About this file
This is a Statement of Work and Specifications document for the re-roofing of the Raco Ten Bay Building at the Saint Ignace Ranger District Office within the Hiawatha National Forest, located at 9200 South Ranger Road, Brimley, Michigan 49715.
The work scope includes complete removal and replacement of existing roof coverings, including shingles, underlayment, and drip edge. The contractor must install Ice & Water Shield in two rows at roof eaves, synthetic underlayment (Grace Synthetic Felt or approved equal) across the remaining roof, new white metal drip edge, and CertainTeed Landmark dimensional asphalt shingles in Moire Black color (or approved equal). The specifications require the shingles to meet UL Certification, ASTM D3462, ASTM D3018 Type I self-sealing specifications, Class A fire resistance per UL 790, and 110 mph wind resistance rating. The roof area measures approximately 26 feet by 96 feet on a building that is 24 feet deep by 94 feet long, with the contractor responsible for verifying exact measurements. The contract is awarded on a Lump Sum basis with a performance schedule of 150 calendar days including materials submittals and delivery. Work must be performed during normal business hours (8 AM to 4:30 PM Monday through Friday) with the contractor responsible for all debris disposal, landfill documentation, site cleanup, protection of adjacent property, and compliance with OSHA and MIOSHA safety regulations. The contractor must submit manufacturer's literature, product data, and a progress schedule within five days of the Notice to Proceed for Contracting Officer approval prior to material purchase.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C_Pictures_Raco10-BayBuilding.pdf | ||
| 12445526Q0053.pdf | ||
| B_ScheduleOfItems_QuoteForm_Raco10-BayRe-Roofing.docx | DOCX document | |
| D_SitePlanRacoAdminSite.pdf | ||
| E_VacinityMapRacoAdminSite.pdf | ||
| F_WDOL_DBA_MI.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Saint Ignace Ranger District Office Re-Roofing Hiawatha National Forest
SPECIFICATIONS
INDEX
SECTION 011000 SUMMARY
SECTION 013000 SUBMITTALS
SECTON 015000 TEMPORARY FACILITIES AND CONTROLS
SECTION 024119 SELECTIVE DEMOLITION
SECTION 073113 ASPHALT SHINGLES
SECTION 011000 - SUMMARY
GENERAL
STATEMENT OF WORK
Project: Raco Ten Bay Building Re-Roofing Address: 9200 South Ranger Rd, Brimley, MI 49715 Purpose of work:
Re-Roofing the Raco Ten Bay Building.
Description of Work The principal features of the work to be performed under these specifications includes:
Base bid includes the removal and replacement of the existing roof coverings at the Raco Work Center, Ten Bay Building including roof shingles, underlayment, and drip edge. The Contractor shall provide Ice & Water Shield two rows at the roof eves, synthetic underlayment on the rest of the roof, new white metal drip edge at eves, and new CertainTeed Landmark dimensional roof shingles (Moire Black color) or approved equal. The Contractor shall include all dump fees for disposal of all debris. The Contractor shall provide all supervision, labor, equipment, materials, and miscellaneous materials and supplies (staples, nails, roof cement, starter shingles, cap shingles, etc.) for a complete weather tight project.
Photos: See attached photos for existing conditions. The building is 24-foot deep by 94-foot long. The roof area is approximately 26’x96’, Contractor to site verify.
The Contractor shall be responsible for measurement of existing office building to determine all materials needed to complete construction.
Performance schedule: Contract time shall be 150 calendar days (5 months) including roofing materials submittals and roofing materials delivery time.
Measurement and Payment: Lump Sum Quantities (LSQ) – These quantities denote one complete unit of work as required by or described in the contract; including materials, equipment, labor, and incidentals necessary to complete the job. They will not be measured; progress payments can be processed based upon the completed percentage of the LSQ.
Workmanship: The CO shall be the sole judge of workmanship; the CO will use standard construction standards and practices as a basis for judgements. All work shall be completed per the material manufacturers warranty instructions and Michigan Building Code Requirements.
Protection of personnel and property: The Contractor shall provide temporary barricades, dust partitions, and other forms of protection as required to protect public and FS personnel from injury due to construction activities. The Contractor shall be responsible for repairing or replacing FS property that is damaged by construction activities in a manner acceptable to the CO.
The Contractor shall follow all OSHA and MIOSHA safety regulations.
WORK RESTRICTIONS
Contractor's Use of Premises: During construction, Contractor will have full use of building site area as indicated. Contractor's use of premises is limited only by Owner's right to perform work or employ other contractors on same site.
Owner will occupy premises during construction. Perform construction only during normal working hours (8 AM to 4:30 PM Monday thru Friday, other than holidays), unless otherwise agreed to in writing by the Contracting Officer (CO). Clean up work areas and return to a useable condition at the end of each work period.
Driveways, Walkways, and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
Contractor must stay within the Owner’s Property Boundaries, which is limited to the Raco Work Center Site. All waste materials to be removed and disposed of from the entire roof area must be removed in a way to avoid entry door areas to protect the public and FS personnel from injury.
Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
END OF SECTION 011000
SECTION 013000 - SUBMITTALS
PART 1 - GENERAL
| 1.1 | REQUIREMENTS |
| A. | It will be the Contractor’s responsibility to submit all items with promptness as to cause no delay in the work. Approvals must be obtained before starting work involving the item. Contractor shall allow ten (10) calendar days for processing of submittals by the Government. |
| B. | The following submittals are required following award of contract for review and/or approval pursuant to contract provisions. |
1. The Contractor shall prepare and submit proposed progress schedule within 5 days of the effective date on the Notice to Proceed.
| 1.2 | MANUFACTURER’S LITERATURE AND SHOP DRAWINGS |
| A. | Submit one (1) copy of product data on the items required herein to the COR for approval. Literature which is not marked or otherwise designated to show the exact model, size, etc. which the Contractor proposes to use, will be returned by the COR “without action.” Circle or check items on submittals. Highlighter pens may print black or not at all when copied. |
| B. | Information must be adequate to determine compliance with specifications. |
| C. | Submit three (3) copies of materials that cannot reasonably be copied on typical copy machines. |
| D. | One (1) copy of all submittals will be returned to the Contractor. |
| E. | Submittals which are received from sources other than through the Contractor’s office will be returned by the COR “without action.” |
PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable)
END OF SECTION 013000
SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS
| 1.1 | SECTION REQUIREMENTS |
| A. | Water and Electric Power: Available from Owner's existing system without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. |
PART 2 - PRODUCTS
| 2.1 | TEMPORARY FACILITIES |
| A. | Provide field offices, storage and fabrication sheds, and other support facilities as necessary for construction operations. Store combustible materials apart from building. |
| 2.2 | EQUIPMENT |
| A. | Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures. |
PART 3 - EXECUTION
| 3.1 | TEMPORARY UTILITY INSTALLATION |
| A. | Sanitary Facilities: |
| 1. | Toilets: Use of Owner's existing toilet facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use. |
| 3.2 | SUPPORT FACILITIES INSTALLATION |
| A. | Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction. |
| 3.4 | OPERATION, TERMINATION, AND REMOVAL |
| A. | Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. |
| B. | At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. |
END OF SECTION 015000
SECTION 024119 - SELECTIVE DEMOLITION
| 1.1 | SECTION REQUIREMENTS |
| A. | Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted. |
PART 2 - PRODUCTS
| 2.1 | PEFORMANCE REQUIREMENTS |
| A. | Regulatory Requirements: Comply with EPA regulations and with hauling and disposal regulations of authorities having jurisdiction. |
PART 3 - EXECUTION
| 3.1 | DEMOLITION |
| A. | Maintain services/systems indicated to remain and protect them against damage during selective demolition operations. Before proceeding with demolition, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of the building. |
| B. | Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. |
| C. | Protect walls, adjacent roof surfaces and other existing finish work that are to remain. |
| D. | Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. |
| E. | Remove demolition waste materials from Project site and legally dispose of them. |
| F. | Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. |
END OF SECTION 024119
SECTION 073113 - ASPHALT SHINGLES
GENERAL
SECTION REQUIREMENTS
Submittals: Product Data, Samples, & Color Choices:
Shingles Drip Edge Ice & Water Shield Roof Underlayment All submittals must be approved by COR prior to purchase of materials Identify each bundle of shingles with appropriate markings of UL or another testing and inspecting agency acceptable to authorities having jurisdiction.
Exterior Fire-Test Exposure: ASTM E 108 or UL 790, Class A.
Wind-Resistance-Test Characteristics: ASTM D 3161 or UL 997 passed.
Warranties: Provide standard manufacturer's written warranty, signed by manufacturer agreeing to promptly repair or replace asphalt shingles that fail in materials within 30 years from date of Substantial Completion, prorated, with first 5 years nonprorated.
PRODUCTS`
ASPHALT FIBERGLASS SHINGLES
CertainTeed Landmark: UL Certification of ASTM D3462; Conforms to ASTM D3018 Type I - Self-Sealing; ASTM D3161-03b, Class “F” Wind Resistance (Regional) ; ASTM D3161-99a Wind Resistance; UL997 Wind Resistance; UL 2390/ASTM D6381 Class “H” and ASTM D7158 Class “H” Wind Resistance; UL 790 Class A Fire Resistance; glass fiber mat base, ceramically colored/UV resistant mineral surface granules across entire face of shingle; two-piece laminated shingle or approved equal.
Weight: 227 pounds per square (100 square feet) Color: Moire Black Wind Resistance: 110 mph Algae Resistance: 10 years Warranty: Limited Lifetime
ACCESSORIES
Underlayment: Grace Synthetic Felt or approved equal.
Self-Adhering Sheet Underlayment: Alco Ice Guard or approved equal, on all eaves.
Asphalt Roofing Cement: Black Jack All Weather Roof Cement or approved equal.
Roofing Nails: Grip Rite 1-1/4” Smooth Galvanized Coil Roofing Nails or approved equal.
Flashing and Trim:
Drip Edge: Formed sheet metal with at least a 2-inch roof deck flange and a 1-1/2-inch fascia flange with a 3/8-inch drip at lower edge, color = White
EXECUTION
INSTALLATION
Contractor will remove sections of existing roof material and cover to protect each working day. Protect stripped sections from elements, tear off only what can be completed in one day or tarp roof sections left exposed.
Shrubbery and improvements adjacent to the building shall be protected during contractors operations, staying within Owner’s property limits.
Material removed from the roof shall be legally disposed of by the contractor. At the completion of work the contractor will perform a final site cleanup.
Contractor shall provide the COR copies of all landfill load receipts.
Contractor shall inform the COR of any areas needing repair as they are uncovered.
Apply self-adhering sheet underlayment at eaves and rakes from edges of roof to at least 36 inchs inside exterior wall line.
Chimneys, vents, and protrusions shall be flashed with new flashing.
Shingles will be attached to flashing with plastic cement.
Install first and remaining courses of asphalt shingles stair-stepping diagonally across roof deck with manufacturer's recommended offset pattern at succeeding courses, maintaining uniform exposure.
Shingle courses shall be laid straight and checked with chalk lines during construction.
Use recommended number of fasteners per shingle and place fasteners according to the shingle manufacturer’s specifications.
Raco Ten Bay Building Re-Roofing Hiawatha National Forest
END OF SECTION 073113