A02_Bid_Schedule_-_base_bid_with_additives.pdf

PDF 117 KB Posted

Attached to
MN-FERGUS FALLS WMD-PARKING IMPROVEMENTS
Solicitation number
140F0222R0029
Issued by

About this file

This document contains a bid schedule for a federal construction contract opportunity with the Department of the Interior Fish and Wildlife Service Region 2. The bid schedule outlines the base bid and three additive alternates to construct parking improvements at the MN-FERGUS FALLS WMD facility. The base bid work includes removing existing asphalt, installing new asphalt and concrete surfaces, relocating light poles, adding fill and seeding. Additive Alternate 1 adds conduits from the maintenance garage to an employee parking area for future electric vehicle charging. Additive Alternate 2 adds similar conduits from a dormitory building to the main parking lot. Additive Alternate 3 replaces curb and gutter in the bus parking zone. Bidders are to provide a lump sum price for each work item and alternate.

View the file

Other files

File Type Posted
Sol_140F0222R0029_Amd_0001.pdf PDF
PPQ.docx DOCX document
A06-DWGS_072822.pdf PDF
Safety_Checklist.pdf PDF
A06_Specs_PWLC_Parking_Improvements.pdf PDF
Sol_140F0222R0029.pdf PDF
BidBond__Form_SF24.pdf PDF
CPARS_Notice.pdf PDF
WD.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STANDARD FORM 36, JULY 1966 REF NO OF DOC BEING CONT'D PAGE 1 OF 1

GENERAL SERVICES ADMINISTRATION

FED PROC. REG. (41 CFR) 1-16.101

NAME OF OFFEROR OR CONTRACTOR

BID SCHEDULE

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Furnish all labor, tools, equipment, materials, superintendence and transportation necessary to construct the project in accordance with the Technical Specifications, Drawings, and terms and conditions contained herein as follows:

SCHEDULE 1

1-1 The Base Bid Item #1 work includes but is not limited to: 1 LS

Removing existing asphalt from highway entrances to entrance/exit roads, main parking lot, bus unloading/parking lot, and maintenance road. Installing new 3" of asphalt in 2 lifts for the same locations.

Shifting main parking lot south and creating new parking along north side. Paint striping/arrows as shown. Installing new curb & gutter, concrete paving and sidewalks, miscellaneous patching as noted.

Installing storm drain system in bus unloading/parking lot to daylight southeast of garage. Relocating light poles at main parking lot and adding 3 ea. new light poles at employee parking area. Installing light bollards at new sidewalks, including conduit/conductors. Adding borrow fill, grading, and seeding as noted.

1-2 The Base Bid Item #2 work includes but is not limited to: 1 LS Mallard Marsh Trail sawcutting and removing existing asphalt, adding borrow fill, gravel, topsoil, erosion straw bio rolls, hydroseeding, and staking.

Total Base Bid

2-1 The Bid Additive #1 work includes but is not limited to: 1 LS

BA-1: Install 2 ea. 2" empty conduits, with pull strings and caps, from outside maintenance garage building to plan north side of new employee parking for future electric vehicle charging station. Noted on Sht. 9.

Total Base Bid plus Bid Additive #1

2-2 The Bid Additive #2 work includes but is not limited to: 1 LS

BA-2: Install 2 ea. 2" empty conduits, with pull strings and caps, from plan north side of dormitory building to north of main parking lot for future electric vehicle charging station. Noted on Sht. 4.

Total Base Bid plus Bid Additive #2

2-3 The Bid Additive #3 work includes but is not limited to: 1 LS BA-3: Remove and replace curb and gutter, B612, on plan south side of bus unload/parking zone. Noted on Sht. 5.

Total Base Bid plus Bid Additive #3

A

File details come from the government source that posted it. Updated .