A04.01 N4523A21R1062 Edgecumbe - Draft SOW 14JAN2021.pdf

PDF 939 KB Posted

Attached to
Preservation of the Edgecumbe Barge
Solicitation number
N4523A21R1062
Issued by

About this file

This notice announces the Department of the Navy's intent to solicit Motive Power Marine, LLC on a sole-source basis for preservation work on the Edgecumbe Barge. The scope of work includes transporting the barge to the contractor's facility, docking and cleaning the exterior, blasting and preserving the hull and Tank 70, and returning the barge to the Navy. The barge measures 240 feet long, with a draft of 3 feet and width of 60 feet. Responses are due by February 27, 2021 from HUBZone certified firms within the Puget Sound region of Washington that can meet the requirements. The period of performance is May 1 to July 1, 2021. The associated NAICS code is 336611. The justification for other than full and open competition is the HUBZone Act, as Motive Power Marine is the only qualified HUBZone contractor that can perform the work.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Edgecumbe Barge 2021

COVER SHEET – STATEMENT OF WORK (SOW)

N4523A21R1062

SOLICITATION COPY

Date Prepared:

Version: One Jan 14, 2021

ERRATA One:

24 June 2008

DRAFT

Table of Contents

Paragraph / Section Page Number

1.0 General Requirements 3

1.1 Vessel Characteristics 3

1.2 Scope Overview 3

1.3 Definitions 4

1.4 Arrival Conference 4

1.5 Required Documents 5

1.6 Progress Meetings 6

1.7 Availability Requirements 6/7

1.8 Care of Vessel 8

1.9 Quality Management 9

1.10 General Requirements for Testing and

Inspections 9/10

1.11 Workmanship 10/11

1.12 Corrective Action Request (CAR) 11

1.13 Condition Found Report (CFR) 11/12

1.14 Interferences 13

1.15 Safety 13/14

1.16 Hotwork/Welding 15

1.17 Access Cuts 16/17

1.18 Threaded Fasteners 17/18

1.19 Preservation 18/20

1.20 Environmental and Hazardous Waste

Management 21/22

1.21 Materials 22

1.22 Gas Free 22

2.0 References 23

2.1 Order of Precedence 23

2.2 Discrepancies 23

Consolidated List of References 24/25 DRAFT

3.0 Work Requirements 25

3.1 Docking and Undocking the Vessel 25/30

3.2 Hull Repairs 30/31

3.3 Tank 70 Repairs 31/33

4.0 Government Furnished Material (GFM) 34

Statement of Work (SOW)

1.0 General Requirements: This document invokes the requirements applicable to the docking and maintenance work to be performed on one each Edgecumbe Barge. Work performed and accomplished shall be in accordance with the highest quality workmanship standards and practices commonly accepted in the commercial marine industry and the technical references listed herein. The Contractor is responsible for understanding and complying with all requirements specified herein. The requirements listed herein work in conjunction with the technical drawings and other references to describe the essential features, functions, and requirements of the work performed.

1.1 Vessel Characteristics:

Edgecumbe Barge Built by: Zidell Exploration Length: 240 FT Draft: 3 FT Width: 60 FT Age: 42 YRS Light Load 921 L Tons Hull Type: Steel

1.2 Scope Overview: Coordinate with the Contracting Officer, via the Contracting Officer’s Representative (COR) to deliver the vessel to the Contractor’s facility. Dock, wash, and clean the exterior surfaces of the vessel upon docking. Blast and preserve hull, freeboard, and Tank 70. Undock the vessel. Arrange and coordinate the delivery of the vessel back to the Government with the Contracting Officer via the COR.

1.3 Definitions: As used throughout this Specification, the following definitions and terms have meanings as indicated:

1.3.1 Unless otherwise stated, “As shown”, “as indicated”, “as detailed”, or other words of similar import refer to the contractual documents including reference documents and publications.

1.3.2 The words “as directed”, “as approved”, “when authorized” or words of similar import refer to the direction, requirements, permission, approval, or acceptance by the Contracting Officer.

1.3.3 The term “Objective Quality Evidence” (OQE) shall mean current, accurate, and complete objective documentation and information submitted together as a complete data package sufficient that a qualified and disinterested third party could analyze and evaluate whether technical requirements were achieved.

1.3.4 Where “in accordance with Regulatory Body requirements” is stated, the industrial efforts shall be in accordance with the appropriate commercial regulatory body requirements unless otherwise authorized by the Government.

1.3.5 The term “marine” or “marine quality” means an item constructed of materials unaffected by moisture, sea spray, extremes in temperature or other hazards of the marine environment, and designed and constructed to perform its intended functions under marine operating conditions.

1.3.6 The term “herein” means the applicable section(s) of this Specification.

1.3.7 The term “NAVSEA” means the Naval Sea Systems Command, one of five system commands, responsible for engineering, building, supporting, and maintaining the Navy’s fleet of vessels.

1.4 Arrival Conference: The Government will arrange an arrival conference with the Contractor after contract award.

1.5 Required Documents:

1.5.1 Administrative requirements of this SOW shall commence at contract award and be updated throughout the contract period.

1.5.2 Prepare and keep current schedules necessary for the purpose of establishing an orderly and systematic accomplishment of production work and material ordering. (CDRL A001)

1.5.3 Maintain a list of all subcontractors with extent of work to be accomplished by each subcontractor.

1.5.4 Maintain a list of manufacturer’s Technical Representatives to be provided per the particular specification requirement.

1.5.5 Maintain a Welder Qualification List, with name, type of qualification(s) and date of last qualification test for each qualification.

Qualification List shall be available for immediate review upon request by the Government or American Bureau of Shipping (ABS) Surveyor.

1.5.6 Maintain manufacturer’s product data sheets for all materials to be used by the Contractor to accomplish the requirements of this contract.

(CDRL A002)

1.5.7 Maintain Safety Data Sheets (SDS) for all materials to be used by the Contractor to accomplish the requirements of this contract. (CDRL A003)

1.5.8 Maintain a list of key Contractor personnel with names, positions, certifications, telephone numbers, e-mail addresses, and emergency contact information.

1.5.9 Maintain a copy of the Contractor’s Inspection and Quality Control System with copies of all related forms, reports, and other supporting documentation.

1.5.10 Maintain a copy of the Contractor’s Environmental Protection and Hazardous Waste Management Plan, including Risk Management/Mitigation plans specific to this contract.

1.5.11 Maintain copies of required federal, state and local environmental notifications and permits for performance of the work (or a schedule of when they will be obtained).

1.6 Progress Meetings: Weekly progress meetings shall be held at the Contractor’s facility near the vessel. The day and time of the meeting shall be set by the COR upon consultation with the Contractor. A review of percentage completion for each work item shall be conducted including the Contractor’s assessment of schedule adherence. Production schedule, corrective action reports, material lead times and other issues shall be discussed.

1.7 Availability Requirements:

1.7.1 Arrange for and transport the vessel from the Government facility at Puget Sound Naval Shipyard (PSNS) in Bremerton, WA to the Contractor’s repair facility. Upon completion of all work coordinate delivery of the vessel to the Government facility at PSNS in Bremerton, WA. Provide all materials, labor, and insurance bonds necessary for the safe transport of the vessel to and from the Contractor’s facility and for the period that the vessel is located at the Contractor’s repair facility.

1.7.1.1 Vessel pickup and delivery schedule with the COR 5 working days prior to Vessel movement.

1.7.1.2 Existing Tow Gear shall not be used for towing and shall not be disturbed.

1.7.2 ABS Surveyor provide and accomplish 100 percent survey of each:

inspection, hull access cut plan, weld process, weld joint preparation, root pass, back gouge, final cover pass, and Non-destructive Test and Inspection.

1.7.2.1 Document accomplish 100 percent of each ABS Survey item listed in 1.7.2. ABS Surveyor shall sign and print name on each document.

(CDRL A004)

1.7.2.2 Each survey item listed in 1.7.2 shall be accepted by the ABS Surveyor. SOW requirements will not be considered complete until 100 percent of surveys and inspections are documented as satisfactory by the ABS Surveyor.

1.7.3 Provide heated/air conditioned office space measuring a minimum of 160 square feet and located within 1/4 mile of the vessel from 2 days prior to project start to 2 days after project completion for use by the COR.

1.7.2.1 The office space shall be equivalent to Satellite model 820MO, 8 feet X 20 feet interior size, with lockable doors and platform with stairs.

1.7.2.2 The office space shall be lockable, secure, and safe for personnel and equipment.

1.7.2.3 Provide Quantity (2 EA) keys for all doors and Quantity (2

EA) master keys to fit all locks to the COR.

1.7.2.4 Provide Quantity (One EA) work station with the following at each workstation:

1.7.2.4.1 Quantity (One EA) duplex 110 volt receptacle.

1.7.2.4.2 Quantity (One EA) desk, 30 inches wide x 48 inches

in length, with chair. Chair shall be adjustable in height, with swivel and adjustable arm rests.

1.7.2.4.3 Quantity (One EA) CAT-5 cable connection or

WIFI at 35 MBPS minimum download speed for a COR supplied desktop/laptop computer. This connection shall be separate from Contractor’s computer servers/networks.

1.7.2.4.4 Quantity (One EA) trash can.

1.7.2.5 Provide Quantity (One EA) parking space adjacent to the office space of 1.7.2 for the entire contract period.

1.7.2.5.1 Designate parking space with a sign stating "PSNS

PARKING ONLY".

1.7.3 Document the result of each test and inspection requirement throughout this SOW.

1.7.4 Tanks and voids opened shall be clean, dry, and pass Government inspection prior to being closed.

1.8 Care of Vessel:

1.8.1 The Contractor shall be responsible for the care of vessel equipment, materials, and components related to the work being performed.

1.8.2 Vessel shall be maintained in a broom clean condition on a daily basis. Vessel shall be free of visual contaminants such as oxide films, oils, grease, dust, dirt, or foreign material.

1.8.2.1 Remove and dispose of industrial debris and extraneous materials from each vessel on a daily basis.

1.8.3 Temporary protective measures shall be taken to avoid wear and damage to the Vessel and all associated components. Water shall not be allowed to accumulate in the hull or structure during work performance.

1.8.3.1 Open areas in structure shall be covered to prevent water entry.

1.8.4 Immediately Install and maintain blanks/plugs, nuts and bolts, painted blaze orange for use as foreign material exclusion (FME) upon equipment, openings in equipment, valves, and piping systems not subject to pressure to prevent entry of foreign material and protect flanges and threaded areas.

Existing system fasteners used for blanking that will be used for installation are excluded from the requirement for blaze orange color. The use of cloth, polyvinyl sheet, paper, tape, and rubber sheeting as FME is prohibited. FME material shall be applied to avoid damage to surfaces/equipment/components being protected.

1.8.5 Wood products, including damage control (DC) plugs are permitted for use as FME external to the vessel for hull penetrations.

1.8.5.1 DC plugs, wood, or wood products are prohibited for use in tanks.

1.9 Quality Management:

1.9.1 Workmanship provided by Contractor employees shall be consistent with the highest standards of commercial marine practices and regulatory bodies.

The Government reserves the right to accept or reject material and workmanship nonconformance. Noncompliance with Contractor’s quality control processes will influence past performance rating provided on contract evaluation. Plating and structural member cuts shall be neatly and accurately made with edges cleaned and prepared for welding. Sharp edges shall be ground smooth to avoid injury to personnel. The vessel shall be protected against weather hazards.

1.9.2 At the time of delivery, work performed shall meet the performance requirements specified. In the event that deficiencies are discovered during the Guarantee period, an opportunity will be afforded the Contractor to witness, inspect and comment on such deficiencies. Materials and articles used for work performed shall be of commercial marine quality, conforming to the requirements of the Regulatory Bodies listed herein unless specified to be otherwise.

1.9.3 The decision that an area is inaccessible shall be determined by inspection and agreed to by the COR prior to proceeding with the requirements of this SOW.

1.10 General Requirements for Testing and Inspections:

1.10.1 Test/Inspect all Contractor affected equipment for compliance with this SOW, Commercial Marine Standards and Practices, and ABS requirements.

Demonstrate workmanship, water tightness, functionality, and suitability for the purpose intended.

1.10.2 Develop a Test & Inspection Plan (TIP) for each Test/Inspection required by this SOW, containing paragraph number or listed applicable reference requiring Tests/Inspections; identification of each item; description of each Test/Inspection; accept/reject criteria; date scheduled; Government notifications; date completed; and each Test/Inspection result. (CDRL A005)

1.10.2.1 Fully integrate the TIP with the Contractor’s production schedule.

1.10.3 Provide a detailed description of each Test/Inspection to be conducted and the parameters to be satisfied. Develop signature sheets for fill-in by the person conducting each Test/Inspection, the ABS Surveyor, the Government witness present, and the date of each Test/Inspection. Include a comment sheet to record significant events and observations by either the Government witness, Contractor, or ABS Surveyor. (CDRL A005)

1.10.4 Provide materials, supplies, utilities, equipment, calibrated equipment/instrumentation, services and personnel to accomplish each Test/ Inspection. Incorporate safety precautions into each Test/Inspection procedure.

1.10.5 The COR or his representative shall receive notification a minimum of 5 work days prior to each Test/Inspection. Equipment shall not be adjusted during acceptance testing. The COR may countersign the acceptance Test/Inspection report, however the Government’s signature does not constitute approval or concurrence in any aspect of the Testing/Inspection, other than the presence of the Government at the test.

1.10.6 Perform tests using the applicable test procedure. Demonstrate compliance with the Specification requirements by satisfactory completion of the test. Complete all work prior to initial testing of that particular system or subsystem and in a timeframe sufficient to allow for correction of deficiencies prior to dock trials, sea trials, or other applicable milestones established in these specifications. Perform adjustments and testing prior to each scheduled acceptance test.

1.11 Workmanship:

1.11.1 Workmanship provided by Contractor employees shall be consistent with the highest standards of commercial marine practices and regulatory bodies.

The Government reserves the right to accept or reject material and workmanship nonconformance. Noncompliance with Contractor’s quality control processes will influence past performance rating provided on contract evaluation. Plating and structural member cuts shall be neatly and accurately made with edges cleaned and prepared for welding. Sharp edges shall be ground smooth to avoid injury to personnel. Equipment shall be protected against weather hazards.

1.11.2 At the time of delivery, work performed shall meet the performance requirements specified. In the event that deficiencies are discovered during the Guarantee period, an opportunity will be afforded the Contractor to witness, inspect and comment on such deficiencies. Materials and articles used for work performed shall be of commercial marine quality, conforming to the requirements of the Regulatory Bodies listed herein, unless specified to be otherwise.

1.11.3 The decision that an area is inaccessible shall be determined by inspection and agreed to by the COR prior to proceeding with the requirements of this SOW.

1.12 Corrective Action Request (CAR): The Contractor is solely responsible for implementation of the Inspection and Quality Control System of 1.5.9.

Government observer(s) will monitor production work performed at any time where work is ongoing. If, during the performance of work, the Government observer(s) witness work that: fails to meet specifications within this SOW, would lead to an unsatisfactory end product, damages Government Property, is a Safety Violation; the observer will alert the COR. Conditions that fail to meet specifications within this SOW may result in the Contractor being issued a CAR.

Contractor shall respond in writing within 2 work days of CAR receipt to the COR concerning the corrective action taken to remedy the issue and prevent future occurrences.

1.13 Condition Found / Inspection Discrepancy Report (CFR/IDR): Utilize FIGURE A (or Company correspondence containing same information) in transferrable media, to communicate to the Contracting Officer and COR concerning all conditions found, discrepancies noted, and other information requiring formal documentation. Provide the Contractor’s recommendation for corrective action and include Contractor’s estimated pricing (man-hours and materials) to correct the condition found. Provide all inspection results including detailed measurements, photographs, sketches, and other means to accurately detail inspection results using FIGURE A, with attachments as necessary. The Government will review and respond to the submitted report. Additional repairs related to the found condition will be tasked if determined necessary by the Government. In the event difficulty is encountered in meeting requirements or difficulty is anticipated in complying with the contract schedule dates, immediately notify the Contracting Officer via verbal communication with the COR. Government receipt of notifications are not to be construed as a waiver of the requirements, delivery schedule, or waiver of rights or remedies provided by law or under this contract, or any other requirements in the SOW relating to jeopardy of contract schedule dates. Reports and notifications do not authorize the Contractor to perform additional work not covered by the contract or authorized by the Contracting Officer. (CDRL A006)

FIGURE A - CONDITION FOUND/INSPECTION DISCREPANCY REPORT

CFR Number________ Date: ______________

From:________________________________ (Contractor Authorized Representative) To: PSNS & IMF, NWRMC IND MAN, C400, Contracting Officer Via: PSNS & IMF, NWRMC IND MAN, C400, Contracting Officer’s Representative

(COR)

Vessel: Edgecumbe Barge 2021

Section of Contract Affected: _____________________________________________

Description:

Impact:

Recommended Action:

C400 Response:

Signature of C400 Representative Date

Page _1__ of ____

1.14 Interferences: Contractor pricing offered shall include removal and re-installation of all interferences associated with performance of the required work.

The fact that interference is not shown on a plan or specifically identified in the specification item is not justification for a contract change. A physical check of each work site prior to bid submittal is strongly encouraged.

1.15 Safety Requirements:

1.15.1 Comply with the requirements of 29 CFR 1915, 29 CFR 1910, and 29 CFR 1926, state and local laws, rules, and ordinances during contract performance.

1.15.2 Contractor shall be responsible for the compliance of the above requirements by all subcontractor personnel performing work related to this contract. In cases of conflict between the above regulations, the stricter of the requirements shall take precedence.

1.15.3 Immediately report injuries to Contractor and subcontractor employees to the COR. Investigation shall be completed within 7 work days of each accident/injury. Document a report that includes narratives of the circumstances leading up to and including the injury and any actions (immediate and contemplated) taken to mitigate future reoccurrences of injuries.

(CDRL A007)

1.15.4 Scaffolds and ladders shall meet the requirements of 29 CFR

1910.27 and 29 CFR 1910.28.

1.15.4.1 Install a swinging gate guardrail at each scaffold ladder and through-platform access opening.

1.15.4.2 Install standard railing around the non-access sides and a swinging gate guardrail on the entrance side of through-platform access openings.

1.15.4.3 Install standard toe-boards around all scaffold floor openings, except at the entrance to the swinging gate guardrail, on all exposed sides of through-platform access openings.

1.15.4.4 Develop detailed engineered drawings and specifications for scaffolds when OSHA, ANSI, or manufacturers’ designed guidelines do not exist, such as for “hanging scaffolding”. Drawings and specifications shall be designed by a registered professional engineer and meet the following:

1.15.4.4.1 Maintain on the jobsite a copy of the detailed

engineering drawings and specifications showing the sizes and spacing of members and the calculations developed for the engineered design(s).

1.15.4.4.2 Construct, load, and maintain scaffolding in

accordance with the registered professional engineer’s design.

1.15.4.5 Install a commercially available scaffold tag system on all scaffolds. The tagging system, as a minimum, shall be prominently attached to the scaffold structure, consist of green colored “Okay to Use” tag(s), red colored “Danger” tag(s), and accomplish the following:

1.15.4.5.1 Apply all tags on the scaffold structure as close

as practicable to each ladder access and/or entry point;

1.15.4.5.2 Apply a red tag to indicate to users that the

scaffold is being dismantled, is not yet completely erected, or for some reason is unsafe for use;

1.15.4.5.3 Apply a green tag to indicate to users that the

scaffold is safe for use and is compliant with all OSHA regulations and other applicable requirements;

1.15.4.5.4 Ensure green tags contain the following

information as a minimum: the location of the scaffolding structure; a unique reference number to identify each separate scaffolding structure, the date the scaffolding structure was first erected; the name(s) of the scaffold builder(s); the load rating of the scaffold structure; and the Competent Person’s printed name and signature.

1.16 Hot Work/Welding:

1.16.1 Prior to performance of any hot work on the vessel, certify a safe atmosphere exists in and around the work area before starting any work that may produce the heat of ignition, sparks or flame. Accomplish steps to make each area safe for hot work. A copy of the gas free certification shall be posted at the work site for the entire period that personnel entry into and around the work area is required.

1.16.2 Each Welder shall be AWS certified.

1.16.3 Weld filler materials, plating materials, weld designs, weld repairs, and equipment shall be in accordance with ABS Rules for Materials and Welding 2020 Part 2.

1.16.4 100 percent Visually Inspect (VT) accomplish each new weld in accordance with ABS requirements. Defects shall be repaired in accordance with ABS requirements.

1.16.5 Remove existing preservation coatings prior to each expected welding, cutting, and hotwork operation.

1.16.5.1 Preservation / coatings shall be removed 4 inches in each direction and each opposite side.

1.16.6 Welding shall be sequenced to keep the thermal expansion of structures to a minimum.

1.16.7 Minimum preheat accomplish 100 percent of each weld joint to 70 degrees Fahrenheit prior to each weld application.

1.17 Hull Access Cuts :

1.17.1 Prior to performing hull access cuts, develop plan and elevation view drawings specifying the location of each access by deck, frame, and distance from the center line or deck edge including measurement and location of adjacent penetrations, bulkheads, framing, and welds within 12-inches of each proposed cut. (CDRL A008)

1.17.2 Documentation maintain each proposed access cut to include: a list of each proposed hull access cut, match marked original location, hull access cut log, and one legible drawing or sketch of each proposed access cut.

(CDRL A008)

1.17.2.1 Identify the location and number of previous cuts visible in each plate.

1.17.2.2 Identify structural reinforcement required to prevent distortion of the vessels structure.

1.17.2.3 Identify the thickness and type of material of plating and structural members to be cut. Identify the source or document/drawing number identifying the material requirements.

1.17.2.4 Identify by positive methods any structural member, interference, and compartment boundary(s) on the opposite side of the proposed access cut.

1.17.2.5 Document weld procedure or identify the Government

approved weld procedure number on/with the drawing or sketch, weld joint design, drawing number and title, and each technical document.

1.17.3 Match mark identify accomplish each hull access opening prior to removal.

1.17.4 Hull access cuts shall be circular and limited to a maximum of 15 inches or a maximum oval of 24 inches long by 15 inches wide with a minimum radius of 6 inches with a minimum of 3 inches from the toe of the access cut weld to the toe of any bulkhead, frame or longitudinal weld.

1.17.5 Hull access cuts shall be limited to the bottom hull of the barge. A maximum of two openings may be located in each tank that covers the full width of the barge. A maximum of one opening may be located in each tank that does not cover the full width of the barge.

1.17.6 Hull access cuts shall be at least 12 inches from existing welds or adjoining structure and centered between longitudinal stiffeners, with the longer dimension running forward and aft.

1.17.7 Double Bevel weld design and weld accomplish each Hull insert.

100 percent back gouge remove each root pass.

1.17.8 Peen accomplish 100 percent of each intermediate weld layer using power-driven equipment with round or blunt nosed tool or circular or oblong cross section. Surface slag, slag inclusions, cracks, gas holes, porosity, rust, scale, excessive roughness, weld bead overlap, reentrant bead contour and other weld defects shall be removed prior to peening to prevent embedding any foreign material or unfused areas in weld. Light grind or burr the peened surface sufficient to remove visual indication of flaking or laps on the finish contour prior to inspection. Minimum weld crown must be achieved after grinding.

1.17.8.1 Root and final passes shall not be peened.

1.17.9 Ultrasonic Test (UT) accomplish and document 25 percent of each new access cut weld. UT acceptance criteria shall be in accordance with ABS Nondestructive Inspection of Hull Welds, class B inspection. (CDRL A009)

1.18 Threaded Fasteners:

1.18.1 Except as otherwise specified herein, or on the drawings listed, threaded fasteners shall be in accordance with applicable ASTM standards.

Coarse thread series shall be used unless the component’s design indicates a necessity to use fine thread series. Opening diameter for each mounting bolt shall not exceed the diameter produced using standard size drill bits. Black oxide coated brass and cadmium plated fasteners are prohibited. Consult the requirements of MIL-STD-777 and Naval Ships’ Technical Manual (NSTM) Chapter 075 for guidance in instances where there is a question as to the material to be utilized.

1.18.2 Threads on externally threaded fasteners, after being installed and tightened, shall protrude a minimum of 2 threads to a maximum of 5 threads beyond the face of the nut with the exception of minimum thread protrusion for self-locking (plastic insert) nut installations. For those installations, bolt or stud end minimum thread protrusion shall be flush with the face of the nut. For self-locking nuts, the bolt or stud end shall protrude a maximum of 5 threads beyond the face of the nut after the nut is tightened.

1.18.3 Clean, chase, and tap exposed threaded areas of each fastener and threaded socket.

1.18.4 Tighten threaded fasteners in the sequence, patterns, and the torque values, when not otherwise specified, using the requirements of Section 4, paragraph 075-4.1 through 075-4.6.2 of NSTM Chapter 075 for guidance.

1.19 PRESERVATION:

1.19.1 Measure, record, and maintain Objective Quality Evidence (OQE) information on Appendices One through 8 throughout the entire performance of preservation operations. OQE information for the in-process being performed must be made immediately available for onsite review upon request by the COR or ABS Surveyor. (CDRL A010)

1.19.1.1 Appendices one through 8 shall be in accordance with Reference QA_Appendix_Forms_Forms_C411_2018_Contractors.pdf

1.19.1.1.1 All spaces that are not applicable shall be

marked N/A.

1.19.1.1.2 Unused sections shall be crossed out and

marked N/A.

1.19.1.1.3 Any errors shall be one lined thru; initialed

and dated by the person making the correction.

1.19.1.1.4 Any markings that are illegible or unclear shall

be considered invalid.

1.19.2 Comply with the coating manufacturer’s product data sheets requirements for the establishment and maintenance of environmental conditions and for coating thickness applications throughout the entire removal and preservation operation(s).

1.19.2.1 Calibrated Electronic Data Logger record and maintain environmental conditions OQE during the entire preservation operations. Data shall be made immediately available for onsite review upon request by the ABS Surveyor and COR. (CDRL 010)

1.19.3 Apply contrasting colors between the primer, stripe, intermediate, and topcoat using coating products that are from the same manufacturer; that are compatible with each other; that are a different color from both the preservation over which it is being applied and the next coat in the system; and in accordance with the manufacturer’s product data sheets.

1.19.4 Apply stripe coat to all edges, weld seams, welds of attachments and appendages, cutouts, corners, butts, foot/handholds, including back side of piping, underside of beams and other mounting hardware (non-flat surface) after each previous full coat has dried. The stripe coat shall encompass and extend a minimum of One-inch beyond the intersection of two flat surface planes, each radii edge, and all perpendicular shapes, edges, or angles.

1.19.5 Mask and/or install temporary expandable foreign material exclusion (FME) plugs, blanks, or other hard and durable protective covers, painted blaze orange, in hull openings and surfaces to prevent system contamination or equipment damage from abrasive blasting, surface preparation, and preservation operations. The use of cloth, polyvinyl sheet, paper, tape, rubber sheeting, and wood or wood products as FME prevention devices is prohibited.

1.19.5.1 Establish an FME log, record, and identify the location of each protective covering installed and removed, including each corresponding and specific measurement(s), location(s), and/or area(s) in relationship to structural members or from suitable hull reference points.

1.19.5.2 Remove each temporary FME plug, blank, and protective covering, record removal date in FME log, and restore each system to its original configuration upon final completion of testing, blasting, and preservation operations.

1.19.6 Solvent clean surface prior to the start of each blasting, and preservation operation. Accomplish the requirements of Surface Preparation Specification SSPC-SP-1 of Systems and Specifications, SSPC Painting Manual, Volume 2.

1.19.7 Accomplish touch-up preservation for new and disturbed surfaces shall match surrounding coating system(s) in accordance with the manufacturer’s product data sheets.

1.19.8 Feather edges of well adhered paint remaining after cleaning for all surface preparation methods. Visible areas of defective existing paint shall be removed until an area of completely intact and adhering paint is attained around the defective area by feathering (tapering) the edges of tightly adhering existing paint at an approximate 30 degree slope into the newly prepared bare metal surface thus preventing application of new paint over loose or cracked paint.

1.19.9 Paints shall not be thinned.

1.19.10 Hull and freeboard preservation coatings shall be fully cured prior to undocking. All other preservation coatings shall be fully cured in accordance with the manufacturer’s product data sheets prior to final delivery to the Government.

1.19.10.1 Preservation coatings are considered fully cured when they meet the requirements of the applicable manufacturer’s product data sheets minimum cure to service time schedule and are dry throughout their thicknesses.

1.19.11 Conduct Surface Chloride or Surface Conductivity measurements.

1.19.11.1 Surface Chloride; shall not exceed 3 ug/cm2 (30 mg/m2) for immersed or 5 ug/cm2 (50 mg/m2) non-immersed applications. Surface Conductivity; shall not exceed 30 Micro-Siemens/cm immersed or 70 Micro- Siemens/cm non-immersed applications.

1.19.11.2 Readings shall be documented on Appendix 4.

1.20 Environmental and Hazardous Waste Management:

1.20.1 Comply with all federal, state, and local laws, codes, regulations, acts, ordinances, and rules for Environmental Protection and Hazardous Waste Management / Disposal, including obtaining required licenses, generator identification number, and permits. Designate one employee responsible for Environmental and Hazardous Waste Management. All contract, manifests, invoices, and other documents related to the removal, storage, handling, transportation or disposal of hazardous waste shall bear a generator identification number issued to the Contractor pursuant to applicable law. Take actions to mitigate creation of hazardous waste by recycling and other available methods.

All hazardous waste generated by work under this contract is anticipated to be Contractor generated and shall be the responsibility of the Contractor. Estimated hazardous waste associated with work required in these Specifications is listed below:

Product Amount Cleaning Solvents 100 gallons Paint (enamel, latex, epoxy, thinners, oil based, rubber, non-skid, lacquer, varnishes, removers) 100 gallons

Rags (contaminated with a known source) 50 pounds Blast Media and paint chips contaminated with heavy metals and other contaminants 1,500 pounds Tank Liquids 100 Gallons Tank Solids 200 Pounds

Hazardous waste generated during the actual performance of the work may vary in type or amount from the waste listed above. The above is an estimate of the amount of waste anticipated to be generated; not an estimate of the amount of work in generating that waste. (CDRL A011)

1.20.2 The Contractor shall ensure that their cost proposal for the work proposed herein includes reasonable compensation for all anticipated cost of managing and disposing of the wastes listed above, and/or created or generated in the execution of the delivery order issued, in accordance with the requirements of 42 USC 6901-6992 Rev 1996, 49 USC 5103, 10 USC 7311 Rev 1/22/11. The Contractor shall include a 5-way break down of the anticipated costs associated with this effort in their offer.

1.20.3 Consider coatings to contain heavy metals (e.g. lead, chromium, cadmium), hexavalent chromium, crystalline silica, and/or other toxic or hazardous substances until laboratory analysis establishes otherwise. Comply with all procedures and precautions required for employee protection, sampling, removal, and disposal.

1.21 Materials: All Contractor furnished materials (CFM) installed shall be new and documented. Materials shall be as indicated on the listed drawings, publications or as specified in this Specification. The use of asbestos, polychlorinated biphenyl (PCB), magnesium, cadmium, or mercury in any materials is prohibited.

1.21.1 All material documentation shall be reviewed and accepted by the ABS surveyor prior to installation of materials. Material documentation shall be available for immediate review upon request by the Government or ABS Surveyor.

1.22 Gas Free:

1.22.1 Provide certified Marine Chemist, Certified Industrial Hygienist services, and Shipyard Competent Person services as required by 29 CFR 1915 for Contractor and Government Personnel.

1.22.2 Consolidate and maintain the Contractor’s current confined space entry/gas free certification processes into a single and comprehensive document as part of a confined space/gas free certification program. (CDRL A012)

1.22.3 Maintain a list of Contractor’s National Fire Protection Association (NFPA) Marine Chemist certifying gas-free conditions for this project and a list identifying Contractor employees designated as “Competent Persons” in accordance with 29 CFR 1915.7.

1.22.4 Post, update, and maintain gas free certificates IAW 29 CFR 1915 during the entire contract period of performance.

2.0 REFERENCES: All references shall be of the latest issue and/or revision or as indicated in the Consolidated List of References. It is incumbent on the Contractor to maintain current commercial specifications and be thoroughly familiar with Federal, State and Local laws, regulations and ordinances.

Contractor is prohibited from using Government provided technical information for any purpose other than that contemplated by the specifications. Contractor is prohibited from further use, release, or disclosure of this information.

References provided on CD-ROM, including any information contained thereon, must be destroyed in accordance with the instructions included on the CD-ROM label, at completion of the contract. After award, for those Contractors in receipt of a CD-ROM and not awarded a delivery order, the CD-ROM including any information contained thereon, shall be destroyed in accordance with the instructions included on the CD-ROM label.

2.1 Order of Precedence: Unless otherwise noted within this specification, hierarchy, priority, or order of precedence of requirements shall be as follows:

2.1.1 Specification Definite Item

2.1.2 Specification General Requirement

2.1.3 Military/Navy Drawings

2.1.4 Military/Navy Technical Manuals

2.1.5 Commercial Drawings

2.1.6 Commercial Technical Manuals

2.1.7 Commercial or Industrial Standards

2.1.8 Commercial Practices

2.2 Discrepancies: Drawing, technical reference, or other discrepancies associated with this specification shall be reported using the Request for Specification Clarification form, during proposal, or the “Condition Found / Inspection Discrepancy Report” form (FIGURE A) during delivery order period of performance.

CONSOLIDATED LIST OF REFERENCES

The following publication and drawing requirements are applicable to this SOW:

Publication Number Title

1) 29 CFR 1910 Occupational Safety and Health Standards

2) 10 USC 7311 Repair or Maintenance of Naval Vessels:

Handling of Hazardous Waste

3) 29 CFR 1915 Occupational Safety and Health for Shipyard Employment

4) 29 CFR 1926 Safety and Health Regulations for Construction

5) 42 USC 6901 to 6992 Resource Conservation and Recovery Act of

6) 49 USC 5103 Hazardous Materials Transportation Authorization Act of

8) NSTM Chapter 997 Docking Instructions and Routine Work in Dry Dock

9) SSPC Painting Manual, Volume 1 Good Painting Practice

10) SSPC Painting Manual, Volume 2 Systems and

Specifications

11) QA_Appendix_Forms_Forms_C411_2018_Contractors.pdf QA Appendices

Drawing Number Title

1) 100-5283618-A Edgecumbe Barge Structural Modifications

Mid Body

2) 100-5283619-A Edgecumbe Barge Removals &

Modifications Bow & Stern

3) 100-7281566-D Barge Paint Schedule

4) 114-5322269-B Edgecumbe WT Bulkheads Required For Stability

Drawing Number Title

1) 100-5283618-A Edgecumbe Barge Structural Modifications

Mid Body

2) 100-5283619-A Edgecumbe Barge Removals &

Modifications Bow & Stern

5) 145-6773239 Edgecumbe Barge Compartmentation

Arrangement

6) 803-921865 Rev R Cathodic Protection Hull Zinc Anodes

7) 845-7281575 Edgecumbe Barge Docking Drawing

8) S2803-980209 Rev L Bureau of Ships, Label Plates

9) S2804-921819C Distinguishing Figures

3.0 WORK REQUIREMENTS:

3.1 DOCKING AND UNDOCKING THE VESSEL:

3.1.1 Personnel and equipment: Furnish qualified and experienced personnel, facilities, and the necessary equipment to safely dock and undock the vessel, including:

3.1.1.1 A Dock Master currently qualified and certified by the Contractor and accepted by the GDO.

3.1.1.2 Supporting employees to accomplish the docking and

undocking evolutions.

3.1.1.3 Tugs, pilots, and divers required for the complete transfer, docking, and undocking of each vessel. At the docking conference, the GDO shall review and approve the number and size of the tugs to be used.

3.1.2 Docking Procedure: Develop a docking procedure prior to dry docking, which shall include the following: (CDRL A013)

3.1.2.1 Operating practices.

3.1.2.2 Safety and security plans.

3.1.2.3 Special precautions or actions required by the characteristics of the dock, marine railway, or other docking methods.

3.1.2.4 Pumping/flooding schedule.

3.1.2.5 Specific list, trim and stability requirements.

3.1.3 Blocking Plan: Develop a blocking plan to set and align the docking blocks in accordance with the requirements of NSTM Chapter 997, using drawing 845-7281575 for guidance.

3.1.3.1 Develop a docking plan in the form of a scaled drawing including: block size, block spacing, and location of vessel with respect to the blocks at landing. Position blocking to ensure that equipment on the surface of or protruding from the hull shall not be damaged.

3.1.3.2 Determine the docking clearances utilizing references for guidance and the following requirements: The minimum clearance between the side of the vessel (including fixed projections) and the permanent dock structure (such as wing walls, crane rails, piers, etc.) shall be 12 inches during vessel movement into or out of dock and allow for safe work practices accomplished inside the dock. Minimum vertical clearance between the keel of the vessel and the dock floor shall allow for safe accomplishment of work and provide sufficient access for all inspections. Hull openings shall not be obstructed.

3.1.3.2.1 Minimum vertical clearance between the keel of

the vessel and the dock floor shall be 42 inches.

3.1.3.3 The blocking plan shall be accompanied by a written request for approval to the GDO a minimum of 5 working days prior to the scheduled docking date. The use of haul, fixed, or fitted blocks shall be clearly stated.

3.1.3.4 The use of universal docking blocks is prohibited.

3.1.3.5 Maintain supporting data substantiating that:

3.1.3.5.1 The block loading pressures are limited to a

maximum of 4 long tons per square foot.

3.1.3.5.2 The number, distance from centerline, and square footage of the side blocks per side is sufficient to resist overturning moments.

3.1.3.5.3 100 percent of blocks land on longitudinal strength members or main transverse bulkheads.

3.1.3.6 Blocking shall be constructed of hardwood or composite hardwood/concrete and soft caps, with at least 2 inches of soft cap thickness.

3.1.3.6.1 The term “hardwood”, for the purposes of this

contract, includes White Oak, California laurel, Oregon myrtle, Iron Wood, Blue Gum, American Rock Elm, or preserved Red Oak. The normal lifespan for hardwood blocking is approximately 10 years.

3.1.3.6.2 Woods acceptable for use as soft caps are Douglas

fir, Tamarack, Long Leaf Pine, or Hemlock.

3.1.3.6.3 Composite blocking showing evidence of spalling

and cracks or chipped and damaged concrete is not acceptable.

3.1.3.7 Blocking showing evidence of excessive crushing, warping, cracking, checking, rotting, or damage from dogging, loss of contact at edges caused by cracking or unequal shrinkage or deterioration to an extent no longer being capable of supporting a prescribed load over full bearing areas is not acceptable and shall be replaced.

3.1.4 Crib and Brace Blocking: Ensure that crib and brace blocking are in accordance with the requirements of NSTM Chapter 997, using the drawing applicable to the docking facility.

3.1.4.1 The aspect ratio for un-cribbed keel blocks shall not exceed

2.0 where the aspect ratio is defined as the height divided by the horizontal dimension for the longitudinal and transverse direction, each checked separately.

3.1.4.2 Side blocks with a longitudinal dimension less than 24 inches shall be longitudinally braced or cribbed when their height as measured from the base to the highest corner of the soft cap exceeds 3 times the longitudinal dimension.

3.1.5 Setting and Alignment of Docking Blocks: Furnish, set, record, and align the blocks in accordance with the Government approved Contractor blocking plan and in accordance with the requirements of NSTM Chapter 997.

Prepare dry dock for inspection at least one work day prior to the proposed docking. Notify and accomplish an inspection of the blocking with the GDO in a timeframe sufficient to make blocking changes. Develop documentation of the inspection showing blocking, sighting marks on dock coping relative to block locations, spacing, offsets, heights, and shaping to the GDO at least 4 hours prior to flooding the dry dock. Immediately prior to flooding the dry dock, perform a final inspection with the GDO to ensure that no loose trash, wood, equipment, and other extraneous matter could float up during flooding and interfere with/delay the docking operation.

3.1.7 Docking Conference: Perform a docking conference attended by the GDO, ABS Surveyor, COR, the Contractor’s Dock Master, the pilot who will be present during the docking evolution, and required dive personnel, within 4 working days prior to the scheduled docking of the vessel. The Dock Master shall discuss the time of docking, tide situation, weather conditions, tug and pilot arrangements, line handling, electrical shore power, grounding, safety issues, safety concerns, other services and procedures.

3.1.8 Docking the Vessel: Dry dock the vessel without strain. Immediately after docking, electrically connect the vessel hull at the bow and stern of vessel for protection against lightning and other static charges in accordance with the requirements of NSTM Chapter 074 Volume One, and NSTM Chapter 997.

3.1.8.1 Notify the GDO a minimum of 2 work days prior to actual docking and undocking of vessel.

3.1.8.1.1 Contact the COR for current GDO contact

information.

3.1.8.2 Dry dock facilities shall have an alternate / back up electrical power generating and distributing source to furnish all electrical requirements for docking and undocking of vessel, in the event of a loss of main power source.

3.1.9 Post Docking: Prepare and inspect vessel underwater hull surfaces.

3.1.9.1 Immediately after docking, perform a visual inspection of the underwater portions of the vessel with the GDO for damage and deterioration.

Inspect the fit on the blocks and furnish necessary shimming between the blocking and the hull to prevent hull movement and to ensure 100 percent block contact with the hull structure.

3.1.9.2 Within 8 hours of docking, wash the underwater hull and fittings with fresh water at a minimum of 3,000 PSIG nozzle pressure to remove dirt, slime, marine growth, fouling and other foreign substances.

3.1.9.3 Comply with federal, state, and local laws and ordinances for disposal of wash water and debris removed from underwater portions of the vessel.

3.1.10 Shifting the Vessel: Relocate the vessel on the dry dock blocks to permit 100 percent preservation painting and weld repair of areas initially covered by the dry dock blocks. Minimum clearance shall be 12 inches for bringing the vessel into or out of dock and performing any work inside the dock.

Relocation of the vessel shall occur after the proper cure time has elapsed after application of the final coat of hull preservation.

3.1.11 Undocking the Vessel: After completion of work, undock the vessel at a time and date agreed upon by the GDO and the Contractor. Perform an undocking conference similar to the Docking Conference of 3.1.7 within 3 days of undocking. Immediately prior to flooding the dry dock, perform an inspection with the GDO to ensure that no loose trash, wood, equipment, and other extraneous matter could float up during flooding and interfere with/delay the undocking operation.

3.1.11.1 Immediately after the hull penetrations are submerged and before the vessel lifts off the blocks-- stop flooding the dry dock. Accomplish a watertight integrity check of the hull with the COR. Continue flooding of the dock when directed by the GDO.

3.1.11.2 After the vessel has cleared the blocks, perform a visual inspection of the underwater hull surfaces to ensure that no soft caps are adhered to the hull surfaces. Perform a visual inspection of the docking blocks to account for all soft caps and to ensure that no blocks are adhered to the underwater hull structure of the vessel.

3.1.11 Docking Observer: The Docking Observer is the Government official certified by the Government as qualified to execute the duties of a Docking Observer. The presence of the Docking Observer is for protecting the Navy’s interests, not to give direction to the Contractor. However, the Docking Observer shall have the authority to stop the docking, undocking or launching evolution when the vessel safety or other Navy interests are jeopardized. This authority does not imply limitations on or responsibility for the actions of the Contractor’s Dock Master.

3.1.12 Final Docking Report: Develop a final docking report (NAVSEA 9997/1 through 9997/5) upon completion of undocking. Electronic versions of the final docking report, in portable document format (PDF) and MSWord format are available from the GDO upon request. (CDRL A014)

3.2 HULL REPAIRS:

3.2.1 Identify Distinguishing Figures and Markings: Identify and record existing distinguishing underwater body, hull, and freeboard color schemes, markings, and figures in sketch form listing colors, locations, sizes, and distinguishing marking(s), and figure(s) information, using drawing S2804- 921819 Rev C for guidance.

3.2.2 Rubber Fenders: Existing rubber fender materials shall not be removed. Blast and paint protection accomplish existing rubber fender materials.

3.2.2.1 Hand tool clean accomplish the requirements of Surface Preparation Specification SSPC-SP-2 of Systems and Specifications, SSPC Painting Manual Volume 2, 100 percent of hull surfaces from edge of existing rubber fender material to 2 inches outward.

3.2.3 Zinc Anodes: Remove existing Quantity (107 EA) and store. Install existing zinc anodes and new fasteners using drawing 100-7281566 Rev D for guidance after hull preservation is completed and fully cured in accordance with the manufacturer’s product data sheet.

3.2.3.1 Electrical resistance test accomplish each zinc anode installed after completion of 3.2.3 in accordance with General Note 4 of drawing 803-921865 Rev R.

3.2.3.2 Template exact sizes, locations,…