area
E-TIC Drawing
09/29/1960
3039-A
Connect Entrance Rd To Us 25E
E-TIC Drawing
10/01/1960
3047-Z1
Campground Layout - Wilderness Road
E-TIC Drawing
11/22/1960
60078
Map Of J. F. Schneider And Son Tract No. 80 Showing Location Of Buildings
E-TIC Drawing
12/09/1960
60078-A
Map Of J. F. Schneider And Son Tract No. 80 Showing Location Of Buildings
E-TIC Drawing
12/09/1960
3049
Comfort Station
E-TIC Drawing
02/01/1961
2050
Traffic Flow 1961
E-TIC Drawing
06/01/1961
61021
Map Of Property Required From The City Of Cumberland Gap For Development Of The Tri State Corner Area
E-TIC Drawing
08/07/1961
3101
Camptenders Quarters
E-TIC Drawing
09/01/1961
D96
Master Plan Development Outline & Narrative
D-TIC Document
10/13/1961
3102
Tri State Marker
E-TIC Drawing
01/01/1962
2009
Boundary Map
E-TIC Drawing
04/01/1962
25900
Tracing Of War - Time Map / Vicinity
E-TIC Drawing
04/01/1962
30961
Overlay Showing Shawanee, Through Which State May Reroute Highway 25E, Also Tentatively Proposed City Street Extension To U.S. Highway 25E
E-TIC Drawing
04/20/1962
3047-A
Campground - Wilderness Road
E-TIC Drawing
06/01/1962
3048-A
Campground Sewer & Water
E-TIC Drawing
06/01/1962
3102-A
Tri State Marker
E-TIC Drawing
08/01/1962
60093
Sketch Of Spence Tract Along With Nps Boundary Lines As Shown In Deed And By Survey (Glenn Justice)
E-TIC Drawing
08/15/1962
30000
Land Acquisition Map
E-TIC Drawing
09/01/1962
3100-A
Picnic Road & Campground Loop
E-TIC Drawing
12/01/1962
3104
Road & Trail System Plan
E-TIC Drawing
02/01/1963
60091-A
Map Showing Property Along Park Boundary East Of 10Th Street - Middlesboro, Ky
E-TIC Drawing
02/05/1963
D98
Completion Report - Purchase Picnic Tables, Benches, Fireplaces And Refuse Container Units
D-TIC Document
02/28/1963
3101-A
Camptenders Quarters
E-TIC Drawing
03/01/1963
3106
Comfort Station
E-TIC Drawing
03/01/1963
3105
Amphitheatre & Miscellaneous Construction
E-TIC Drawing
04/01/1963
3103
Water Supply & Sewage Disposal
E-TIC Drawing
04/01/1963
3105-A
Amphitheatre & Misc.Construction
E-TIC Drawing
05/01/1963
3107
Full Size Lettering Layouts
E-TIC Drawing
06/01/1963
60082
Map Showing Reulsions In Boundary Lines In Cumberland
E-TIC Drawing
06/19/1963
3108
Tri State Peak Shelter
E-TIC Drawing
12/01/1963
60096
Fire Trails, General Location And Distances
E-TIC Drawing
04/13/1964
D101
Completion Report - Wilderness Road Campground And Picnic Area, Amphitheater Construction, Entrance Sign Construction
D-TIC Document
04/21/1964
3104-A
Road & Trail System Plan
E-TIC Drawing
04/28/1964
3104-B
Road & Trail System
E-TIC Drawing
05/01/1964
3105-B
Amphitheatre & Misc.Construction
E-TIC Drawing
06/01/1964
3109
Amphitheatre & Shelter Development
E-TIC Drawing
06/01/1964
3110-A
Campground Sewer & Water
E-TIC Drawing
06/01/1964
3108-A
Tri State Peak Shelter
E-TIC Drawing
06/01/1964
60047
Sewer Line From Schneider Packing House To Connection With Existing City Sewer
E-TIC Drawing
07/21/1964
60076-A
Job Corps Camp Site
E-TIC Drawing
07/29/1964
60076
Job Corps Camp Site
E-TIC Drawing
07/29/1964
2910
Column Details&Anchor Bolt Layout
E-TIC Drawing
09/01/1964
60058
Willie Gibbons Farm Site
E-TIC Drawing
09/13/1964
3111
Tri-State Markers
E-TIC Drawing
10/01/1964
D100
Completion Report - Wilderness Road Campground And Picnic Areas
D-TIC Document
11/06/1964
60051-A
Pinic Area, Wilderness Road Campground
E-TIC Drawing
11/25/1964
60916
Cumberland Gap Route 25E Relocation Proposals
E-TIC Drawing
01/01/1965
2052
Gap Job Corps Camp-Bartlette Park
E-TIC Drawing
01/01/1965
D19
History Of Cumberland Gap
D-TIC Document
01/01/1965
60048
Plan, Gas Line From Avondale Avenue To Construction Site
E-TIC Drawing
01/01/1965
80007
Temporary Lighttrap - Assembly Room, Visitor Center
E-TIC Drawing
01/01/1965
60077
Topographic Map Of Residence Area, Administration Area
E-TIC Drawing
01/01/1965
80008
Visitor Center Fitness Trail
E-TIC Drawing
01/01/1965
2052-A
The Gap Job Corps Camp, Bartlette Park
E-TIC Drawing
03/10/1965
80004
Concrete Surfaced Play Area, Job Corps Conservation Center
E-TIC Drawing
05/12/1965
60000
Proposed Works Building/J.C.C.C
E-TIC Drawing
05/28/1965
2053-A
Base Course And Surfacing, Job Corps Conservation Center
E-TIC Drawing
06/01/1965
136090
U.S. Highway 58 - Alternatives A,B,C, Alignments
E-TIC Drawing
06/01/1965
60083-A
Job Corps Conservation Center
E-TIC Drawing
06/07/1965
3112-A
Tri-State Marker Parking
E-TIC Drawing
07/01/1965
41900
Virginia Route 25
E-TIC Drawing
07/01/1965
60920
Plan And Profile Of Proposed State Highway
E-TIC Drawing
07/22/1965
3003-E
Development Plan
E-TIC Drawing
08/01/1965
3112
Tri-State Marker Parking
E-TIC Drawing
10/01/1965
60049
Proposed C&P Telephone Company Of Virginia, Facilities To Serve Camptender's Quarters
E-TIC Drawing
11/10/1965

TYPICAL MISSION 66 STRUCTURES (MODERN VIEWS):

APPENDIX B – GIS STANDARDS

NPS STANDARDS AND GUIDANCE

GIS data for the cultural landscape must follow the National Park Service Cultural Resource Spatial Data Transfer Standards found at:

https://irma.nps.gov/DataStore/DownloadFile/639911 At the contractor’s option, an empty GIS template that contains all of the various feature classes, feature level metadata fields and domains associated with the cultural resource spatial data transfer standards can be downloaded here:

https://irma.nps.gov/DataStore/Reference/Profile/2206880 Please note that this template was not designed for GPS data collection. GPS data should be used to guide creation of GIS data in this template.

Further information regarding spatial data for cultural resources can be found at:

https://www.nps.gov/crgis/

GPS EQUIPMENT AND FIELD RECORDATION

GPS Equipment. GPS/GNSS units must be of acceptable precision rating, produce data that can be differentially corrected (whether real-time or not), and be capable of exporting data into a format compatible with ESRI ArcGIS software.

The Contractor shall use their own computers and software capable of producing data and metadata compatible with ESRI ArcGIS. Though older NPS standards call for use of Trimble equipment and software, it is understood that a variety of GPS equipment and software, both from Trimble and other manufacturers, will be suitable for producing the required data deliverables.

GPS Equipment Precision Rating. GPS equipment must be capable of submeter accuracy when used with adequate position averaging and differential correction.

Field Recordation. See the appendices to this Statement of Work for a list of physical features that must be recorded. Where no list is provided, contractor shall plan to record all features identified through the project, both those that are potentially contributing (historic) and those that are non-contributing (non-historic). Typically, buildings, structures and objects larger than 3 meters across should be recorded by GPS with at least one corner point when possible GPS may be appropriate for other types of resources such as site areas and linear features.

An offset must be used for GPS data collection adjacent to structures when the structure deflects the satellite signals enough to move the estimated accuracy out of the required accuracy radius.

Use of Total Station. In cases where the contractor uses a total station with integrated GPS,…