This is a Statement of Work (SOW) for the Forestwide Barracks Decommission project on the Tahoe National Forest in Yuba, Nevada, and Placer Counties, California.
The contractor shall furnish all labor, materials, equipment, and incidentals necessary to decommission barracks and other buildings, including demolishing and dismantling all assigned structures, disposing of all waste and hazardous materials through proper channels, removing and disposing of asbestos-containing materials as noted in the Schedule of Items, and properly disconnecting and capping all utilities (power, sewer, water) per code. All removed items must be disposed of off-forest. Personnel performing the work must be licensed to install scheduled items in the State of California. The project schedule spans from February 1, 2026, through May 1, 2027, with all work to be completed by May 1, 2027. Because barracks are generally occupied between May and October, typically only one barracks will be available for work at a time, and all work must be completed within an agreed timeframe to allow occupants to return; all buildings must remain entirely functional while occupied. Bidders shall submit a proposed schedule with their bid for tenant management purposes.
An organized site visit is scheduled for Monday, July 27 to July 29, 2026, at 0800, meeting at Tahoe National Forest Supervisor's Office, 631 Coyote Street, Nevada City, California 95959. A tour of representative facilities will be held starting June 24, 2026, at 0800 AM PST. Building exteriors are accessible without prior approval; interiors will be open during the scheduled tour. The contracting documents include a map of complex locations, GPS coordinates, and addresses. For further information or to schedule additional site visits, contact Assistant Forest Engineer Cesar Villa at (530) 966-6183 or cesar.villa@usda.gov. Some sites require travel on National Forest roads that may be infeasible in winter depending on conditions. Contractors may propose optional alternative systems or items but must demonstrate cost savings or superior performance; technical proposals must clearly identify whether a metal roofing system structurally rated for existing purlin span or additional sheathing will be used to support the specified metal roofing requiring a continuous, rigid substrate.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FORESTWIDE BARRACKS DECOMMISSION
Tahoe National Forest
Yuba, Nevada and Placer Counties
STATEMENT OF WORK
The purpose of this project is to decommission barracks, and other buildings located on the Tahoe National Forest. The work includes but is not limited to demolishing, clearing and disposing properly of debris, HAZMAT mitigation such as led paint, asbestos, and/or animal feces, and capping utilities.
Furnish all labor, materials, equipment, and other incidentals necessary to complete the following work items as listed in the Schedule of Items:
Demolishing – Dismantle all assigned buildings.
Disposing - Contractor will dispose of all waste, including hazard materials properly and through the proper chanels.
HAZMAT Mitigation – Properly remove and dispose of any asbestos containing materials
(noted in Schedule of Items).
Utilities/Services – Contractor shall properly disconnect and cap all services per code, sus as power, sewer, and water.
Note that removal of any items listed for removal includes appropriate disposal off-forest.
SUBMITTALS
N/A
PROPOSALS
Contractor’s quotes shall provide for the purchase and installation of the items and types specified in the Schedule of Items and Specifications. Contractors may also provide quotes and technical plans for optional alternative systems or items but must demonstrate cost savings or superior performance of the alternative options. The contractor’s technical proposal should clearly identify the use of either a metal roofing system structurally rated for the existing purlin span, or the addition of sheathing to support the type of metal roofing specified in this contract, which requires a continuous, rigid substrate. If proposing an alternative structural metal system, provide manufacturer’s specifications.
SITE VISITS
An organized site visit has been scheduled for-
Date / Time: Monday, July 27th to the 29th, 2026 @ 0800
Participants will meet at-
Address / bldg. #: Tahoe National Forest SO, 631Coyote St. Nevada City, CA 95959 We will visit facilities in Yuba Counties, on Monday June 27th. Placer county on June 28th. then on Thursday June 26th, we will re-visit sites if a contractor could not make the previous dates, but not all sites will be shown on this date.
FS personnel leading Site Visit Contact Info
Title: Assistant Forest Engineer
Engineer/COR Name: Cesar Villa
Phone #: 530-966-6183
All bidders are strongly urged to conduct site visits prior to entering bids in order to best assess the nature and condition of the existing buildings. The building exteriors are accessible without prior approval. A tour of several representative facilities will be held starting June 24th , 2026 at 0800 AM PST at which time the interior of the buildings in concern will be open for viewing. Please contact Assistant Forest Engineer, Cesar Villa at (530) 966-6183 cesar.villa@usda.gov for further questions or to schedule site visits you would like to conduct to barracks not shown on the tour.
SCHEDULE
Calander days: February 1st, 2026 through May 1st, 2027
All work shall be completed by May 1, 2027. Barracks are generally occupied between May and October. Unless circumstances allow, only one barracks will be made available for work at a time and all work must be completed within an agreed time frame to allow for occupants to return. All buildings shall be entirely functional while occupied. Bidders shall submit a proposed schedule along with their bid so that the US Forest Service can manage tenants accordingly.
PERSONNEL QUALIFICATIONS
All work shall be performed by a contractor licensed to install scheduled items in the State of California.
PROJECT LOCATION
A map of complex locations has been provided in the contracting documents and sites are generally locatable through online mapping applications. Approximate GPS coordinates and addresses have been submitted. Some sites require travel on National Forest roads which can be infeasible in the winter depending on conditions. For further information, or directions, contact Assistant Forest Engineer, Cesar Villa at (530) 966-6183 cesar.villa@usda.gov.