This is an Independent Government Cost Estimate (IGCE) for a roof replacement project at Alchesay National Fish Hatchery in Navajo County, Arizona. The solicitation (No. 140FC225Q0043) involves replacing the roof for Residence #6 and its garage, with detailed line items for demolition, disposal, and installation of new roofing materials. The project includes removing existing single-layer shingle roofs, installing new underlayment, ice barriers, drip edges, flashing, shingles, and a gutter system. A bid option for roof decking replacement (384 sq ft) is also included, with estimated costs for mobilization, overhead, insurance, and performance bonds. The total base price includes direct costs, indirect costs, and a profit margin, with the project being managed by the Department of the Interior Fish and Wildlife Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A04_SOW_Alchesay_Residence__6_Roof_Replacement.docx | DOCX document | |
| Gen__Wage_Decision_No_AZ20250004_01_03_25.pdf | ||
| Gen__Wage_Decision_No_AZ20250005_01_03_25.pdf | ||
| Sol_140FC225Q0043.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IGCE
| Alchesay National Fish Hatchery | 2025 Residence #6 & Garage Roof Replacement |
| Navajo County, AZ |
| CONFIDENTIAL GOV. ESTIMATE | ||||||||
| ITEM NO. | Direct Cost Bid Item Description | UNIT | UNIT PRICE | Unit | Est QTY | Unit Price | AMOUNT | |
| [0001] | Residence #6 -Demolition Existing Shingle Roof (1 Layer) | 1 | Job | $ 2,000.00 | ||||
| [0002] | Residence #6 - Disposal | |||||||
| [0003] | Residence #6 - Installation New Underlayment, Ice Barrier, Drip Edges, Flashing, Shingles, Fascia | 72 | Hrs | $ 50.00 | ||||
| [0004] | Garage - Demolition Existing Shingle Roof (1 Layer) | 1 | Job | $ 2,000.00 | ||||
| [0005] | Garage Disposal | |||||||
| [0006] | Garage - Installation New Underlayment, Ice Barrier, Drip Edges, Flashing, Shingles, Gutter System | 72 | Hrs | $ 50.00 | ||||
| [0007] | Bid Option #1 - Roof Decking Replacement (384 sf) | 32 | Hrs | $ 50.00 | ||||
| 1 | Job | $ 4,000.00 | ||||||
| Direct Cost SUBTOTAL |
| Indirect Cost Item Description | |
| M | Mobilization & Demobilization |
| O | Overhead Cost |
| I | Insurance, Payment & Performance bonds |
| Indirect Cost SUBTOTAL |
| P | Profit |
| Total Base Award Price |
| Alternate/ADDITIVE including O/H & profit | ||||
| 2 | Ea | $ 1,500.00 | ||
| TB | Total Base Price & Added Alternative |