This bid schedule outlines design-build services for replacing water supply lines at the Mammoth Spring National Fish Hatchery. It requests lump sum pricing for site survey, geotechnical investigation, schematic design, design development, and construction document services. Pricing is also to be determined for construction services during the design phase. The related federal contract opportunity is solicitation number 140F0421R0018 for water supply line replacement projects at the Mammoth Spring National Wildlife Refuge, issued by the Department of the Interior Fish and Wildlife Service.

View the file

Other files

File Type Posted
Sol_140F0421R0018.pdf PDF
General Decision.pdf PDF
A04 Statement of Work (SOW) Rev1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

Design-Build Services for the Mammoth Spring NFH Replace Water Supply Lines Project

Item Number Description Unit Amount

NOTE Please use the Attached DB Fee Proposal Spreadsheet to show Proposed Design Costs for this Project in detail in addition to completing items below.

0001 Site/Topographic Survey Lump Sum $___________

0002 Geotechnical Investigation Lump Sum $___NA____

0003 Schematic Design Services Lump Sum $___________

0004 Design Development Services Lump Sum $___________

0005 Construction Documents Services Lump Sum $___________

SUBTOTAL CLINS (0001-0005) $___________

0006 Construction Services Lump Sum $___TBD____

TOTAL AMOUNT (CLINS 0001-0006) $___________

NOTE: Construction Services are to be determined (TBD) during design.