This is an Independent Government Cost Estimate (IGCE) for a roof replacement project at Alchesay National Fish Hatchery in Navajo County, Arizona. The solicitation (No. 140FC225Q0043) involves replacing the roof for Residence #6 and its garage, with detailed line items for demolition, disposal, and installation of new roofing materials. The project includes removing existing single-layer shingle roofs, installing new underlayment, ice barriers, drip edges, flashing, shingles, and a gutter system. A bid option for roof decking replacement (384 sq ft) is also included, with estimated costs for mobilization, overhead, insurance, and performance bonds. The total base price includes direct costs, indirect costs, and a profit margin, with the project being managed by the Department of the Interior Fish and Wildlife Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IGCE

Alchesay National Fish Hatchery2025 Residence #6 & Garage Roof Replacement
Navajo County, AZ
CONFIDENTIAL GOV. ESTIMATE
ITEM NO.Direct Cost Bid Item DescriptionUNITUNIT PRICEUnitEst QTYUnit PriceAMOUNT
[0001]Residence #6 -Demolition Existing Shingle Roof (1 Layer)1Job$ 2,000.00
[0002]Residence #6 - Disposal
[0003]Residence #6 - Installation New Underlayment, Ice Barrier, Drip Edges, Flashing, Shingles, Fascia72Hrs$ 50.00
[0004]Garage - Demolition Existing Shingle Roof (1 Layer)1Job$ 2,000.00
[0005]Garage Disposal
[0006]Garage - Installation New Underlayment, Ice Barrier, Drip Edges, Flashing, Shingles, Gutter System72Hrs$ 50.00
[0007]Bid Option #1 - Roof Decking Replacement (384 sf)32Hrs$ 50.00
1Job$ 4,000.00
Direct Cost SUBTOTAL
Indirect Cost Item Description
MMobilization & Demobilization
OOverhead Cost
IInsurance, Payment & Performance bonds
Indirect Cost SUBTOTAL
PProfit
Total Base Award Price
Alternate/ADDITIVE including O/H & profit
2Ea$ 1,500.00
TBTotal Base Price & Added Alternative