A01_REQUIREMENT PACKAGE_FR321 High Qualty Surfacing_Statement of Work.pdf
PDF 547 KB Posted
- Attached to
- High Quality resurfacing Federal contract opportunity
- Solicitation number
- 12441923Q0053
- Issued by
- Department of Agriculture Forest Service
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| NRE_Commercial Services_RFP or RFQ_03162023 (1).docx | DOCX document | |
| FR321 BLANK BID SHEET.pdf | ||
| FS 14.pdf | ||
| Evaluation Best Value.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information Location and Project Description Contractor Requirements
Road Log - Description of Work Deliverables / Schedule
Project Forest Road 321 High Quality Surfacing
General Information This contract is for Roadbed Reconditioning on Forest Road (FR) 321 East Windfall Road. Work includes Roadbed Reconditioning, Aggregate Base Coarse and Aggregate Surface Coarse Placement. All work performed shall be completed in accordance with the Standard Specification for Roads and Bridges on Federal Highway Project (FP-14) and the provided Forest Service Supplemental Specifications to the FP-14 (FSSS).
Location and Project Description Road to receive reconditioning is located within the Zone 1, Bradford Ranger District, of the Allegheny National Forest, in McKean county of Pennsylvania. Total road length to be reconditioned is .44 miles, with 322 tons of Aggregate surface course (type DSA Limestone) and 23 tons of Aggregate Surface Course (Crushed #3).
Contractor Requirements Road Log - Description of Work
FR 321- EAST WINDFALL
STATION 0+00 TO 252+10: LEVEL OF SERVICE I (OPEN)
OGM CONTACT INFORMATION: PENNSYLVANIA ONE CALL (800-242-1776)
MILEPOST STATION
ROAD LOG/WORK DESCRIPTION (OCTOBER 22)
0.000
0+00
INTERSECTION OF FR 150 AND FR 321
COORDINATES: LATITUDE 41° 46’23.9" N (41.773297)
LONGITUDE 78° 46’11.3" W (-78.769793)
0.000
0+00
INTERSECTION WITH FR150 AT STATION 535+35
0.000 - 0.303 0+00 - 16+00
RECONDITION ROADBED ACCORDING TO THE
TYPICAL DRAWING (SEE “TYPICAL RECONDITION
SECTION” IN THE DRAWINGS), AND FP-14 FOREST
SERVICE SUPPLEMENTAL SPECIFICATIONS (FSSS),
SECTION 303.05, ROADBED RECONDITIONING,
APPLY (253) TONS OF COMPACTED LIMESTONE
DSA SPOT SURFACING
0.160
8+45
CAMPSITE #15 PARKING AREA RIGHT
0.211
11+15
MEAD RUN TRIPLE CMPA'S 83" X 57" X 40' CMPA
0.189
- 0.234 11+40 - 12+40
APPLY (23) TONS OF COMPACTED #3 CRUSHED
AGGREGATE AS BASE
2.235
118+00
OGM ROAD LEFT
2.259
119+30
PARKING AREA LEFT / OGM ROAD RIGHT
2.272
2.386 120+00
126+00
RECONDITION ROADBED ACCORDING TO THE
TYPICAL DRAWING (SEE “TYPICAL RECONDITION
SECTION” IN THE DRAWINGS), AND FP-14 FOREST
SERVICE SUPPLEMENTAL SPECIFICATIONS (FSSS),
SECTION 303.05, ROADBED RECONDITIONING,
APPLY (69) TONS OF COMPACTED LIMESTONE DSA
SPOT SURFACING, END OF FR321 ROADWORK
Requirements
• All work performed shall be completed in accordance with the Standard Specification for Roads and Bridges on Federal Highway Project (FP-14) and the provided Forest Service Supplemental Specifications to the FP-14 (FSSS).
• Contractor shall provide all equipment, labor, materials, tools, and other incidentals and execute all work necessary to perform the required road maintenance on the designated National Forest roads in accordance with the specifications, and bidder’s technical proposal which is incorporated by reference.
• Prior to any earth disturbing activities, contractor shall call the Pennsylvania One Call System (800-242-1776) and all Oil and Gas Operators in the work area to determine locations of any underground utility lines.
• The contractor shall be held liable and is responsible for any damage caused by their personnel or equipment to any pipelines, trees, culverts, signs, posts, riprap, or structures. Repair or replacement shall be at the Contractor's expense and at no additional cost to the Government.
• Mitigation for Non-Native Invasive Species (NNIS) will be discussed at the pre-work conference. Maps of infestations and appropriate prevention and mitigation measures will be supplied and discussed. Construction Requirements and equipment cleaning for mitigation are as described in Supplemental Specification 151.
Deliverables / Schedule
• Within 10 days after award, the contractor will submit to the Contracting Officer, for approval, a plan of operation indicating the planned operations and proposed timetable to complete the scheduled work activities. Contractor shall notify the COR of any changes to the plan of operation by phone call or e-mail.
• Contractor is responsible to have in place a quality control system that will ensure work is performed in an acceptable manner. The Contractor will promptly furnish the COR with a copy of all inspection documents. Government Inspections are for the Government’s benefit.
| Project |
| General Information |
| Location and Project Description |
| Contractor Requirements |
| Road Log - Description of Work |
| Deliverables / Schedule |