About this file

This document provides specifications for vacuum fill tubes required by the Department of the Army Materiel Command Joint Munitions Command. The solicitation seeks a one-time fixed price contract to supply vacuum fill tubes in accordance with the included statement of work and drawing. The tubes must achieve and maintain 28.5 inches of mercury vacuum for 10 minutes when assembled and have a minimum 58.13 inch interior diameter and 194.5 inch interior length without the lid. The lid must attach using stainless steel bolts and have lifting eyelets for weight support. Aluminum construction and material thicknesses, as well as a polycarbonate fill plate, o-ring seals, and design review requirements are specified. The response deadline is July 21st, 2022 with performance at the McAlester Army Ammunition Plant in Oklahoma. This procurement is reserved entirely for small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to Vacuum Fill Tubes, newest first.
File Type Posted
A02 - SOW_MPLF VACUUM TUBE.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D

C

.a

194.50

REQUIRED INSIDE

HEIGHT

96.50

) ERENCE

- J

SWING BOLTS & THREADED HANDLE REQUIRED.

DESIGNER WILL DETERMINE THE QTY. TO MEET CRITERIA.

(/)58.13

MINNIMUM ID

(/).80 THRU HOLE

L

4X4XI AN LE

QTY.6 EQUALLY SP

" " /2" G

ACE

185.0 0

HEIGHT REQUIRED

TUBE NEEDS ANCHORING CAPABILITIES

DOUBLE O-RING SEAL Ot THIS FACE

DETERMINED BY DESIGNER

SLOTS SIZE/NUMBER OF DETERMINED BY DESIGNER

THICKNESS DETERMINED BY

r DESIGNER

40.00 SCQO,S[aT==-='====-====1=-=:zi_i

LMINIMUM .50 FLANGE THICKNESS

MINIMUM OF QTY.6, .80 DIAMETER MOUNTING HOLES

"'--, MINIMUM OF I THICK BOTTOM PLATE

NOTE:

I. ALUMINUM 6061-T6 (/)24.00

REQUIRED DIMENSION

NOTE:

I. AL

U

MINUM 6061-T6

VACUUM LID

D

C

VACUUM TUBE

UUM T

U

B

: ____ 7 _____________________ _J_ ____________________________________

REQUIR

�i��

ENSION

VACUUM LID

________________ J_ ________________________ _

QUALIFYING STATEMENT FOR THE VACUUM TUBE

NOTE:

I. MATERIAL CLEAR POLYCARBONATE

(/)23.90

(/)26.87

I-< 12 5)

FILL PLATE ONLY

SCOPE

THE FOLLOWING DOCUMENT PROVIDES THE REQUIREMENTS AND SPECIFICATIONS FOR VACUUM TUBE CHAMBER TO SUPPORT THE FILL AREA OPERATIONS.

1. GENERAL REQUIREMENTS

THIS SECTION PROVIDES REQUIREMENTS THAT ARE COMMON TO EACH OF THE VACUUM CHAMBERS.

A. MUST ACHIEVE AND HOLD 28.5 IN/HG OF VACUUM FOR 10 MINUTES WHEN WELDED AND ASSEMBLED.

B. 58.13" INSIDE MINIMUM DIAMETER.

C. 194.5" INSIDE OVERALL LENGTH WITHOUT LID (CHAMBER).

D. LID MUST ATTACH TO VACUUM TUBE USING STAINLESS 300 SERIES SWING BOLTS, HANDLES AND LIFTING EYELETS (CHAMBER LID).SWING-BOLTS SHALL BE ADEQUATE TO MAINTAIN VACUUM.

E. ALUMINUM CONSTRUCTION ON TUBE & LID.

F. 3/8" MINIMUM MATERIAL THICKNESS ON ALL COMPONENTS UNLESS OTHERWISE SPECIFIED ON DRAWING.

G. LIFTING EYELETS (QTY. 6 EQUALLY SPACED) AROUND VACUUM TUBE OPENING 48" DOWN TO SUPPORT WEIGHT OF VACUUM TUBE.

H. (QTY. 6 EQUALLY SPACED) 4" X 4" X ½" THICK TAB WELDED AROUND TUBE OPENING.

I. BUILD A POLYCARBONATE FILL PLATE TO FIT IN THE 24" DIAMETER HOLE. 1/4" VITON 0-RING SEALS (FILL PLATE).

J. PRELIMINARY APPROVAL/TECHNICAL DRAWINGS ARE REQUIRED FOR APPROVAL PRIOR TO AWARD, BUILD DRAWINGS TO BE SUBMITTED FOR APPROVAL WITHIN 4 WEEKS OF AWARD.

PRESSURE SUMMARY, THICKNESS SUMMARY, WEIGHT SUMMARY & VACUUM SUMMARY (REQUIRED).

K. VACUUM LID TO MEET DIAMETERS AND HEIGHTS SPECIFIED ON DRAWING, MATERIAL THICKNESS IS DETERMINED BY DESIGNER.

L 40,000 LBS. WILL BE APPLIED TO THE BOTTOM OF VACUUM CHAMBER, MCAAP WILL SUPPLY THE SUPPORT STRUCTURE UNDERNEATH THE TUBE.

M. MANUFACTURE A FILL PLATE PER TUBE.

N. (QTY.1) OPERATIONAL, MAINTENANCE, AND PARTS MANUALS THE CONTRACTOR SHALL FURNISH UNDER THIS PURCHASE DESCRIPTION TWO (2) SETS OF OPERATIONAL, MAINTENANCE, AND PARTS

MANUALS AS NECESSITATED BY THE EQUIPMENT. THE MANUALS SHALL BE SPECIFIC (NOT CANNED STATEMENTS ABOUT THE SYSTEM IN GENERAL) TO THE SYSTEM SUPPLIED. THERE SHALL BE A BRIEF DESCRIPTION CONCERNING THE PURPOSE OF THE SPECIFIC EQUIPMENT SUPPLIED AND THE RATED OPERATING CAPACITIES. THE MANUALS SHALL CONTAIN A COMPLETE PARTS LISTTO INCi LJDF (AT MINIMUM) Al I INFORMATION NFCFSSARY (MANLJFACTLJRFR'S NAMF, ADDRFSS, PHONF NLJMRFR, P/N, S/N, Sl7F, MODFI NlJMRFR, TYPF, FTC.) TO RF-ORDFR THF PART IF NFCFSSARY THE MANUALS SHALL INCLUDE ALL PREVENTATIVE MAINTENANCE PROCEDURES/SCHEDULES SPECIFIC TO THE EQUIPMENT SUPPLIED. THESE MANUALS SHALL BE APPLICABLE TO THE EQUIPMENT PROVIDED ONLY AND SHALL INCLUDE ALL SAFETY PRECAUTIONS/WARNINGS ASSOCIATED WITH THE OPERATION. ALL MANUALS SHALL BE AUTHORIZED FOR REPRODUCTION AND DISTRIBUTION TO END USERS OF THE EQUIPMENT. ONE (1) SET OF HARD COPY VERSIONS OF THE MANUALS SHALL BE PROVIDED WITH THE EQUIPMENT. ONE (1) SET OF THE MANUALS SHALL BE ELECTRONIC IN FORM (ON CD) AND MUST BE CAPABLE OF BEING READ IN EITHER A ".PDF" OR A ".DOC" FORMAT.

0. 30%,60%,90% DESIGN/PROGRESS REVIEW REQUIRED

JMMC-OMP WILL VALIDATE AND VERIFY EQUIPMENT BEFORE AWARD IS GRANTED. POCJASON TUCKER

DISTRIBUTION STATEMENT A.

APPROVED FOR PUBLIC RELEASE:

DISTRIBUTION IS UNLIMITED.

UNLESS OTHERWISE SPECIAEO: MCAAP APPROVAL

TOLERAN CES

>------+------ �R:gJ��A� l/6�

TWOPLACEDECIMAL a.OJ

D AWN T KER

IRECTOROM!fl.'IALAPPROVAL)

DE 21

1------+-----tTHREEPLACEDECIMAL a.

1----------------t

1------+-----t :��it BURRS AND SHA RP

MPLF VACUUM

CHAMBER TUBE

1------+-----t g�!��:fg����U

G C�

UMBER 1-,-0-,0-◊-M-H�O-W�El-L

N

O

T

_--W-EIG-HT

�, �-,-,o-G-. N-0-.---<

1-..::,::'.'.,,,._J _ _::::,:__4,, A:::S:,;S::_P:;:EC::IF_::IE;::D_--lwe-;------r,,c'<«ecc<e"',io;;AC(Y-----i si��E0�N�M

AS SPECIFIED

N/A N/A

MCALESTER ARMY AMMUNITION PLANT A

SHEET I OF I