Statement of Work Summary: BRD Nederland Garage Door Replacement

This is a Statement of Work (SOW) issued by the U.S. Department of Agriculture Forest Service for the replacement of four industrial 10'x10' rollup overhead garage doors at the Boulder Ranger District's Nederland Work Center in Nederland, Colorado. The contractor shall remove the original doors (assumed to be from the 1997 building construction) and install new garage doors, motors, and associated components in accordance with manufacturer specifications and State and Federal laws. The contractor is responsible for furnishing all labor, equipment, materials, supervision, transportation, and incidentals necessary to complete the work, and must provide a 5-year warranty on parts, materials, supplies, and labor.

Work must be completed within 30 days of start date, with all activities occurring between 0800-1700 hours Monday through Friday, excluding weekends and Federal holidays. The contractor must submit multiple deliverables prior to construction, including a schedule (14 days before start), safety plan (14 days before start), material submittals (14 days before start), installer certifications (August 17, 2026), accident prevention plan (7 days before start), operation and maintenance manuals (before final payment), and warranties (before final payment). The contractor must coordinate with the Contracting Officer's Representative (COR) for daily site access at 534 Ridge Road, Nederland, CO 80466, and shall not be permitted to stay overnight on site. Personnel must be experienced in servicing and replacing industrial garage door components and must meet all State of Colorado and Federal licensing requirements. Technical specifications reference three CSI divisions: 08331 (Overhead Door), 08710 (Hardware), and 09900 (Painting), with building plans and photographs of existing doors provided as attachments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Statement of Work

Contents Project General Information

1.0 Scope of Work

2.0 Background

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights ........................................................................................................ Error! Bookmark not defined.

10.0 Section 508 – Electronic and Information Technology Standards .......................... Error! Bookmark not defined.

Attachment

Project BRD Nederland Garage Door Replacement

General Information

1.0 Scope of Work

The Boulder Ranger District needs replacement of four (4) industrial, 10’x10’ rollup, overhead garage doors.

2.0 Background

The Nederland Work Center Engine Bay is located in Nederland, CO. initially the doors were to just be serviced, springs repaired/replaced and motors replaced. Upon further discussion with industry, it was decided to be in better interest to replace the four (4) original doors, motors and associated components. The garage doors and openers are assumed to be original. The building was constructed in 1997.

3.0 Contractor Responsibility

The Contractor shall furnish all management, labor, equipment, supervision, tools, materials, transportation, operating supplies, supervision, workman’s compensation, unemployment insurance and incidentals necessary to perform the work in accordance with the specification and provisions of the contract.

The contractor shall remove and install new garage doors according to State and Federal laws and regulations. Extreme care shall be taken by the contractor to ensure that not damage is done to the building, structure, and site due to Contractor’s work. Any damage shall be repaired by the Contractor by a Contracting Officer approved repair plan.

All removed components, trash, debris, etc. shall be maintained to one designated area, removed from site by the contractor, and disposed of in a State approved landfill or State recycling center as appropriate. All trash shall be removed from site each day.

The contractor is responsible for always maintaining safe operations. The Forest Service is not responsible for the safety of the Contractor nor any operators or assistants. The Contractor shall provide and maintain work procedures which will safeguard the public and Government personnel, as well as the Contractor’s own personnel. The Contractor shall be expected to use reasonable safety procedures and equipment while operating on National Forest lands.

Contractor must ensure that they do not interfere with U.S. Forest Service fire operations and personnel, which may occur in the work area. Contractor must coordinate with Forest Service personnel to allow for personnel, engines and equipment to come and go at any given moment.

The Contractor shall provide complete and accurate activity records throughout the duration of the contract and provide the Government with legible, readable copies of such records upon completion of a unit of work on the contract, and prior to or accompanying the invoice.

Contractor shall ensure that doors do not remain open after working hours. The building shall be secured at the end of each workday. Include this plan in the safety plan.

The Contractor shall submit product data and obtain approval from the Contracting Officer for all materials and supplies used on the project prior to use. This shall include materials, dimensions of components, profiles, finishes, installation instructions, forces/loads, motor nameplate data, etc. The contractor shall submit shop drawings for components and installation not in the product data.

The contractor shall submit a safety plan that includes company safety policy, site specific job safety items, traffic control, hazard area identification, address site access, site security, etc.

The Contractor must notify the COR upon completion of installing the doors. The COR may inspect the site up to 15 days following completion of work to verify work was performed according to contract requirements. If the contractor fails to meet the specifications, the contractor must rework the requirment. The COR must be notified of work completion prior to submitting invoice.

The Contractor shall submit Install Certifications, signed by the manufacturer certifying that the installers comply with specified requirements.

The Contractor shall submit all operation and maintenance documents for all components before final payment.

The Contractor shall provide a 5-year warranty on parts, materials, supplies, and labor.

4.0 Technical Requirements / Tasks / Specifications

The Contractor shall install all materials and components of the garage door system in accordance with manufacture's recommendation.

Technical requirements and specifications are found in the attachments. Specifications attached include:

1. 08331 – Overhead Door

2. 08710 – Hardware

3. 09900 – Painting

The original building construction plans are included as an attachment if needed to see building construction.

5.0 Government Furnished

The contractor will need to schedule a date and time to meet the COR or Government Technical Monitor for this contract. There are electrical, water, and restroom facilities on site for contractor use as it pertains to this contract.

6.0 Deliverables / Schedule

All work must occur between 0800-1700, Monday through Friday, and no work shall occur on weekends or Federal holidays. The company is responsible for completing this work within 30 days of starting the work. The Contracting Officer’s Representative will inspect the work after completion for final inspection.

Key Deliverables Item No.

Deliverable / Item Title

Description Frequency Delivery Format

Due By

1 Schedule A schedule outlines the proposed timeline, from Removal and installation of each door.

As needed

Via email to

COR

14 days before construction is intended to begin

2 Safey Plan Submit a safety plan Once Via email to

COR

14 days before construction is intended to begin

3 Material Submittals

Submit all materials and product data sheets for this contract to the COR.

As needed

Via email to

COR

14 days before construction is intended to begin

4 Installer Certifications

Submit Installer Certifications. Once Via email to CO With Solicitation

August 17, 2026

5 Accident Prevention Plan

Submit a site-specific accident prevention plan to ensure contractor and public safety

Once Via email to

COR

7 days before construction is intended to begin

6 Operation & Maintenance Manuals

Submit Operation & Maintenance Manuals.

Once Via email to

COR

Before Final Payment

7 Warranties Submit Warranties for approval. Once Via email to

COR

Before Final Payment

7.0 Travel

The project location is in the Engine Bay in the U.S. Forest Service Nederland Work Center, located at 534 Ridge Road, Nederland, CO 80466. The contractor will not be permitted to stay overnight on site.

8.0 Contractor’s Key Personnel

Contractor Representative: The contractor shall provide a contract representative for the performance of work. The name of this person and an alternate(s) who can act for the contractor when the contractor is absent should be designated in writing to the Contracting Officer.

Certification and Personnel Requirements: The contractor and employees shall be experienced in servicing, repairing, and replacing various components associated with industrial garage doors. The contractor and employees shall be proficient in following the specifications of the contract. The contractor installing the garage door under this contract must meet all State of Colorado and Federal licenses and requirements. Personnel employed by the Contractor must be briefed and trained in service and safety techniques.

9.0 Security Requirements

The contractor must coordinate with the COR, Government Technical monitor, or other designated U.S. Forest Service personnel for daily access to the project site.

Attachment

- Pictures of the existing doors.

- Specifications.

- Building plans.

08331 - 1

OVERHEAD COILING DOORS

SECTION 08331

PART 1 – GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following types of overhead coiling doors:

1. Insulated service doors.

B. Related Sections include the following:

1. Division 8 Section "Door Hardware" for lock cylinders and keying.

2. Division 9 Section "Painting" for field-applied paint finish.

1.3 DEFINITIONS

A. Operation Cycle: One complete cycle of a door begins with the door in the closed position. The door is then moved to the open position and back to the closed position.

1.4 PERFORMANCE REQUIREMENTS

A. Structural Performance: Provide overhead coiling doors capable of withstanding the effects of gravity loads and the following loads and stresses without evidencing permanent deformation of door components:

1. Wind Load: Uniform pressure (velocity pressure) of 20 lbf/sq. ft., acting inward and outward.

B. Operation-Cycle Requirements: Design overhead coiling door components and operator to operate for not less than 20,000 cycles.

C. Operation-Cycle Requirements: Design overhead coiling door components and operator to operate for not less than 20,000 cycles and for 10 cycles per day.

1. Include tamperproof cycle counter.

1.5 SUBMITTALS

A. Product Data: Include details of construction relative to materials, dimensions of individual components, profiles, and finishes. Provide roughing-in diagrams, operating instructions, and maintenance information. Include the following:

1. Setting drawings, templates, and installation instructions for built-in or embedded anchor devices.

2. Summary of forces and loads on walls and jambs.

3. Motors: Show nameplate data and ratings; characteristics; mounting arrangements; size and location of winding termination lugs, conduit entry, and grounding lug; and coatings.

08331 - 2

B. Shop Drawings: For special components and installations not dimensioned or detailed in manufacturer's data sheets.

1. Wiring Diagrams: Detail wiring for power, signal, and control systems. Differentiate between manufacturer-installed and field-installed wiring and between components provided by door manufacturer and those provided by others.

C. Samples for Initial Selection: Manufacturer's color charts showing the full range of colors available for units with factory-applied finishes.

D. Installer Certificates: Signed by manufacturer certifying that installers comply with specified requirements.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: Engage an experienced installer who is an authorized representative of the overhead coiling door manufacturer for both installation and maintenance of units required for this Project.

B. Source Limitations: Obtain overhead coiling doors through one source from a single manufacturer.

1. Obtain operators and controls from the overhead coiling door manufacturer.

C. Listing and Labeling: Provide electrically operated fixtures specified in this Section that are listed and labeled.

1. The Terms "Listed" and "Labeled": As defined in NFPA 70, Article 100.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Atlas Door Corp.; Div. of Clopay Building Products Co.

2. The Cookson Company.

3. Cornell Iron Works Inc.

4. Overhead Door Corporation.

5. Roll-Lite Door Corp.; Div. of Clopay Building Products Co.

6. Southwestern Steel Rolling Door Co.

7. Wayne-Dalton Corp.

8. Windsor Door; A United Dominion Company.

2.2 DOOR CURTAIN MATERIALS

A. Door Curtain: Fabricate overhead coiling door curtain of interlocking slats, designed to withstand wind loading indicated, in a continuous length for width of door without splices. Unless otherwise indicated, provide slats of material thickness recommended by door manufacturer for performance, size, and type of door indicated, and as follows:

1. Steel Door Curtain Slats: Structural-quality, 24 gauge cold-rolled galvanized steel sheets complying with ASTM A 653, with G90 zinc coating.

a. Provide manufacturer's standard flat-profile slats.

08331 - 3

2. Insulation: Fill slat with manufacturer's standard rigid cellular polystyrene or polyurethane-foam-type thermal insulation complying with maximum flame-spread and smoke-developed indices of 75 and 450, respectively, according to ASTM E 84. Enclose insulation completely within metal slat faces.

3. Inside Curtain Slat Face: 24 gauge galvanized steel sheet to match material of outside metal curtain slat.

B. Endlocks: Malleable-iron castings galvanized after fabrication, secured to curtain slats with galvanized rivets, or high-strength nylon. Provide locks on not less than alternate curtain slats for curtain alignment and resistance against lateral movement.

C. Windlocks: Malleable-iron castings secured to curtain slats with galvanized rivets or high-strength nylon, as required to comply with wind load.

D. Bottom Bar: Consisting of 2 angles, each not less than 1-1/2 by 1-1/2 by 1/8 inch thick, either galvanized or stainless-steel or aluminum extrusions to suit type of curtain slats.

E. Curtain Jamb Guides: Fabricate curtain jamb guides of steel angles, or channels and angles, with sufficient depth and strength to retain curtain, to allow curtain to operate smoothly, and to withstand loading. Build up units with not less than 3/16-inch-thick, galvanized steel sections complying with ASTM A 36, and ASTM A 123. Slot bolt holes for guide adjustment. Provide removable stops on guides to prevent overtravel of curtain and a continuous bar for holding windlocks.

2.3 HOODS AND ACCESSORIES

A. Hood: Galvanized steel, 24-gauge hood with intermediate supports as required. Provide internal hood baffle weatherseal.

B. Chain Lock Keeper: Suitable for padlock.

C. Provide safety interlock switch to disengage power supply when door is locked.

2.4 COUNTERBALANCING MECHANISM

A. General: Counterbalance doors by means of adjustable-tension steel helical torsion spring, mounted around a steel shaft and contained in a spring barrel connected to door curtain with required barrel rings. Use grease-sealed bearings or self-lubricating graphite bearings for rotating members.

B. Counterbalance Barrel: Fabricate spring barrel of hot-formed, structural-quality, welded or seamless carbon-steel pipe, of sufficient diameter and wall thickness to support rolled-up curtain without distortion of slats and to limit barrel deflection to not more than 0.03 in./ft. of span under full load.

C. Provide spring balance of one or more oil-tempered, heat-treated steel helical torsion springs. Size springs to counterbalance weight of curtain, with uniform adjustment accessible from outside barrel.

Provide cast-steel barrel plugs to secure ends of springs to barrel and shaft.

D. Fabricate torsion rod for counterbalance shaft of cold-rolled steel, sized to hold fixed spring ends and carry torsional load.

E. Brackets: Provide mounting brackets of manufacturer's standard design, either cast-iron or cold-rolled steel plate with bell-mouth guide groove for curtain.

2.5 LOCKING DEVICE ASSEMBLY

A. Fabricate with lock, spring-loaded dead bolt, operating handle, cam plate, and adjustable locking bar to engage through slots in tracks.

08331 - 4

1. Locking Bar: Single-jamb side, operable from inside and outside.

2.6 FINISHES, GENERAL

A. General: Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples. Noticeable variations in the same piece are not acceptable. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

2.7 STEEL AND GALVANIZED STEEL FINISHES

A. Factory Primer for Field Finish: Apply manufacturer's standard primer, compatible with field-applied finish according to coating manufacturer's written instructions for cleaning, pretreatment, application, and minimum dry film thickness.

1. Apply to ferrous surfaces except zinc-coated metal.

B. Thermoset Finish: Apply manufacturer's standard baked finish consisting of primer and thermosetting topcoat according to coating manufacturer's written instructions for cleaning, pretreatment, application, thermosetting, and minimum dry film thickness.

1. Color and Gloss: As selected by CO from manufacturer's full range of colors and glosses.

2.8 ELECTRIC DOOR OPERATORS

A. General: Provide electric door operator assembly of size and capacity recommended and provided by door manufacturer for door and operational life specified, with electric motor and factory-prewired motor controls, starter, gear-reduction unit, solenoid-operated brake, clutch, remote-control stations, control devices, integral gearing for locking door, and accessories required for proper operation.

B. Comply with NFPA 70.

C. Disconnect Device: Provide hand-operated disconnect or mechanism for automatically engaging sprocket-chain operator and releasing brake for emergency manual operation while disconnecting motor, without affecting timing of limit switch. Mount disconnect and operator so they are accessible from floor level. Include interlock device to automatically prevent motor from operating when emergency operator is engaged.

D. Design operator so motor may be removed without disturbing limit-switch adjustment and without affecting emergency auxiliary operator.

E. Provide control equipment complying with NEMA ICS 1, NEMA ICS 2, and NEMA ICS 6, with NFPA 70 Class 2 control circuit, maximum 24-V, ac or dc.

F. Door-Operator Type: Provide wall-, hood-, or bracket-mounted, jackshaft, gear-head hoist-type door operator unit consisting of electric motor, enclosed worm-gear running-in-oil primary drive, chain and sprocket secondary drive, and auxiliary chain-hoist and floor level disconnect.

G. Electric Motors: Provide high-starting torque, reversible, continuous-duty, Class A insulated, electric motors, complying with NEMA MG 1, with overload protection, sized to start, accelerate, and operate door in either direction, from any position, at not less than 2/3 fps or more than 1 fps, without exceeding nameplate ratings or considering service factor.

08331 - 5

1. Type: Polyphase, medium-induction type.

2. Service Factor: According to NEMA MG 1, unless otherwise indicated.

3. Coordinate wiring requirements and electric characteristics of motors with building electrical system.

4. Provide open dripproof-type motor, and controller with NEMA ICS 6, Type 1 enclosure.

5. Provide totally enclosed, nonventilated or fan-cooled motors, fitted with plugged drain, and controller with NEMA ICS 6, Type 4 enclosure where indicated.

H. Remote-Control Station: Provide momentary-contact, 3-button control station with push-button controls labeled "Open," "Close," and "Stop."

1. Provide interior units, full-guarded, surface-mounted, heavy-duty type, with general-purpose NEMA ICS 6, Type 1 enclosure.

I. Obstruction Detection Device: Provide each motorized door with indicated external automatic safety sensor able to protect full width of door opening. Activation of sensor immediately stops and reverses downward door travel.

1. Sensor Edge: Provide motorized door with an automatic safety sensor edge, located within astragal or weather stripping mounted to bottom bar. Contact with sensor immediately stops and reverses downward door travel. Connect to control circuit using manufacturer's standard take-up reel or self-coiling cable.

a. Provide electrically actuated automatic bottom bar.

J. Limit Switches: Provide adjustable switches, interlocked with motor controls and set to automatically stop door at fully opened and fully closed positions.

K. Provide safety interlock switch to disengage power supply when door is locked.

PART 3 - EXECUTION

3.1 INSTALLATION

A. General: Install door and operating equipment complete with necessary hardware, jamb and head mold strips, anchors, inserts, hangers, and equipment supports according to Shop Drawings, manufacturer's written instructions, and as specified.

3.2 ADJUSTING

A. Lubricate bearings and sliding parts; adjust doors to operate easily, free from warp, twist, or distortion and fitting weathertight for entire perimeter.

3.3 DEMONSTRATION

A. Startup Services: Engage a factory-authorized service representative to perform startup services and to train Government's maintenance personnel as specified below:

1. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

a. Test door closing when activated by detector or alarm connected fire-release system. Reset door-closing mechanism after successful test.

08331 - 6

2. Train Government's maintenance personnel on procedures and schedules related to startup and shutdown, troubleshooting, servicing, preventive maintenance, and procedures for testing and resetting release devices.

3. Review data in the maintenance manuals. Refer to Division 1 Section "Contract Closeout."

END OF SECTION

08710 - 1

FINISH HARDWARE

SECTION 08710

PART 1 - GENERAL

A. Drawings and general provisions of the contract, including general and supplementary conditions and Division 1 specifications sections, apply to this section.

A. Description: "Finish Hardware" includes items known commercially as finish hardware which are required for swing, sliding and folding doors, except special types of unique and non-matching hardware specified in the same section as the door and door frame.

B. Extent of finish hardware required is indicated on drawings and in schedules.

C. Types of finish hardware required include the following:

1. Hinges

2. Lock Cylinders and Keys

3. Lock and Latch Sets

4. Closers

5. Weatherstripping for Exterior Doors

6. Thresholds

D. Related sections include the following:

1. Division 8 Section “Overhead Doors” for door installation information.

1.3 QUALITY ASSURANCE

A. Obtain each type of hardware (latch and lock sets, hinges, closers, etc.) from a single manufacturer, although several may be indicated as offering products complying with requirements.

1.4 SUBMITTALS

A. Submit proposed hardware list showing all items listed on hardware schedule.

B. Submittal shall include manufacturer's catalogs, certification, or other material which proves compliance with these specifications.

C. Samples showing function, finish, and design of proposed items shall be submitted upon request of CO.

All samples remain the property of the supplier and will be returned to him at completion of the work.

D. Hardware Schedule:

1. Submit final hardware schedule in manner indicated below.

2. Coordinate hardware with doors, frames and related work to ensure proper size, thickness, hand, function and finish of hardware.

E. Final Hardware Schedule Content:

08710 - 2

1. Based on finish hardware indicated, organize hardware schedule into "hardware sets" indicating complete designations of every item required for each door or opening.

2. Include the following information:

a. Type, style, function, size and finish of each hardware item.

b. Name and manufacturer of each item.

c. Fastenings and other pertinent information.

d. Location of hardware set cross-referenced to indications on Drawings both on floor plans and in door and frame schedule.

e. Explanation of all abbreviations, symbols, codes, etc. contained in schedule.

f. Mounting locations for hardware.

g. Door and frame sizes and materials.

1.5 PRODUCT HANDLING

A. Hardware shall be delivered and stored in packages that permit handling without damage to the contents.

B. Each package shall be marked to permit easy identification and shall contain fastening and installation instructions.

2.1 SCHEDULED HARDWARE

A. Requirements for design, grade, function, size and other distinctive qualities of each type of finish hardware is indicated in the Hardware Schedule at the end of this section.

2.2 REFERENCE SPECIFICATIONS

A. ANSI/BHMA designations used elsewhere in this section or in schedules to describe hardware items or to define quality or functions are derived from the following standards. Provide products complying with these standards and requirements specified elsewhere in this section.

Butts and Hinges: ANSI A156.1 (BHMA 101) Locks and Lock Trim: ANSI A156.2 (BHMA 601) Door Controls - Closers: ANSI A156.4 (BHMA 301) Template Hinge Dimensions: ANSI A156.7 Mortise Locks and Latches: ANSI A156.13 (BHMA 621) Materials and Finishes: ANSI A156.18 (BHMA 1301)

B. Federal Specifications:

1. Locks and Door Trim - FF-H-106C/Gen., 106/1, 106/2, 106/3.

2. Shelf and Miscellaneous Hardware - FF-H-111C.

3. Hinges - FF-H-116E.

4. Door Closers - FF-H-121D.

2.3 MATERIALS AND FABRICATION

A. General:

1. Hand of door: Drawings show direction of swing or hand of each door leaf. Furnish each item of hardware for proper installation and operation of door movement as shown.

08710 - 3

B. Base Metals:

1. Produce hardware units of basic metal and forming method indicated, using manufacturer's standard metal alloy, composition, temper and hardness, but in no case of lesser (commercially recognized) quality than specified for applicable hardware units by applicable ANSI A156 series standard for each type hardware item and with ANSI A156.18 for finish designations indicated.

Do not furnish "optional" materials or forming methods for those indicated, except as otherwise specified.

C. Fasteners:

1. Provide hardware manufactured to conform to published templates, generally prepared for machine screw installation. Do not provide hardware which has been prepared for self-tapping sheet metal screws, except as specifically indicated.

D. Furnish screws for installation, with each hardware item. Provide Phillips flat-head screws except as otherwise indicated. Finish exposed (exposed under any condition) screws to match hardware finish or, if exposed in surfaces of other work, to match finish of such other work as closely as possible, including "prepared for paint" in surfaces to receive painted finish.

E. Provide concealed fasteners for hardware units which are exposed when door is closed, except to extent no standard units of type specified are available with concealed fasteners. Do not use thru-bolts for installation where bolt head or nut on opposite face is exposed in other work, except where it is not feasible to adequately reinforce the work. In such cases, provide sleeves for each thru-bolt or use sex screw fasteners.

F. Any item found defective or deficient shall be removed and replaced with good and suitable hardware.

2.4 HINGES, BUTTS AND PIVOTS

A. Templates:

1. Except for hinges and pivots to be installed entirely (both leaves) into wood doors and frames, provide only template- produced units.

B. Screws:

1. Furnish Phillips flat-head or machine screws for installation of units, except furnish Phillips flat-head or wood screws for installation of units into wood. Finish screw heads to match surface of hinges or pivots.

C. Hinge Pins:

1. Except as otherwise indicated, provide hinge pins as follows:

a. Steel Hinges: Steel pins.

e. Interior Doors: Non-rising pins.

f. Tips: Flat button and matching plug, finished to match leaves.

g. Number of hinges: Provide number of hinges indicated but not less than three hinges for door leaf for doors 90" or less in height.

2.5 LOCK CYLINDERS AND KEYING

08710 - 4

1. Supplier will meet with CO to finalize keying requirements and obtain final instructions in writing.

2. Standard System:

a. Except as otherwise indicated, provide new masterkey system for project.

B. Equip locks with manufacturer's standard 6-pin tumbler cylinder.

C. Metals:

1. Construct lock cylinder parts from brass/bronze, stainless steel or nickel silver.

D. Key Material:

1. Provide keys of nickel silver only.

E. Key Quality:

1. Furnish 3 change keys for each lock; 5 master keys for each master system; and 5 grandmaster keys for each grandmaster system.

F. Forest Service cylinders, Yale 1152, will be furnished by the Government for installation by the contractor in locks. The locks furnished by the contractor must be a type that will accept the Yale 1152 cylinder and operate properly.

G. No keys required for Forest Service locks.

2.6 LOCKS, LATCHES AND BOLTS

A. Strikes:

1. Provide manufacturer's standard wrought box strike for each latch or lock bolt, with curved lip extended to protect frame, finished to match hardware set.

a. Provide standard (open) strike plates for interior doors of residential units where wood door frames are used.

B. Lock Throw:

1. Provide 5/8" minimum throw of latch and deadbolt used on pairs of doors. Comply with UL requirements for throw of bolts and latch bolts on rated fire openings.

a. Provide 1/2" minimum throw on other latch and deadlock bolts.

2.7 CLOSERS AND DOOR CONTROL DEVICES

A. Size of Units:

1. Except as otherwise specifically indicated, comply with the manufacturer's recommendations for size of door control unit, depending upon size of door, exposure to weather and anticipated frequency of use.

a. Provide non-handed/non-sized heavy duty cast iron door closer which can be mounted any one of four ways to control interior and exterior doors.

b. Provide complete door control and effective back check for each mounting location.

08710 - 5

c. Provide adjustable units complying with ANSI A117.1 provisions for door opening force and delayed action closing.

2.8 DOOR TRIM UNITS

A. Fasteners:

1. Provide manufacturer's standard exposed fasteners for kick plates, either machine screws or self-tapping screw.

B. Fabricate protection kick plates not more than 1-1/2" less than door width on stop side x the height indicated.

1. Metal Plates: Stainless Steel, .050" (U.S. 18 ga.).

2.9 WEATHERSTRIPPING

1. Except as otherwise indicated, provide continuous weatherstripping at each edge of every exterior door leaf. Provide type, sizes and profiles shown or scheduled. Provide noncorrosive fasteners as recommended by manufacturer for application indicated.

B. Replaceable Seal Strips:

1. Provide only those units where resilient or flexible seal strip is easily replaceable and readily available from stocks maintained by manufacturer.

C. Weatherstripping at Jambs and Heads:

1. Provide bumper-type resilient insert and metal retainer strips, surface-applied unless shown as mortised or semi-mortised, of following metal, finish and resilient bumper material:

a. Extruded aluminum with natural anodized finish; 0.062" minimum thickness of main walls and flanges.

b. Closed-cell sponge neoprene insert, conforming to MIL-R-6130A Type II, GradeII, 1/4" x 3/4".

D. Weatherstripping at Door Bottoms:

1. Provide automatic door bottom seals made of extruded aluminum with spring loaded silicon gasket insert.

2.10 THRESHOLDS

A. Passage Door:

1. Provide ramp type threshold built up of three sections as shown on the drawings and specified in the Hardware Group.

2.11 HARDWARE FINISHES

A. Hinges, lock sets and latch sets, pulls, plates, and panic devices shall have US26D, US28, or US32D finish.

B. Door closers and door stops shall have same finish as other hardware or matching lacquer.

08710 - 6

C. Thresholds and weather stripping shall have mill finish.

PART 3 - GENERAL

3.1 PREPARATION

A. Doors, frames, and hardware shall be examined for damage, defects, and suitability for the intended use.

B. Any part or item found damaged, defective, or inadequate shall be repaired before installation, or shall be replaced with good material.

3.2 INSTALLATION

A. Mounting Heights:

1. Heights given are centerline heights up from the floor unless otherwise stated; heights given "Number to Number" indicate that all shall be at one height within the limits given.

INCHES

Bottom Hinge 10-13 from floor Top Hinge 6-8 down from head Intermediate Hinges Equally spaced Door Knob 36-38 from floor

B. Install each hardware item in compliance with the manufacturer's instructions and recommendations.

Wherever cutting and fitting is required to install hardware onto or into surfaces which are later to be painted or finished in another way, coordinate removal, storage and reinstallation or application of surface protections with finishing work specified in the Section 09900 - "Painting". Do not install surface-mounted items until finishes have been completed on the substrate.

Set units level, plumb and true to line and location. Adjust and reinforce the attachment substrate as necessary for proper installation and operation.

Drill and countersink units which are not factory-prepared for anchorage fasteners. Space fasteners and anchors in accordance with industry standards.

Set thresholds for exterior doors in full bed of butyl-rubber or polyisobutylene mastic sealant.

3.3 ADJUST AND CLEAN

A. Adjust and check each operating item of hardware and each door, to ensure proper operation or function of every unit. Replace units which cannot be adjusted to operate freely and smoothly as intended for the application made.

B. Clean adjacent surfaces soiled by hardware installation.

PART 4 - HARDWARE GROUP

1 each Entrance latchset: Latchbolt by lever either side, except when outside lever is set by push/turn button in inside trim. Push button is released by key outside or trim inside.

Turn button must be released manually. Key retracts latchbolt when outside trim is locked. Yale No. 5307

08710 - 7

1-1/2 pair - 4-1/2”x 4-1/2”, full mortise, ball bearing type hinges with non-rising, non-removable pins.

Hager #BB1168

1 each Barrier free door closure with full cover, hold open arm. Yale #3511 BF with dull bronze finish (US 32D).

1 each Modular ramp threshold, for 1/2 inch high offset, 12-3/4 inches wide, extruded aluminum. Pemko R.50SSA

1 set - Weatherstripping, extruded aluminum and closed cell EPDM sponge neoprene for door head and jamb, R 6130 Class II, Grade C materilal. Pemko No. 379 CR

1 each Floor stop -Federal Spec. type 1329E - cast bronze, heavy weight, rubber tip, height 3", diameter of base 2-1/2", hook and keeper, attachment to floor by steel stud with expansion shield and auxiliary machine screw with expansion shield.

09900 - 1

PAINTING

SECTION 09900

PART 1 - GENERAL

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

A. This Section includes surface preparation and field painting of the following:

1. Exposed exterior items and surfaces.

2. Exposed interior items and surfaces.

3. Surface preparation, priming, and finish coats specified in this Section are in addition to shop priming and surface treatment specified in other Sections.

B. Paint exposed surfaces, except where the paint schedules indicate that a surface or material is not to be painted or is to remain natural. If the paint schedules do not specifically mention an item or a surface, paint the item or surface the same as similar adjacent materials or surfaces whether or not schedules indicate colors. If the schedules do not indicate color or finish, the CO will select from standard colors and finishes available.

1. Painting includes field painting of exposed bare and covered pipes and ducts (including color coding), hangers, exposed steel and iron work, and primed metal surfaces of mechanical and electrical equipment.

C. Related Sections include the following:

1. Division 8 Section "Overhead Door" for overhead door requirements. shop priming ferrous metal.

1.3 DEFINITIONS

A. General: Standard coating terms defined in ASTM D 16 apply to this Section.

1. Flat refers to a lusterless or matte finish with a gloss range below 15 when measured at an 85-degree meter.

2. Eggshell refers to low-sheen finish with a gloss range between 5 and 20 when measured at a 60-

3. Satin refers to low-sheen finish with a gloss range between 15 and 35 when measured at a 60-

4. Semigloss refers to medium-sheen finish with a gloss range between 30 and 65 when measured at a 60-degree meter.

5. Full gloss refers to high-sheen finish with a gloss range more than 65 when measured at a 60-

1.4 SUBMITTALS

A. Product Data: For each paint system specified. Include block fillers and primers.

09900 - 2

1. Material List: Provide an inclusive list of required coating materials. Indicate each material and cross-reference specific coating, finish system, and application. Identify each material by manufacturer's catalog number and general classification.

2. Manufacturer's Information: Provide manufacturer's technical information, including label analysis and instructions for handling, storing, and applying each coating material proposed for use.

1.5 QUALITY ASSURANCE

A. Source Limitations: Obtain block fillers, primers, and undercoat materials for each coating system from the same manufacturer as the finish coats.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to the Project Site in manufacturer's original, unopened packages and containers bearing manufacturer's name and label, and the following information:

1. Product name or title of material.

2. Product description (generic classification or binder type).

3. Manufacturer's stock number.

4. Contents by volume, for pigment and vehicle constituents.

5. Thinning instructions.

6. Application instructions.

7. Color name and number.

B. Store materials not in use in tightly covered containers in a well-ventilated area at a minimum ambient temperature of 45 deg F. Maintain containers used in storage in a clean condition, free of foreign materials and residue.

1. Protect from freezing. Keep storage area neat and orderly. Remove oily rags and waste daily.

Take necessary measures to ensure that workers and work areas are protected from fire and health hazards resulting from handling, mixing, and application.

1.7 PROJECT CONDITIONS

A. Apply water-based paints only when the temperature of surfaces to be painted and surrounding air temperatures are between 50 and 90 deg F.

B. Apply solvent-thinned paints only when the temperature of surfaces to be painted and surrounding air temperatures are between 45 and 95 deg F.

C. Do not apply paint in snow, rain, fog, or mist; or when the relative humidity exceeds 85 percent; or at temperatures less than 5 deg F above the dew point; or to damp or wet surfaces.

1. Painting may continue during inclement weather if surfaces and areas to be painted are enclosed and heated within temperature limits specified by manufacturer during application and drying periods.

2.1 MANUFACTURERS

A. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products listed in the paint schedules.

09900 - 3

B. Manufacturers Names: The following manufacturers are referred to in the paint schedules by use of shortened versions of their names, which are shown in parentheses:

1. Devoe & Raynolds Co. (Devoe).

2. Fuller-O'Brien Paints (Fuller).

3. Glidden Co. (The) (Glidden).

4. Benjamin Moore & Co. (Moore).

5. PPG Industries, Inc. (PPG).

6. Pratt & Lambert, Inc. (P & L).

7. Sherwin-Williams Co. (S-W).

2.2 PAINT MATERIALS, GENERAL

A. Material Compatibility: Provide primers, undercoats, and finish-coat materials that are compatible with one another and the substrates indicated under conditions of service and application, as demonstrated by manufacturer based on testing and field experience.

B. Material Quality: Provide manufacturer's best-quality paint material of the various coating types specified. Paint-material containers not displaying manufacturer's product identification will not be acceptable.

C. Colors: Paint colors are based on Federal Standard 595a “Federal Standard Colors (FSC)” Printer 1984.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with the Applicator present, under which painting will be performed for compliance with paint application requirements.

1. Do not begin to apply paint until unsatisfactory conditions have been corrected and surfaces receiving paint are thoroughly dry.

2. Start of painting will be construed as the Applicator's acceptance of surfaces and conditions within a particular area.

B. Coordination of Work: Review other Sections in which primers are provided to ensure compatibility of the total system for various substrates. On request, furnish information on characteristics of finish materials to ensure use of compatible primers.

1. Notify the CO about anticipated problems using the materials specified over substrates primed by others.

3.2 PREPARATION

A. General: Remove hardware and hardware accessories, plates, machined surfaces, lighting fixtures, and similar items already installed that are not to be painted. If removal is impractical or impossible because of the size or weight of the item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations in each space or area, reinstall items removed using workers skilled in the trades involved.

B. Cleaning: Before applying paint or other surface treatments, clean the substrates of substances that could impair the bond of the various coatings. Remove oil and grease before cleaning.

09900 - 4

1. Schedule cleaning and painting so dust and other contaminants from the cleaning process will not fall on wet, newly painted surfaces.

C. Surface Preparation: Clean and prepare surfaces to be painted according to manufacturer's written instructions for each particular substrate condition and as specified.

1. Provide barrier coats over incompatible primers or remove and reprime.

2. Wood: Clean surfaces of dirt, oil, and other foreign substances with scrapers, mineral spirits, and sandpaper, as required. Sand surfaces exposed to view smooth and dust off.

a. Scrape and clean small, dry, seasoned knots, and apply a thin coat of white shellac or other recommended knot sealer before applying primer. After priming, fill holes and imperfections in finish surfaces with putty or plastic wood filler. Sand smooth when dried.

b. Prime, stain, or seal wood to be painted immediately on delivery. Prime edges, ends, faces, undersides, and backsides of wood, including cabinets, counters, cases, and paneling.

3. Ferrous Metals: Clean ungalvanized ferrous-metal surfaces that have not been shop coated;

remove oil, grease, dirt, loose mill scale, and other foreign substances. Use solvent or mechanical cleaning methods that comply with the Steel Structures Painting Council's (SSPC) recommendations.

a. Blast steel surfaces clean as recommended by paint system manufacturer and according to requirements of SSPC-SP 10.

b. Treat bare and sandblasted or pickled clean metal with a metal treatment wash coat before priming.

c. Touch up bare areas and shop-applied prime coats that have been damaged. Wire-brush, clean with solvents recommended by paint manufacturer, and touch up with the same primer as the shop coat.

4. Galvanized Surfaces: Clean galvanized surfaces with nonpetroleum-based solvents so surface is free of oil and surface contaminants. Remove pretreatment from galvanized sheet metal fabricated from coil stock by mechanical methods.

D. Materials Preparation: Mix and prepare paint materials according to manufacturer's written instructions.

1. Maintain containers used in mixing and applying paint in a clean condition, free of foreign materials and residue.

2. Stir material before application to produce a mixture of uniform density. Stir as required during application. Do not stir surface film into material. If necessary, remove surface film and strain material before using.

3. Use only thinners approved by paint manufacturer and only within recommended limits.

E. Tinting: Tint each undercoat a lighter shade to simplify identification of each coat when multiple coats of the same material are applied. Tint undercoats to match the color of the finish coat, but provide sufficient differences in shade of undercoats to distinguish each separate coat.

3.3 APPLICATION

A. General: Apply paint according to manufacturer's written instructions. Use applicators and techniques best suited for substrate and type of material being applied.

1. Paint colors, surface treatments, and finishes are indicated in the schedules.

09900 - 5

2. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or conditions detrimental to formation of a durable paint film.

3. Provide finish coats that are compatible with primers used.

4. Before the final installation of equipment, paint surfaces behind permanently fixed equipment or furniture with prime coat only.

5. Paint back sides of access panels and removable or hinged covers to match exposed surfaces.

6. Finish exterior doors on tops, bottoms, and side edges the same as exterior faces.

7. Sand lightly between each succeeding enamel or varnish coat.

B. Scheduling Painting: Apply first coat to surfaces that have been cleaned, pretreated, or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration.

1. The number of coats and the film thickness required are the same regardless of application method. Do not apply succeeding coats until the previous coat has cured as recommended by the manufacturer. If sanding is required to produce a smooth, even surface according to manufacturer's written instructions, sand between applications.

2. Omit primer on metal surfaces that have been shop primed and touchup painted.

3. If undercoats, stains, or other conditions show through final coat of paint, apply additional coats until paint film is of uniform finish, color, and appearance. Give special attention to ensure edges, corners, crevices, welds, and exposed fasteners receive a dry film thickness equivalent to that of flat surfaces.

4. Allow sufficient time between successive coats to permit proper drying. Do not recoat surfaces until paint has dried to where it feels firm, does not deform or feel sticky under moderate thumb pressure, and where application of another coat of paint does not cause the undercoat to lift or lose adhesion.

C. Application Procedures: Apply paints and coatings by brush, roller, spray, or other applicators according to manufacturer's written instructions.

1. Brushes: Use brushes best suited for the type of material applied. Use brush of appropriate size for the surface or item being painted.

2. Rollers: Use rollers of carpet, velvet back, or high-pile sheep's wool as recommended by the manufacturer for the material and texture required.

3. Spray Equipment: Use airless spray equipment with orifice size as recommended by the manufacturer for the material and texture required.

D. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer's recommended spreading rate. Provide the total dry film thickness of the entire system as recommended by the manufacturer.

E. Mechanical and Electrical Work: Painting of mechanical and electrical work is limited to items exposed in equipment rooms and in occupied spaces.

F. Prime Coats: Before applying finish coats, apply a prime coat of material, as recommended by the manufacturer, to material that is required to be painted or finished and that has not been prime coated by others. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat appears, to ensure a finish coat with no burn through or other defects due to insufficient sealing.

G. Pigmented (Opaque) Finishes: Completely cover surfaces as necessary to provide a smooth, opaque surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness, or other surface imperfections will not be acceptable.

H. Completed Work: Match approved samples for color, texture, and coverage. Remove, refinish, or repaint work not complying with requirements.

09900 - 6

3.4 CLEANING

A. Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from the site.

1. After completing painting, clean glass and paint-spattered surfaces. Remove spattered paint by washing and scraping. Be careful not to scratch or damage adjacent finished surfaces.

3.5 PROTECTION

A. Protect work of other trades, whether being painted or not, against damage by painting. Correct damage by cleaning, repairing or replacing, and repainting, as approved by CO.

B. Provide "Wet Paint" signs to protect newly painted finishes. Remove temporary protective wrappings provided by others to protect their work after completing painting operations.

1. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces. Comply with procedures specified in PDCA P1.

3.6 EXTERIOR PAINT SCHEDULE

A. Smooth Wood: Provide the following finish systems over smooth exterior wood surfaces:

1. Semigloss, Acrylic-Enamel Finish: 2 finish coats over a primer.

a. Primer: Exterior, alkyd or latex, wood primer, as recommended by the manufacturer for this substrate, applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 1.5 mils.

1) Devoe: 1102 All-Weather Exterior Alkyd House Paint Primer.

2) Fuller: 220-08 Exterior Latex Wood Primer.

3) Glidden: UH 450 Ultra-Hide Oil/Alkyd Exterior Primer.

4) Moore: Moorwhite Primer #100.

5) PPG: 72-1 Sun-Proof Exterior House & Trim Wood Primer Flat--Latex.

6) P & L: S/D 1002 Suprime "2" Exterior Latex Wood Primer.

b. First and Second Coats: Semigloss, waterborne, exterior, acrylic enamel applied at spreading rate recommended by the manufacturer to achieve a total dry film thickness of not less than 2.4 mils.

1) Devoe: 17XX Wonder-Shield Semi-Gloss Exterior Acrylic Latex House and

Trim Paint.

2) Fuller: 664-XX Weather King II Semi-Gloss House & Trim Paint.

3) Glidden: 6600 Series Spred Ultra Exterior Gloss Latex House & Trim Paint.

4) Moore: MoorGlo Latex House & Trim Paint #096.

5) PPG: 78 Line Sun-Proof Semi-Gloss Acrylic Latex House and Trim Paint.

6) P & L: Z/F 3100 Series Aqua Royal Latex House & Trim Finish.

7) Color: Match steel siding trim, or as directed by CO.

B. Fiber cement pre-primed siding and trim: Provide the following finish systems over exterior…