A04 Fencing Repairs SOW.pdf
PDF 907 KB Posted
- Attached to
- GATE-REPAIR/REMOVE FENCING @GATE NRA
- Solicitation number
- 140P4520R0015
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P4520R0015_Amd_0003.pdf | ||
| Sol_140P4520R0015_Amd_0002.pdf | ||
| Price Schedule Rev 1_0002.docx | DOCX document | |
| A06 Fencing Repairs SOW Rev 1. docx_0002.docx | DOCX document | |
| Sol_140P4520R0015_Amd_0001.pdf | ||
| A06 Maps.pdf | ||
| Sol_140P4520R0015.pdf | ||
| References Worksheet.doc | DOC document | |
| Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
PMIS 00000 – Repair fencing or remove damaged fencing in various locations in
Miller Field, Fort Wadsworth and Riis Park in Gateway N.R.A.
STATEMENT OF WORK
1.0 Background
2.0 Scope
3.0 Objectives
4.0 Locations of Work
5.0 Tasks
6.0 Construction Requirements
7.0 Government-Furnished Property
8.0 Security
9.0 Period of Performance
10.0 Payment
11.0 Site Plan, Maps and Addenda
12.0 Project Closeout
13.0 Substantial Completion and Final Inspection
1.0 Background
Over the past year, Gateway National Recreation Area staff have noted damage to existing fencing in the Staten Island locations of Gateway National Recreation Area. Removal of damaged fencing at Riis Park was added in response to concerns expressed by constituents. It was decided to combine all the repair work into one contract in the interest of expediency.
2.0 Scope
This project will provide services for the repair or replacement of existing fencing in the Fort Wadsworth and Miller Field locations and removal of damaged fencing at Riis Park in Gateway National Recreation Area.
3.0 Objectives
The objective of this project is to repair existing damaged fencing in-kind for aesthetics as well as function. In some cases, the fence damage makes it easier for the public to access unsafe areas of the parks, such as structurally unstable gun batteries. In Riis Park, fencing has been damaged by vehicles in multiple locations and is heavily rusted. For a long length of 4’ chain-link fence in Riis, the mesh was washed off in the Sandy storm surge and never replaced.
Replacements will be done as part of a future project in 2021 provided that funding is found.
4.0 Locations of Work
Miller Field and Fort Wadsworth
1. Miller Field, Miller Field Playground (Basketball Court) Staten Island, New York
2. Miller Field Entrance at end of Father Capodanno Blvd.
3. Fort Wadsworth, near New York Ave & Battery Road, around Battery Upton.
4. Fort Wadsworth, on Loop road next to Battery Barry.
5. Fort Wadsworth, at the Battery Rd./McClain Ave. entrance.
6. Fort Wadsworth, along Ayres Road, around the waste material yard.
Riis Park
1. Riis Park picnic area, along the walkway, north side
2. Riis Park Parking Lot, south side, along perimeter lanes
3. Riis Park Parking Lot, west side, along access road
5.0 Tasks
Location 1. Miller Field Playground (Basketball Court)
Supply and install approximately 119’ x 10’ high chain link fence to connect to existing fence. Post and rail sizing and spacing shall match existing. Posts shall be set in concrete a minimum of 3’-2” deep. One (1) 4’ wide gate matching the other gate at these courts shall be installed. The gate will be installed at the existing walkway leading to the courts. Old post footings may be encountered and shall be removed entirely.
Location 2. Miller Field Entrance at Father Capodanno Blvd.
Re-hang ~88’ of 8’-6” chain link fence. Replace 10-12’ of damaged #9 x 2” black vinyl-coated steel mesh and replace four (4) broken or bent line posts. Posts shall be set in concrete a minimum of 2’ deep. Post spacing to match existing. Clean mesh of vegetative material, dirt and trash before re-hanging.
Location 3. New York Ave. & Battery Rd. around Battery Upton, Ft. Wadsworth
Existing fencing around the historic battery was damaged by a fallen tree. Replace bent section of top rail. Put chain link mesh fabric back in place and attach with wire ties. Roughly 34’ of 5’ high fence is damaged. Any broken or damaged vinyl slats shall be replaced in-kind. Check adjacent posts for damage and repair as needed.
Location 4. Along Loop road next to Battery Barry, Ft. Wadsworth Existing 5’ high fencing around the battery was damaged by falling trees. Replace bent section of top rail, roughly 49’. Replace roughly 30’ of damaged chain link mesh fabric and attach with wire ties. Check adjacent posts for damage and repair as needed.
Location 5. At the Battery Rd./McClain Ave. entrance., Ft. Wadsworth
The posts of the center pedestrian gate were damaged by vehicles.
One post is missing. Contact NPS Police for removal of the chain and lock. The posts shall be replaced with 3” dia. or larger posts, factory-coated in black vinyl. The posts shall be filled with mortar mix concrete for rigidity and strength. Posts shall be set in concrete a minimum of 2’ deep. Salvage any serviceable hardware such as hinges and bolts and clean and paint for re-use. The existing gate shall have a gate stop welded on, positioned so the gate only opens outward. The gate will then be cleaned, painted and re-hung. The existing sign on the gate shall be re-hung. Ensure proper alignment with the existing rolling vehicle gate. Any pavement removed or damaged by removal of the posts shall be replaced. Asphalt shall be sawcut along sound pavement. Joints of the asphalt patch shall be sealed with tar.
Location 6. Along Ayres road around the waste material yard, Ft. Wadsworth
Existing 5’ high fencing around the yard and adjacent batteries was damaged by falling trees or heavy vines. Cut vines from the fencing. Clean mesh of vegetative material and trash before re-hanging. Note that this section of fence is within a stand of Japanese Knotweed which will have to be cut down to access the fence. Inspect fencing all around the batteries.
Replace any missing or bent top rail. Most of this fence was not installed with a top rail and only needs coil wire. Re-hang all chain link mesh fabric that has been knocked down and attach with wire ties. Check posts for damage and repair or replace as needed.
Location 7. (a, b & c) Riis Park picnic area, along walkway, north side
Remove a total of 331 LF of existing 4’ high chain link fencing as noted on the plan sheet. Removal shall include concrete footings and any other below-grade hardware. Holes created by removal of posts shall be backfilled immediately.
Location 8. (a, b & c) Riis Park Parking Lot, along perimeter lanes, south side of lot
Remove a total of 488 LF of existing 4’ high chain link fencing as noted on the plan sheet.
Removal shall include concrete footings and any other below-grade hardware. 429 LF of this fencing is only posts. Holes created by removal of posts shall be backfilled immediately.
Location 9. Riis Park Parking Lot, along access road, west side of lot
Remove 155 LF of existing 4’ high chain link fencing as noted on the plan sheet. Posts shall be cut off flush with the pavement. Grind as needed to be level with grade.
General Notes, Fencing
A. Fence repairs shall match existing adjacent fencing in type of mesh, size, finish and hardware.
B. Chain link mesh shall be attached with wire ties. Tie wire shall be aluminum alloy 1100-
H14. Ties shall be spaced 1’ apart on posts and 18” apart on horizontal members. Ties shall make two loops around mesh wire for secure fastening. Coil wire shall be used on the bottom of fencing 6’ or less in height where there is no bottom rail. Mesh placement in relation to the posts (inside or outside) shall be the same as on adjacent fencing.
C. Fencing shall have 1 5/8” horizontal members (mid-rails) at gates, ends, and corners.
For 8’ high fencing, one horizontal member is required. 10’ high fencing shall have 1- 5/8” mid rails on all sections.
D. All fencing shall have 1 5/8” dia. top rails unless the adjacent existing fencing only has coil wire.
E. New or refurbished gates and the fence sections at gates shall have ½” diameter diagonal truss rods. For new gates, members shall be 1-7/8” dia.
F. All end, corner and gate posts shall have caps. Post cap is to be of malleable iron or pressed steel and have a smooth “dome” shape. Caps shall fit snugly and shall be set in place with two #14 stainless steel drive or set screws.
G. Concrete for footings shall be Class B-32, Type IIA; cement Type II Portland, sand Type
1A, coarse aggregate Type 1, Grade B or Type 2, Size #57.
H. Chain link fabric shall not be spliced between posts. Splices shall be made in such a way as to create a neat, finished appearance.
I. Chain link fabric on fences up to and including 6’ in height shall be knuckled on the top and bottom.
J. Vinyl-coated fence fabric shall be PVC-coated to meet the requirements of ASTM F668 for Class 2b chain link fabric. Thickness of the fusion bonded vinyl coating shall be 7-10 mils, color to be black. The vinyl coating shall be evenly applied and free of blisters. The bond between the vinyl coating and the steel fabric to be equal or greater than the cohesive strength of the vinyl.
K. Paint shall be Rust-oleum brand oil-based gloss enamel or approved equal. Color shall be black.
6.0 Construction Requirements
General Notes
A. Before work begins, the Contractor shall thoroughly survey the site and surrounding area and carefully note all environmental and human factors which may be adversely affected by the intended work. Potential problems should be brought to the attention of the Project Manager or his/her designated representative. The contractor shall be liable for any damage to existing trees, plants, buildings, and any other property caused by concrete work. The locations of underground utilities shall be verified before excavation.
B. Waste materials become the contractor’s responsibility and shall be removed from the site. Waste materials shall be disposed of in accordance with the law. See also “Environmental Requirements”.
C. Safety Plan
i. Contractor shall provide a safety plan for the work. Include traffic safety and flaggers where appropriate. The safety plan shall include the following and be approved in writing before the start of work.
ii. Name of responsible supervisor to carry out the program; monthly safety meetings;
first aid procedures; outline of each phase of work, hazards associated with each phase and methods proposed to ensure property protection, and safety of the public, planning for possible emergency situations; housekeeping and fire protection.
Environmental Requirements. The following are general requirements:
• Air: Employ construction practices that minimize combustion byproducts.
• Water: Avoid materials that can leach toxic chemicals into the ground water. Do not allow toxic chemicals to enter sewers or storm drains.
• Soil: Protect against erosion and topsoil depletion. Soil used as backfill shall be seeded with grass immediately after placement. A specification will be provided. Grass should cover 90% of seeded areas within two months of seeding. Driving or parking on lawn areas is not permitted. Materials and equipment shall be brought in by hand or tracked vehicle if no paved route to the work location is available. Any surplus soil from excavation for post-hole digging becomes the property of the park. Any deleterious or toxic material found in the soil shall be removed and hauled away. The contractor shall haul the surplus soil to a designated location within the limits of the park.
• Noise: Minimize noise generation during construction. Operate power equipment in accordance with local noise restrictions. Crews shall be considerate of beginning work in housing areas too early. Noise shall be minimized when working in proximity to housing.
• Waste Management Goals: Employ processes that ensure the generation of as little waste as possible. Waste disposal in landfills shall be minimized.
• Recycling is a requirement of this project.
• All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.
The Contractor shall designate an on-site party (or parties) responsible for instructing workers and overseeing the environmental requirements of this project. Distribute copies of the environmental requirements to the Job Site Foreman and each Subcontractor.
6.0 Delivery
A. Road Closures – No road closures are permitted.
B. On-street Parking – The contractor shall make every effort possible to have parked cars removed when in the way of work. Posting of “No Parking” signage the day before work is to begin is advised.
C. Traffic management– contractor shall use signage, traffic cones, and flaggers during work in streets as needed. Access to buildings shall not be hindered.
D. When working on the Father Capodanno entrance, equipment and vehicles must be kept on the Miller Field side. Usage of the city street is not permitted.
E. Any signage posted shall be removed immediately after related work is complete.
F. This project shall continue from start to finish on successive days until completion is reached. Allowances are made for inclement weather.
G. Working hours are from 7:00 am to 5:30 pm.
6.0 Government-Furnished Property
There will be no government furnished property for this Statement of Work. Contractor may use public restrooms at work sites. Storage of equipment on site may be allowed in certain cases.
Written permission from the Project Manager will be required.
7.0 Security
Entry gates shall not be left in an unsecured condition overnight. Temporary fencing shall be put in place and chained to existing fencing if work cannot be completed in one day. No building access is available.
9.0 Period of Performance
A. Period of performance shall be 90 days from issuance of the Notice to Proceed.
B. Contractor shall prepare and submit a schedule for this project. Scheduling will be crucial to inform park staff, residents, and visitors of the events that may affect their residences and work areas.
10.0 Payment
A Schedule of Values shall be furnished by the contractor before the start of work. Payments shall be based on work completed per the SOV.
11.0 Site Plan, Maps and Addenda
Refer to the work locations as called out on the air photos.
12.0 Project Close-out
Cleaning: Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Revegetate areas that are damaged due to the work of this contract to original condition. Patch any areas where pavement was removed. The contractor shall leave the site clean and free of left-over materials upon completion of the work. At time of final inspection, fencing shall be intact and sound and all gates shall swing freely.
13.0 Substantial Completion and Final Inspection
Submit written certification that project, or designated portion of project, is substantially complete, and request in writing a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer or his/her designated representative, will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
When work is determined to be substantially complete, the Contracting Officer or his/her designated representative, will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The Contracting Officer or his/her designated representative will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the Contracting Officer will notify the DBC in writing. After completing work, the DBC shall resubmit certification and request a new final inspection.
If, following final inspection, the work is determined to be substantially complete, Contracting Officer or his/her designated representative will prepare a list of deficiencies to be corrected before final acceptance and issue a Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer or his/her designated representative may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs.
Acceptance of the work: After all deficiencies have been corrected, the Contracting Officer or his/her designated representative will issue a Letter of Acceptance.