OZARK PLATEAU NWR LOONEY CABIN RENOVATION

COLCORD COUNTY, OKLAHOMA 2021

SPECIFICATIONS

TABLE OF CONTENTS

SECTION

01009 GENERAL INFORMATION AND REQUIREMENTS

01505 MOBILIZATION

02070 SELECT DEMOLITION

02080 PIPED UTILITIES - BASIC MATERIALS AND METHODS

02200 EARTHWORK AND DRAINAGE

03300 CAST-IN-PLACE CONCRETE

04200 MASONRY

06100 ROUGH CARPENTRY

06250 WOOD REPAIR

06402 INTERIOR ARCHITECTURAL WOODWORK

07411 MANUFACTURED (METAL) ROOF PANELS

07920 JOINT SEALANTS

08550 WOOD WINDOWS

09900 PAINTING

15050 BASIC MECHANICAL MATERIALS AND METHODS

15110 VALVES

15140 DOMESTIC WATER PIPING

15410 PLUMBING FIXTURES – WATER HEATER

236200 PACKAGED COMPRESSOR CONDENSER UNITS

GENERAL INFORMATION AND REQUIREMENTS 01009-1

SECTION 01009 - GENERAL INFORMATION AND REQUIREMENTS

PART 1: GENERAL

1.1 SUMMARY:

A. Description of Work: The work shall consist of labor, equipment, supplies, materials, and demolition as necessary to renovate a cabin including metal roofing, log wall repair, window replacement, foundation drains, CMU retraining wall rebuild, HVAC package unit replacement, water piping and water heater replacement, and all other items as shown on the drawings and specifications and required for a complete installation.

B. Location: Work under this Contract is located in Colcord County, Oklahoma on the

Ozark Plateau National Wildlife Refuge as shown on the drawings.

C. Site Visit: Contractors are encouraged to visit the project site and inspect existing conditions prior to submitting quotes. See Federal Acquisition Regulation (FAR) clause 52.236-27 Site Visit. Contact Damon Taylor – contact information below - to arrange a site visit:

Damon Taylor Deputy Refuge Manager Sequoyah and Ozark Plateau National Wildlife Refuges 107993 S 4520 Rd Vian, OK 74962 Office: (918) 773-5251 x31 Cell: (918) 774-2842 Damon_Taylor@fws.gov

1.2 REFERENCES:

Referenced Standards are listed in the applicable specification section.

1.3 DEFINITIONS:

Approvals: Approval of submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's (CO) attention in writing.

mailto:Damon_Taylor@fws.gov

GENERAL INFORMATION AND REQUIREMENTS 01009-2

1.4 SUBMITTALS:

A. Scope: Submittals include shop drawings, manufacturers' literature, as-built drawings, samples, work schedules and a schedule of values.

B. Requirements: Refer to specification sections for submittals required. Allow at least 7 working days for review, plus transmittal time back and forth. Submittals shall be sent or delivered to the Contracting Officer's Technical Representative (COTR) at U.S. Fish and Wildlife Service, Region 2, Division of Engineering, P.O. Box 1306, Albuquerque, NM 87103-1306. Submittals shall come directly from the Contractor with their stamp and signature of approval; submittals will not be accepted from sub-contractors or suppliers.

Do not commence work which requires review of any submittals until receipt of returned submittals with an acceptable action. Do not allow submittals without an acceptable action marking to be used for the project.

C. Identification of Submittals: Completely identify each submittal by showing at least the following information:

1. Name and address of submitter (Contractor), plus name and telephone number of the individual to contact for further information.

2. Name of project as it appears in these specifications.

3. Contract number, submittal number, and specification section number to which the submittal applies.

4. Whether this is an original submittal or resubmittal.

5. Each item shall clearly note the manufacturer's name and address, trade name, product, lot, style, color, catalog designation or model number, and locations of use.

D. Unless stated otherwise in the individual specification section, and unless electronic submittals are used, provide 3 copies of hard copy submittals for use by the Government, plus the number of submittals needed to be returned to the Contractor for use by Contractor, sub-contractors, suppliers, or others.

E. Electronic submittals through email attachments are acceptable and preferred. These shall be emailed directly to the COR, with email cc to the CO.

F. There will be no approval of submittals prior to bid opening and award. Submittals will be evaluated based on the requirements of the specifications and drawings, during the submittal process after contract award.

1.5 CONFORMANCE:

GENERAL INFORMATION AND REQUIREMENTS 01009-3

Submittals must show clearly that the product, sample or shop drawing conforms to the specifications.

1.6 QUALITY ASSURANCE:

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This contract incorporates materials, applications, and tests by reference, with the same force and effect as if they were given in full text.

B. Conflict: Where a conflict occurs between reference documents, drawings, and project specifications, the most stringent requirement shall govern.

C. Product basis: Where specifications or drawings call out a specific product or manufacturer, it is understood that an equal or better product is acceptable, as approved in the submittal process.

1.7 DELIVERY, STORAGE, AND HANDLING:

A. Delivery: Protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated. The containers shall bear the referenced specification number, type, and class as applicable.

B. Storage: Provide temporary storage facilities for products. Storage shall comply with the manufacturer's instructions. The storage area shall permit access for inspection and handling.

C. Handling: Load and unload products protecting them from damage.

1.8 PROJECT/SITE CONDITIONS:

A. The project site is a Fish and Wildlife National Wildlife Refuge. Work areas shall be roped off to alert unauthorized personnel to work in progress.

B. Existing property not indicated for demolition, shall be protected. All damage by

Contractor's activities shall be repaired by the Contractor at no additional cost to the Government.

GENERAL INFORMATION AND REQUIREMENTS 01009-4

C. Safety is paramount. Contractor is responsible for safety on the project site and shall take measures to maintain a safe area around the project site which is used by Government employees and the public. Applicable OSHA regulations shall be adhered to by the Contractor. Contractor shall submit a safety plan prior to starting work.

D. Landscape Protection: Protect all vegetation inside and outside work limits. All rutting caused by Contractor activities shall be filled and contoured to match adjacent areas.

Areas damaged by Contractor activities shall be repaired.

E. Utility interruptions, including electrical service, shall not be longer than 24 hours unless approved at least 24 hours beforehand by the Deputy Refuge Manager. Any planned utility service interruption less than 24 hours in duration shall be approved at least 24 hours beforehand by the Deputy Refuge Manager.

1.9 SEQUENCING AND SCHEDULING:

A bar chart type work schedule shall be submitted to the COTR within 5 days after the preconstruction conference. When requested, submit an updated schedule within 3 calendar days.

PART 2: PRODUCTS

2.1 TEMPORARY FACILITIES:

A. The Contractor shall provide toilet facilities for their workers at the site.

B. Water is available from the Refuge water system, and reasonable quantities may be used by Contractor at no charge. Large quantities of water for soil compaction purposes may exceed the Refuge's available supply and in that case the contractor will need to truck in water from sources outside the Refuge boundaries.

C. Electric power is available at the site, and contractor may use reasonable quantity of electric power at no charge.

PART 3: EXECUTION

3.1 PROJECT MEETINGS:

GENERAL INFORMATION AND REQUIREMENTS 01009-5

A. Preconstruction Conference:

1. A preconstruction conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose of the meeting will be to review required work, project drawings and specifications, construction schedules, payroll, payments, and administrative provisions of the contract.

2. The Contractor, subcontractors and the persons responsible for coordination of the work shall be present at the meeting.

3. The Contractor shall submit a schedule of values within 5 days after the preconstruction conference, which may be used as a basis of payment as the work progresses.

B. Progress Meetings:

To be held at the project site as required.

C. Inspections:

1. Routine inspections will be performed by the government Field Inspector (FI).

Inspection of items of work by the FI will not relieve the Contractor of the requirement to meet project specifications. The FI shall be informed 24 hours in advance of work requiring his observation. After being informed in advance the FI's non-attendance shall not prohibit the Contractor from proceeding with work in the FI's absence.

2. For final inspection, notify the COTR in writing at least 6 working days before the completion date so the Government can schedule final inspection. The superintendent shall be present during the final inspection.

3.2 DISPOSAL OF DEBRIS:

Demolition debris and all the refuse generated by the project shall be removed from the project site and disposed of in a legal disposal site by the Contractor. Contractor shall pay all fees required for disposal. Use of Refuge dumpsters for demolition and project refuse is not permitted.

3.3 AS-BUILT DRAWINGS:

GENERAL INFORMATION AND REQUIREMENTS 01009-6

A complete set of full-sized prints, furnished by the Contracting Officer for this purpose only, shall be kept by the Contractor. As the job progresses, continuously maintain as-built drawings of the work. The changes shall be noted legibly in red pencil or red ink.

These drawings shall be submitted to the COR prior to final inspection. Should final inspection reveal changes in the Project not so noted on the As-Built Drawings, the Contractor shall record these changes on the As-Built Drawings within 3 working days of

Final Inspection and deliver completed As-Built Drawings to the COTR.

3.4 WARRANTY:

A. All project construction shall be provided with a one-year warranty in accordance with

FAR 52.246-21.

B. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the contract, the Contractor shall:

1. Obtain the most favorable warranties that would be given by the Contractor in normal commercial practices, but in no case less than called for by the specifications.

2. Require warranties to be executed, in writing, for the benefit of the Government.

3. Submit warranties to the COR prior to the final inspection.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

The work described in these specifications will not be measured for payment.

4.2 BASIS OF PAYMENT:

Payment will be made at the contract price, as indicated in the approved Schedule of Values.

END OF SECTION

MOBILIZATION 01505-1

SECTION 01505 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY: Section includes preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site.

1.2 MEASUREMENT AND PAYMENT:

Units: Progress payments will be made as follows:

1. When 5% of the original contract amount is earned from other Schedule of Value items, 50% of the amount bid for mobilization or 5% of the original contract amount, whichever is lesser, will be paid.

2. When 10% of the original contract amount is earned from other Schedule of Value items, 100% of the amount for mobilization or 10% of the original contract amount, whichever is lesser, will be paid.

3. Upon completion of work for the project, payment of the amount for mobilization in excess of 10% of the original contract amount, will be paid.

4. The total sum of all payments shall not exceed the original Schedule of Values amount for mobilization, regardless of the fact that the Contractor may have shut down the work on the project or moved equipment away from the project and then back again.

PART 2 - PRODUCTS (Not Used.)

PART 3 - EXECUTION (Not Used.)

SELECTIVE DEMOLITION 02070 - 1

SECTION 02070 - SELECTIVE DEMOLITION

1.1 SUMMARY

A. This Section includes the following:

1. Demolition and removal of materials and equipment as indicated in the drawings and specifications.

1.2 MATERIALS OWNERSHIP

A. Demolished materials shall become the property of the Contractor, and shall be removed from the project site and legally disposed of.

1.3 PROJECT/SITE CONDITIONS

A. A staging area for contractor activities will be available in the immediate vicinity of the project. The exact area will be established by the Contractor and FI.

B. Unforseen Conditions: Should unforseen conditions be encountered that affect design or function of the project, investigate fully and submit an accurate, detailed, written report to the COR. While awaiting the Contracting Officer’s response, reschedule operations if necessary to avoid delay of overall project.

PART 2: PRODUCTS (NOT USED)

PART 3: EXECUTION

3.1 EXAMINATION

A. The Contractor shall visit the site and verify the extent and location of the demolition work required. Correlate with drawings and specifications.

3.2 PREPARATION

A. Protection:

1. Provide for the protection of persons passing around or through the area of demolition.

SELECTIVE DEMOLITION 02070 - 2

2. Perform demolition so as to prevent damage to adjacent improvements and facilities to remain.

3. Examine structural supporting conditions and report to the COR any conditions which vary from the drawings or for which unstable conditions may be created by Contractor’s activities. Temporary structural support is the responsibility of the

Contractor. Permanent structural support plans are based on “as-built” drawings which are sometimes not accurate; Contractor shall verify accuracy before proceeding, and shall halt activities and report any variance to the COR before proceeding.

3.3 DEMOLITION - GENERAL

A. Remove debris daily.

B. Perform selective demolition using methods which are least likely to damage work to remain and which will provide adequate structural support and proper surfaces for patching.

C Any areas not called out for demolition but damaged by Contractor activities shall be repaired by the Contractor to pre-existing conditions at no additional cost to the government.

3.4 CLEANING

A. Clean areas affected by demolition to conditions existing prior to the demolition.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 1

SECTION 02080 - PIPED UTILITIES - BASIC MATERIALS AND METHODS

1. Piping materials and installation instructions common to most piping systems.

2. Transition fittings.

3. Dielectric fittings.

4. Sleeves.

5. Identification devices.

6. Grout.

7. Equipment installation requirements common to equipment sections.

8. Concrete bases.

9. Metal supports and anchorages.

1.2 DEFINITIONS

A. Exposed Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions.

B. Concealed Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures.

1.3 SUBMITTALS

A. If piping materials differ from those indicated on drawings, submit proposed substitution for approval.

1.4 QUALITY ASSURANCE

A. Piping work shall comply with IBC, IPC, IMC and local codes and requirements.

B. Comply with ASME A13.1 for lettering size, length of color field, colors, and viewing angles of identification devices.

2 PART 2 - PRODUCTS

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 2

2.1 JOINING MATERIALS

A. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.

B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.

1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch (3.2-mm) maximum thickness unless thickness or specific material is indicated.

a. Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges.

b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.

2. AWWA C110, rubber, flat face, 1/8 inch (3.2 mm) thick, unless otherwise indicated;

and full-face or ring type, unless otherwise indicated.

C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.

D. Plastic, Pipe-Flange Gasket, Bolts, and Nuts: Type and material recommended by piping system manufacturer, unless otherwise indicated.

E. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according to

ASTM B 813.

F. Brazing Filler Metals: AWS A5.8, BCuP Series, or BAg1, unless otherwise indicated.

G. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.

H. Solvent Cements for Joining Plastic Piping:

1. ABS Piping: ASTM D 2235.

2. CPVC Piping: ASTM F 493.

3. PVC Piping: ASTM D 2564. Include primer according to ASTM F 656.

4. PVC to ABS Piping Transition: ASTM D 3138.

I. AWWA Transition Couplings: Same size as, and with pressure rating at least equal to and with ends compatible with, piping to be joined.

2.2 DIELECTRIC FITTINGS

A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solder-joint, plain, or weld-neck end connections that match piping system materials.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 3

B. Insulating Material: Suitable for system fluid, pressure, and temperature.

C. Dielectric Unions: Factory-fabricated, union assembly, for 250-psig (1725-kPa) minimum working pressure at 180 deg F (82 deg C).

D. Dielectric Flanges: Factory-fabricated, companion-flange assembly, for 150- or 300-psig

(1035- or 2070-kPa) minimum working pressure as required to suit system pressures.

E. Dielectric-Flange Kits: Companion-flange assembly for field assembly. Include flanges, full-face- or ring-type neoprene or phenolic gasket, phenolic or polyethylene bolt sleeves, phenolic washers, and steel backing washers.

1. Separate companion flanges and steel bolts and nuts shall have 150- or 300-psig (1035-or 2070-kPa) minimum working pressure where required to suit system pressures.

F. Dielectric Couplings: Galvanized-steel coupling with inert and noncorrosive, thermoplastic lining; threaded ends; and 300-psig (2070-kPa) minimum working pressure at 225 deg F (107 deg C).

G. Dielectric Nipples: Electroplated steel nipple with inert and noncorrosive, thermoplastic lining; plain, threaded, or grooved ends; and 300-psig (2070-kPa) minimum working pressure at 225 deg F (107 deg C).

2.3 SLEEVES

A. Mechanical sleeve seals for pipe penetrations are specified in Division 15 Section "Basic

Mechanical Materials and Methods."

B. Galvanized-Steel Sheet: 0.0239-inch (0.6-mm) minimum thickness; round tube closed with welded longitudinal joint.

C. Steel Pipe: ASTM A 53, Type E, Grade B, Schedule 40, galvanized, plain ends.

D. Cast Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated.

E. Molded PVC: Permanent, with nailing flange for attaching to wooden forms.

F. PVC Pipe: ASTM D 1785, Schedule 40.

G. Molded PE: Reusable, PE, tapered-cup shaped, and smooth-outer surface with nailing flange for attaching to wooden forms.

2.4 IDENTIFICATION DEVICES

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 4

A. Equipment Nameplates: Metal permanently fastened to equipment with data engraved or stamped.

1. Data: Manufacturer, product name, model number, serial number, capacity, operating and power characteristics, labels of tested compliances, and essential data.

2. Location: Accessible and visible.

B. Snap-on Plastic Pipe Markers: Manufacturer's standard preprinted, semirigid, snap-on type.

Include color-coding according to ASME A13.1, unless otherwise indicated.

C. Pressure-Sensitive Pipe Markers: Manufacturer's standard preprinted, color-coded, pressure-sensitive vinyl type with permanent adhesive.

D. Plastic Tape: Manufacturer's standard color-coded, pressure-sensitive, self-adhesive vinyl tape, at least 3 mils (0.08 mm) thick.

1. Width: 1-1/2 inches (40 mm) on pipes with OD, including insulation, less than 6 inches

(150 mm); 2-1/2 inches (65 mm) for larger pipes.

2. Color: Comply with ASME A13.1, unless otherwise indicated.

E. Valve Tags: Stamped or engraved with 1/4-inch (6.4-mm) letters for piping system abbreviation and 1/2-inch (13-mm) sequenced numbers. Include 5/32-inch (4-mm) hole for fastener.

1. Material: 0.032-inch- (0.8-mm-) thick, polished brass or aluminum.

2. Valve Tag Fasteners: Brass, wire-link or beaded chain; or brass S-hooks.

F. Engraved Plastic-Laminate Signs: ASTM D 709, Type I, cellulose, paper-base, phenolic-resin-laminate engraving stock; Grade ES-2, black surface, black phenolic core, with white melamine subcore, unless otherwise indicated. Fabricate in sizes required for message. Provide holes for mechanical fastening.

1. Engraving: Engraver's standard letter style, of sizes and with terms to match equipment identification.

2. Thickness: 1/16 inch minimum, unless otherwise indicated.

3. Thickness: 1/16 inch (1.6 mm), for units up to 20 sq. in. (130 sq. cm) or 8 inches (200

mm) in length, and 1/8 inch (3 mm) for larger units.

4. Fasteners: Self-tapping, stainless-steel screws or contact-type permanent adhesive.

G. Plastic Equipment Markers: Manufacturer's standard laminated plastic. Use colors and designs recommended by ASME A13.1.

1. Terminology: Match schedules as closely as possible. Include the following:

a. Name and plan number.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 5

b. Equipment service.

c. Design capacity.

d. Other design parameters such as pressure drop, entering and leaving conditions, and speed.

2. Size: 2-1/2 by 4 inches (65 by 100 mm) for control devices, dampers, and valves; 4-1/2 by 6 inches (115 by 150 mm) for equipment.

2.5 GROUT

A. Description: ASTM C 1107, Grade B, nonshrink and nonmetallic, dry hydraulic-cement grout.

1. Characteristics: Post-hardening, volume-adjusting, nonstaining, noncorrosive, nongaseous, and recommended for interior and exterior applications.

2. Design Mix: 5000-psi (34.5-MPa), 28-day compressive strength.

3. Packaging: Premixed and factory packaged.

3PART - EXECUTION

3.1 PIPING SYSTEMS - COMMON REQUIREMENTS

A. Install piping according to IBC, IPC, IMC and local codes and requirements.

B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. If location or arrangement change is proposed by Contractor, submit requested change to COTR for approval prior to construction of utility work.

C. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

D. Install piping to permit valve servicing.

E. Install piping at code-required slopes.

F. Install piping free of sags and bends.

G. Install fittings for changes in direction and branch connections.

H. Select system components with pressure rating equal to or greater than system operating pressure.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 6

I. Install sleeves for pipes passing through concrete and masonry walls and concrete floor slabs.

1. Cut sleeves to length for mounting flush with both surfaces.

a. Exception: Extend sleeves installed in floors of equipment areas or other wet areas 2 inches (50 mm) above finished floor level.

2. Install sleeves in new walls and slabs as new walls and slabs are constructed.

a. PVC or Steel Pipe Sleeves: For pipes smaller than NPS 6 (DN 150).

b. Steel Sheet Sleeves: For pipes NPS 6 (DN 150) and larger, penetrating gypsum-board partitions.

J. Verify final equipment locations for roughing-in.

K. Refer to equipment specifications in other Sections of these Specifications for roughing-in requirements.

3.2 PIPING JOINT CONSTRUCTION

A. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

B. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

C. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32.

D. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube"

Chapter, using copper-phosphorus brazing filler metal complying with AWS A5.8.

E. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

F. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 7

G. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

H. Plastic Piping Solvent-Cement Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following:

1. Comply with ASTM F 402 for safe-handling practice of cleaners, primers, and solvent cements.

2. ABS Piping: Join according to ASTM D 2235 and ASTM D 2661 Appendixes.

3. CPVC Piping: Join according to ASTM D 2846/D 2846M Appendix.

4. PVC Pressure Piping: Join schedule number ASTM D 1785, PVC pipe and PVC socket fittings according to ASTM D 2672. Join other-than-schedule-number PVC pipe and socket fittings according to ASTM D 2855.

5. PVC Nonpressure Piping: Join according to ASTM D 2855.

6. PVC to ABS Nonpressure Transition Fittings: Join according to ASTM D 3138

Appendix.

I. Plastic Pressure Piping Gasketed Joints: Join according to ASTM D 3139.

J. Plastic Nonpressure Piping Gasketed Joints: Join according to ASTM D 3212.

K. PE Piping Heat-Fusion Joints: Clean and dry joining surfaces by wiping with clean cloth or paper towels. Join according to ASTM D 2657.

1. Plain-End Pipe and Fittings: Use butt fusion.

2. Plain-End Pipe and Socket Fittings: Use socket fusion.

L. Fiberglass Bonded Joints: Prepare pipe ends and fittings, apply adhesive, and join according to pipe manufacturer's written instructions.

3.3 PIPING CONNECTIONS

A. Make connections according to the following, unless otherwise indicated:

1. Install unions, in piping NPS 2 (DN 50) and smaller, adjacent to each valve and at final connection to each piece of equipment.

2. Install flanges, in piping NPS 2-1/2 (DN 65) and larger, adjacent to flanged valves and at final connection to each piece of equipment.

3. Dry Piping Systems: Install dielectric unions and flanges to connect piping materials of dissimilar metals.

4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 8

3.4 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS

A. Install equipment level and plumb, unless otherwise indicated.

B. Install equipment to facilitate service, maintenance, and repair or replacement of components.

Connect equipment for ease of disconnecting, with minimum interference with other installations. Extend grease fittings to an accessible location.

C. Install equipment to allow right of way to piping systems installed at required slope.

3.5 IDENTIFICATION

A. Piping Systems: Install pipe markers on each system. Include arrows showing normal direction of flow.

1. Plastic markers, with application systems. Install on insulation segment if required for hot noninsulated piping.

2. Locate pipe markers on exposed piping according to the following:

a. Near each valve and control device.

b. Near each branch, excluding short takeoffs for equipment and terminal units.

Mark each pipe at branch if flow pattern is not obvious.

c. Near locations where pipes pass through walls or floors or enter inaccessible enclosures.

d. At manholes and similar access points that permit view of concealed piping.

e. Near major equipment items and other points of origination and termination.

B. Equipment: Install engraved plastic-laminate sign or equipment marker on or near each major item of equipment.

1. Lettering Size: Minimum 1/4 inch (6.4 mm) high for name of unit if viewing distance is less than 24 inches (610 mm), 1/2 inch (13 mm) high for distances up to 72 inches (1800 mm), and proportionately larger lettering for greater distances.

Provide secondary lettering two-thirds to three-fourths of size of principal lettering.

2. Text of Signs: Provide name of identified unit. Include text to distinguish among multiple units, inform user of operational requirements, indicate safety and emergency precautions, and warn of hazards and improper operations.

C. Adjusting: Relocate identifying devices that become visually blocked by work of this or other

Divisions.

3.6 CONCRETE BASES

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 9

A. Concrete Bases: Anchor equipment to concrete base according to equipment manufacturer's written instructions and according to seismic codes at Project.

1. Construct concrete bases of dimensions indicated, but not less than 4 inches (100 mm) larger in both directions than supported unit.

2. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch (450-mm) centers around the full perimeter of the base.

3. Install epoxy-coated anchor bolts for supported equipment that extend through concrete base, and anchor into structural concrete floor.

4. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

5. Install anchor bolts to elevations required for proper attachment to supported equipment.

6. Install anchor bolts according to anchor-bolt manufacturer's written instructions.

7. Use concrete and reinforcement as specified in Division 3 Section "Cast-in-Place

Concrete”

3.7 ERECTION OF METAL SUPPORTS AND ANCHORAGES

A. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor piped utility materials and equipment.

B. Field Welding: Comply with AWS D1.1.

3.8 GROUTING

A. Mix and install grout for equipment base bearing surfaces, pump and other equipment base plates, and anchors.

B. Clean surfaces that will come into contact with grout.

C. Provide forms as required for placement of grout.

D. Avoid air entrapment during placement of grout.

E. Place grout, completely filling equipment bases.

F. Place grout on concrete bases and provide smooth bearing surface for equipment.

G. Place grout around anchors.

H. Cure placed grout.

PIPED UTILITIES - BASIC MATERIALS AND METHODS 02080 - 10

END OF SECTION 02080

EARTHWORK & DRAINAGE 02200 - 1

SECTION 02200 - EARTHWORK

1.1 SUMMARY - This section includes the following:

A. Excavation and backfill required in conjunction with foundation and utility trenches.

B. Earthwork shall be performed in accordance with the International Building Code and the drawings and specifications.

1.2 JOB CONDITIONS

A. Locate existing underground utilities in areas of work. If utilities are to remain in place, provide adequate means of support and protection during earthwork operations.

B. Should uncharted, or incorrectly charted, piping or other utilities be encountered during excavation, contact the COR or PI immediately for directions. Cooperate with COR and PI in keeping respective services and facilities in operation. Repair damaged utilities.

C. Do not interrupt existing utilities serving facilities occupied and used by the Government or others, during occupied hours, except when permitted in writing by the COR and then only after acceptable temporary utility services have been provided.

D. Barricade open excavations occurring as part of this work and post with warning tape.

E. Protect structures, utilities, sidewalks, pavements, trees, and other facilities from damage caused by settlement, lateral movement, undermining, washout and other hazards created by earthwork operations.

2.1 MATERIALS:

A. General Fill shall be soils free of organics and other deleterious materials, with a maximum liquid limit of 40, Plasticity Index between 5 and 20, maximum particle size of 3".

EARTHWORK & DRAINAGE 02200 - 2

3.1 SUBGRADE TREATMENT

A. All subgrade areas to receive General Fill, or Engineered Fill shall be stripped of a minimum of 6 inches of vegetation, roots, topsoil, and soft soils, and compacted.

B. General Fill shall be placed in no greater than 8" thick lifts and compacted to a comparable level of at least 93% of maximum dry density as determined by ASTM D- 698 (Standard Proctor) at -1 to +3% optimum moisture content.

3.2 EXCAVATION

A. Excavation is unclassified. Excavate to subgrade elevations regardless of material encountered, including rock, soil materials and obstructions.

B. Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of COR. Unauthorized excavation as well as remedial work shall be at Contractor’s expense.

C. Excavation for structures shall conform to elevations and dimensions shown within a tolerance of plus or minus 0.1', and extending a sufficient distance from footings for placing and removal of concrete form work, other construction, and for inspections.

3.3 COMPACTION

A. Where subgrade or layer of fill material must be moisture conditioned before compaction, uniformly apply water to surface of subgrade, or layer of soil material, to prevent free water appearing on surface during or subsequent to compaction operations.

B. Do not place fill material on surfaces that are muddy, frozen, or contain frost or ice.

C. Place fill materials evenly adjacent to structures or piping to required elevations. Take care to prevent wedging action of backfill against structures or displacement of piping by carrying material uniformly around structure or piping to approximately same elevation in each lift.

EARTHWORK & DRAINAGE 02200 - 3

3.4 GRADING

A. Uniformly grade areas within limits of grading under this section, including adjacent transition areas. Smooth finished surface within specified tolerances, compact with uniform levels or slopes between points where elevations are indicated, or between such points and existing grades.

B. Grade areas adjacent to building lines as shown on the drawings and to drain away from structures and to prevent ponding. Finish surfaces free from irregular surface changes.

3.5 QUALITY CONTROL

A. If, based on observation and inspection, fills which have been placed are below specified density, provide additional compaction and testing at no additional expense to the Government.

F. Remove trash, debris and waste materials and dispose of legally off site.

G. Excess excavated material shall be removed from the construction site.

3.6 DEWATERING

A. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.

B. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.

1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.

2. If required to keep subgrades dry and convey ground water away from excavation, install a dewatering system. Maintain until dewatering is no longer required.

CAST-IN-PLACE CONCRETE 03300 - 1

SECTION 03300 - CAST-IN-PLACE CONCRETE

1.1 SUMMARY - This section includes cast-in-place concrete for foundations.

1.2 SUBMITTALS

A. Concrete Mix Design in accordance with ACI 301, for approval.

B. Shop drawings of placement and mill reports of reinforcing steel, for approval.

1.3 QUALITY ASSURANCE

A. Contractor or concrete supplier shall measure slump vs mix design slump prior to placement.

B. Standards:

1. International Building Code, Concrete, except as modified herein.

2. American Concrete Institute, Building Code Requirements for Reinforced Concrete.

3. ACI Standards 318 and 315 for reinforcement detailing and placement, including concrete protection for steel reinforcement, unless otherwise indicated or modified herein.

1.4 DEFINITION:

A. All concrete on this project is considered to be “exterior.”

B. Foundation includes footing for retaining wall.

PART 2 - PRODUCTS

2.1 FORMWORK:

A. Forms for Unexposed Finish Concrete: Plywood, lumber, metal, or neatly excavated trench.

2.2 REINFORCING

CAST-IN-PLACE CONCRETE 03300 - 2

A. Reinforcing Bars: ASTM A615, Grade 60, deformed.

B. Supports for Reinforcement: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire fabric in place. Use wire bar-type supports complying with CRSI specifications. For slabs-on-grade, use supports with sand plates or horizontal runners where base material will not support chair legs.

2.3 MATERIALS

A. Aggregate: Except as otherwise specified, aggregate, both fine and coarse, shall conform to ASTM C-33.

1. Maximum size aggregate is 1/5 of narrowest dimension between forms of the concrete member or 3/4 of minimum clear spacing between reinforcing bars.

2. Gradation:

Sieve % Passing (By Weight) 1 100 3/4 35-70 3/8 10-30 #4 0-5

3. Anchorage Items: Slots and inserts for anchoring masonry and mechanical items to concrete, shall be of standard manufacture and of types required to engage with the anchors to be provided and installed therein under other sections of these specifications, and shall be subject to approval.

B. Cement shall be Type I or II Portland Cement and conform to ASTM specification C150.

C. Air Entraining Admixture: Not required.

D. Water Reducing and Retarding Admixtures: If called for in mix design.

1. The admixtures shall produce concrete with the following specific qualities as required in this division- workability, controlled rate of hardening, and compressive and/or flexural strength

2. Minimum of five years actual experience and field service using the exact formulation and dosage for which approval is requested. Only products with an established field record will be approved.

CAST-IN-PLACE CONCRETE 03300 - 3

3. The admixture manufacturer shall provide a certified test result showing that admixture exceeds the minimum requirement of ASTM C494, type A or D.

E. Fly Ash: ASTM C618, Type F.

F. Epoxy Adhesive: ASTM C881, two component material.

PART 3 - EXECUTION

3.1 CONCRETE QUALITY AND STRENGTH

A. Use 3500 psi concrete for all cast in place concrete.

3.3 PROPORTIONING OF CONCRETE MIXES: Trial design batches and testing to meet requirements of the concrete as specified shall be the responsibility of the Contractor.

The design mix shall contain aggregates representative of those proposed for use in the work and shall be of consistencies specified in Paragraph 3.3C, Slump.

A. Established Design-Mix Proportions: Prior to commencing operations, the Contractor shall furnish a statement giving the mix proportions of all ingredients that will be used in the manufacture of concrete proposed for use. The statement shall be accompanied by test reports and all test results from an independent commercial testing laboratory, attesting that the proportions stated will produce concrete of the qualities indicated. No substitutions shall be made in the materials used in the work without additional tests to show that the quality of the concrete is satisfactory.

C. Slump: In the field, slump shall be determined in conformance with ASTM C143, and shall be within the following limits: 1 inch to 4 inches. If mix design calls for less than 4" maximum slump, then slump shall be held to that limit.

3.4 BATCHING AND MIXING: Concrete of the ingredients and design mixes herein specified shall be measured, batched and mixed in conformance with ASTM C94. Semi-automatic plant, is a plant in which batching weights are set manually, mixes are changed manually and materials are batched automatically.

CAST-IN-PLACE CONCRETE 03300 - 4

3.5 PLACING CONCRETE: Concrete shall be handled from mixer to place of final deposit in a continuous manner, as rapidly as practicable and without segregation or loss of ingredient until the approved unit of operation is completed. Concrete shall be placed in the forms, as nearly as practicable in final position in uniform, approximately horizontal layers not over 12 inches deep. Forms or reinforcement splashed with concrete shall be cleaned in advance of placing subsequent lifts. Concrete shall not be allowed to drop freely more than 5 feet in unexposed work nor more than 3 feet in exposed work. Where greater drops are required, a tremie or other approved means shall be employed. Building floor slab and foundation shall be placed in one day in a continuous pour.

A. Cold Weather Placement: All cold weather concreting shall conform to ACI 306

“Recommended Practice for Cold Weather Concreting.” Concrete shall be mixed and placed only when the temperature is at least 40 degrees F, and rising, unless permission to pour is obtained from the COR, in which event all material shall be heated and otherwise properly prepared so that batching and mixing can proceed in full accord with this specification. Suitable means shall be provided for maintaining the concrete at a temperature of at least 50 degrees F, for a period of 72 hours after placing, except that where high-early-strength cement is used, this period may be reduced to 24 hours. The methods proposed for heating the materials and protecting the concrete shall be approved by the COR. Salt, chemicals, or other materials shall not be mixed with the concrete for the purpose of preventing freezing. Accelerating agents shall not be used except when approved in writing by the COR.

B. Hot Weather Placement: All hot weather concrete shall conform to ACI 305. Concrete shall not be placed if its temperature is above 90 degrees F. The concrete mix shall include ice in order to maintain its temperature below 90 degrees F.

3.6 COMPACTION: Immediately after placing, each layer of concrete shall be compacted by internal concrete vibrators supplemented by hand spading, rodding, and tramping.

Mechanical vibration by internal concrete vibrators is not required for slabs. Tapping or other external vibration of forms will not be permitted. Vibrators shall not be used to transport concrete inside forms. Internal vibrators submerged in concrete shall maintain a speed of not less than 7,000 impulses per minute. The vibrating equipment shall at all times be adequate in number of units and power to properly consolidate all concrete.

Spare units shall be on hand as necessary to produce satisfactory consolidation without causing objectionable segregation. The vibrators shall be applied at uniformly spaced points not farther apart than the visible effectiveness of the machine.

3.7 BONDING AND GROUTING: Before depositing new concrete on concrete that has

CAST-IN-PLACE CONCRETE 03300 - 5

set, the surfaces of the set concrete shall be thoroughly cleaned of laitance, coatings, foreign matter, and loose particles. Forms shall be re-tightened. The cleaned surfaces shall be moist but shall be without free water when grout is applied. Apply an even coat of neat cement grout to old concrete surfaces before placing new concrete.

3.8 CURING

A. Concrete shall be protected against moisture loss, rapid temperature change, mechanical injury from rain or flowing water, for the following period: Concrete shall be maintained in a moist condition at temperatures above 50 degrees F for the first 7 days or not less than 70 degrees F for the first 3 days. Concrete shall be protected from local application of heat. Curing activities shall be started as soon as free water has disappeared from the surface of the concrete after placing and finishing.

B. Moist Curing: Unformed surfaces shall be covered with burlap or mats, wetted before placing, and overlapped at least 6-inches. Burlap or mats shall be kept continually wet and in intimate contact with the surface. Where formed surfaces are cured in the forms, the forms shall be continually wet. Burlap shall be used only on surfaces that will be unexposed in the finished work and shall be in 2 layers.

C. Impervious-Sheet Curing: All surfaces shall be thoroughly wetted with fine spray of water and be completely covered with waterproof paper. Covering shall be lapped not less than 12-inches and securely weighted down.

D. Membrane-forming Compound Curing: The compound shall be applied on damp surfaces as soon as the moisture film has disappeared. The compound shall be applied in a two coat, continuous operation at a coverage of not more than 175 square feet per gallon for each coat. The compound shall form a uniform, continuous, adherent film that shall not check, crack or peel, and shall be free from pinholes or other imperfections. Membrane curing compound shall not be used on surfaces that are to receive any subsequent treatments that depend on adhesion or bonding to the concrete, or that are to receive floor hardener. Compound shall not be applied when the wind velocity exceeds 5 miles per hour.

UNIT MASONRY 04200-1

SECTION 04200 - UNIT MASONRY

1.1 SUMMARY

A. This section includes concrete unit masonry.

1.2 SYSTEM PERFORMANCE REQUIREMENTS - Provide concrete unit masonry that develops1500 psi minimum installed compressive strengths (f'm).

1.3 QUALITY ASSURANCE

A, Unit Masonry Standard: Comply with IBC Chapter 21, Masonry.

B. Grout shall be mixed and placed according to manufacturer or grout supplier standard mixes to achieve compressive strength required.

1.4 DELIVERY, STORAGE, AND HANDLING

A. Deliver masonry materials to project in undamaged condition.

B. Store and handle masonry units off the ground, under cover, and in a dry location to prevent their deterioration or damage due to moisture, temperature changes, contaminants, corrosion, and other causes. If units become wet, do not place until units are in an air-dried condition.

C. Store cementitious materials off the ground, under cover, and in dry location.

D. Store aggregates where grading and other required characteristics can be maintained and contamination avoided.

E. Store masonry accessories including metal items to prevent corrosion and accumulation of dirt and oil.

1.5 PROJECT CONDITIONS

A. Protection of Masonry: During erection, cover tops of walls, projections, and sills with waterproof sheeting at end of each day's work. Cover partially completed masonry when construction is not in progress. Extend cover a minimum of 24 inches down both sides

UNIT MASONRY 04200-2

and hold cover securely in place.

B. Do not apply soil loads for at least 12 hours and concentrated loads for at least 3 days after building masonry walls.

C. Cold-Weather Construction: Comply with referenced unit masonry standard for cold-weather construction and the following:

1. Do not lay masonry units that are wet or frozen.

2. Remove masonry damaged by freezing conditions.

D. Hot-Weather Construction: Comply with referenced unit masonry standard.

1.6 SUBMITTALS

A. Product Data: Provide data for concrete masonry units, mortar, grout, and reinforcement.

2.1 MATERIALS - Comply with referenced unit masonry standard and other requirements specified in this Section applicable to each material indicated.

2.2 CONCRETE MASONRY UNITS

A. Comply with requirements indicated below applicable to each form of concrete masonry unit required.

1. Provide special shapes where indicated for bond beams, and other special conditions.

2. Size: Provide concrete masonry units complying with requirements indicated below for size that are manufactured to specified face dimensions within tolerances specified in the applicable referenced ASTM specification for concrete masonry units.

a. Concrete Masonry Units: Manufactured to specified dimensions of 3/8 inch less than nominal widths by nominal heights by nominal lengths indicated on drawings. Standard Units shall be 8x8x16 inch nominal, as shown on drawings.

Special shapes shall be manufacturer’s standard or field modified units.

B. Hollow Load-Bearing Concrete Masonry Units: ASTM C 90, and as follows:

1. Unit Compressive Strength: Provide units with minimum average net area

UNIT MASONRY 04200-3

compressive strength of 1900 psi.

2. Weight Classification: Normal weight, with minimum dry weight of 125 pcf.

2.3 MORTAR AND GROUT MATERIALS

A. Portland Cement: ASTM C 150, Type I or II, except Type III may be used for cold-weather construction. Provide natural color cement as required to produce required mortar color. Match existing mortar color.

B. Hydrated Lime: ASTM C 207, Type S.

C. Aggregate for Mortar: ASTM C 144, except for joints less than 1/4 inch use aggregate graded with 100 percent passing the No. 16 sieve. All mortar shall be match color of mortar on existing shop building.

D. Aggregate for Grout: ASTM C 404.

E. Water: Clean and potable.

2.4 REINFORCING STEEL

A. Provide reinforcing steel complying with requirements of referenced unit masonry standard and this paragraph.

B. Deformed Steel Reinforcing Bar - Material and grade as follows:

1. Billet steel complying with ASTM A 615.

2. Grade 60.

2.5 MORTAR AND GROUT MIXES

A. Do not add admixtures including coloring pigments, air-entraining…