This document is a Contract Data Requirements List (CDRL) for a federal government contract related to engineering services and data deliverables. The key details are:
The CDRL is for a contract titled "Essential Engineering Services in support of the C130J sustaining engineering requirements" with Solicitation Number FA850924F0023. The contract is an Indefinite Delivery, Indefinite Quantity (IDIQ) Cost-Reimbursement, No-Fee contract with a basic year plus four one-year option periods. The contractor is required to provide engineering services, materials, travel, and data to support all SOF/PR C-130 aircraft, with a focus on cyber support, modification analysis, reverse engineering, testing, reliability assessment, and sustainment.
The CDRL specifies numerous technical data package (TDP) requirements, including product drawings/models, artwork, test data, marking, and software/memory device data. It also details inspection, approval, and distribution requirements for the TDP deliverables. Specific submittal timelines and formats are provided, such as sample submittals, Bill of Materials, final paper copies, and final digital data deliveries. The contracting office is AFLCMC/LZPEM at Robins AFB.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
BLOCK 16:
1. Government Activity and Part Identification: The contractor shall comply with Air Force drawing 9626025 (CAGE 98752), titled “Air Force Drawing Requirement”. This requirement defines format requirements for the generation of Air Force drawings. The contractor shall use the Government activity identifier Commercial and Government Entity (CAGE) code and Air Force drawing numbers. The contractor shall contact the AFLCMC/LZPEM EDMS to obtain the drawing numbers.
1.1. Engineering Change Orders (ECOs): When an existing Air Force CAGE code drawing is revised, all ECOs shall be incorporated prior to the paper submittal for review.
1.2. Concurrent with the final submittal, all ECO’s against existing Air Force CAGE code drawings shall be incorporated and a copy of the ECO shall be delivered for Air Force revision documentation.
2. Content, format, and media requirements for delivery of Digital Engineering Data: The contractor shall comply with Air Force drawing 9579776 (CAGE 98752).
3. Product Drawings/Models and Associated Lists: Product drawings/models and associated lists shall be prepared to provide the design, engineering, and manufacturing information necessary to enable the procurement or manufacture of an item essentially identical to the original item. The product shall be defined to the extent necessary for a competent manufacturer to produce an item, which duplicates the physical, interface, and functional characteristics of the original product, without additional design engineering effort or recourse to the current design activity. Product data shall reflect the approved, tested and accepted configuration of the defined delivered item. This includes but is not limited to special tooling, interface hardware, special test equipment, and support equipment.
4. Engineering Drawing Practices: The contractor shall use the practices described in ASME Y14.100-2017. For clarification, the documents listed in section 2 of ASME Y14.100-2017 shall be considered first tier and shall apply. The contractor may find it useful to incorporate the concepts of MIL-HDBK-288 into the preparation of the TDP. MIL-HDBK-288 refers to Engineering Drawing Package (EDP); this term shall be considered synonymous with TDP. In instances where the ASME standards do not fully define requirements concerning preparation of engineering drawings, the contractor may use the guidance provided in the Drawing Requirements Manual (DRM) 11th Edition available from IHS, Inc. copyright 2008.
5. Control Drawings: Control drawings shall be created in accordance with DI-SESS-81000F and ASME Y14.24-2012 to depict engineering criteria used in selecting purchased or vendor developed items. Control drawings shall disclose engineering form, fit, function and performance requirements for the acquisition of interchangeable purchased items of existing designs, or of items specially developed by vendors to the control drawing requirements. When COTS/purchased items are used by the contractor and are part of this effort as defined in the tasking document (SOW, PWS, etc.), control drawings shall be developed and delivered. Control drawings not developed for this contract that are part of the deliverable TDP shall be updated, to show current information (i.e., performance/qualification requirements, vendors/sources names and part numbers.)
5.1. Control drawings are not required for items which are Government directed purchases or for Government Furnished Material/Government Furnished Equipment (GFM/GFE). Such items shall be identified using the GFE/GFM notation on the parts list, etc. The use of a flag note is acceptable.
6. Contract Numbers: For specifications, processes and standards When a TDP document is prepared under a Government contract, the Government contract number under which it is prepared shall appear on the first sheet of the document original. When a TDP document is delivered under a Government contract other than the one under which it was prepared, the Government contract number under which it is delivered shall also appear on the first sheet of each copy submitted. If the document is prepared and submitted under the same contract, only the entry for the contract under which it is prepared is required.
7. Application Data: All new and revised drawings shall contain Application Data. The Application Data is mandatory for all drawings. The Application Data shall show the “Next Assembly” and “Used On”. The application data shall be located near the title block on sheet 1, placed on a separate referenced document, or provided on a separate parts list. When the application data appears on a separate referenced document, a cross reference note shall be included on each parent drawing to indicate that a separate referenced document is available. When an item is used in more than three applications, the entry “general usage” may be entered in the “Used On” column.
8. Reference Documents: Documents referenced in a TDP shall be furnished as part of the TDP with the exception of those specified in referenced documents available in Acquisition Streamlining and Standardization Information System (ASSIST) and non-Government standardization documents available from the issuing non-Government standards body, such as the American Society of Mechanical Engineers (ASME). The following types of documents shall not be referenced in a TDP: technical manuals, procedural manuals, maintenance manuals, company drafting manuals, management plans, uncontrolled documents or unreleased documents. However, when information essential to meeting the content of a TDP (such as default surface texture values) is contained within such prohibited documents, that information shall be extracted from the reference document and included in the TDP.
8.1 Prohibited Documents, References, and Phrases: Technical Orders (TOs), Time Compliance Technical Orders (TCTO), pamphlets, recordings, National Stock Numbers (NSNs), To Be Determined (TBD), Statement of Work ((TASKING DOCUMENT)), Performance Work Statement (PWS), Statement of Objectives (SOO), and Contract Data Requirements List (CDRL), shall not be referenced within the TDP.
9. Traceability: The contractor shall prepare the TDP in such a manner to ensure that all applicable documents and part or identifying numbers (PINS) i.e., Artwork, Schematics, Software/Programming Data, Test Criteria, etc., are referenced within the TDP for traceability.
9.1 If the contractor is the original equipment manufacturer (OEM), impacted engineering data that are part of the effort as defined in the tasking document (SOW, PWS, etc.) shall be revised to include changes to reflect the delivered item’s configuration.
9.2 If the contractor is not the OEM, the contractor shall ensure impacted engineering data that are part of the effort as defined in the tasking document (SOW, PWS, etc.) are updated and delivered to reflect the delivered items configuration.
10. Preparation Method: American English language shall be used in the preparation of this TDP. Dimensioning and Tolerancing shall be Decimal Inch in accordance with ASME Y14.5-2009. Size and format of drawings shall be Decimal Inch per ASME Y14.1. All drawings shall be prepared using Third Angle Orthographic Projection method of presentation. The symbol for angle of projection shall be delineated in the Title Block of newly prepared or revised engineering data. (ASME Y14.3-2003 figure 2)
11. TDP Validation: The contractor shall validate that the TDP conforms to the contractual requirements, and that they accurately depict the item(s) developed, modified, or produced under the contract.
12. Clarification of Detailed Test Criteria for Electrical and Avionics Items: Test criteria for items designed or developed with Government funds is an inherent part of the TDP. Test criteria shall be incorporated, either directly on each TDP document or by reference, for each end item, top assembly item, configured item, and lowest assembled item IAW Air Force drawing 9579777 (CAGE 98752), titled “Clarification of Detailed Test Criteria for Electrical and Avionics Items.”
13. Associated Lists: Parts Lists per ASME Y14.34 are required. Parts Lists are required at assembly level. Parts Lists for Contractor Activity identifier CAGE code may be an integral part of a document or it may be a separate document. The identification and quantity of parts shown on the assembly drawing shall agree with the parts list.
14. Marking: Drawings shall specify requirement for marking part number identification on items as required by MIL-STD-130N and other applicable documents referenced therein. Item unique identification (IUID) marking is mandatory for applicable items as determined by the Program Office. (See DFARS 252.211-7003 Item Identification and Valuation) The drawings shall identify the content, method of application, material and location of marking on the part.
15. Printed Board Artwork Master Drawing. The printed board artwork master drawing shall include images of all artwork required to manufacture the printed board. These images will serve as a reference to those images produced from the Gerber data files IAW Air Force drawing 9579776 (CAGE 98752) titled “Product Data Specification”. These requirements are IAW ASME Y14.24-2012 paragraph 15.3 and the IPC-standards called out in these paragraphs. Also, this drawing shall reference a unique part or identifying number (PIN) with revision data for the digital file set which includes the Gerber, test, and drill data files. The PIN number format structure and characters shall meet the same requirements as for the part number.
16. Printed Board Artwork Master, Test, and Drill NC Data. The printed board artwork master, test, and NC drill data shall be delivered IAW Air Force drawing 9579776 (Cage 98752). These requirements are IAW ASME Y14.24-2012 paragraph 15.3 and the IPC-standards called out in these paragraphs.
17. Legacy Stable Base Media (Mylars, un-dimensioned drawings, master patterns, etc.). Data originally produced on stable base drawing media that has been redrawn/converted/reproduced in a digital format or developed on a CAD platform shall be delivered.
18. Legibility and Reproducibility: All documents prepared or submitted shall meet the and reproducibility requirements of the specification or standard controlling the media in which the data is to be delivered. As a minimum, all lines, symbols, letters, and numerals shall be readable.
19. Protecting Classified Information: TDPs or parts thereof, containing classified information shall be protected and marked in accordance with the Department of Defense National Industrial Security Program Operating Manual for Safeguarding Classified Information, DoD Manual 5220.22-M. When 3D TDP data is used, the solid models shall display classification marking clearly visible when the solid model is first opened.
20. Software and Memory Device Data: Software and Memory Device drawings shall be selected per ASME Y14.24 and CAD/CAM data files shall be delivered per Air Force drawing 9579776 (CAGE 98752).
21. Inspection of TDP: The TDP shall be inspected for the following:
a. Compliance with the requirements of this contract.
b. Inclusion of all documents, including sub-tier references, required to meet the design disclosure requirements of the TDP.
c. Accuracy of the assignment and identification of security markings, restriction statements (for example distribution statements), export control notices, rights-in-data legends, and other special markings.
d. Inclusion of contract numbers and contractor identifications.
e. Legibility and reproducibility.
f. TDP components have not been prepared for requirements, which could be met by existing standardization documents.
g. Completeness and accuracy of the TDP documents, including required quality assurance information, in describing design of the item, its subassemblies, and component parts. The design to be described by the TDP documents is that configuration of the item the Government has approved, tested, or accepted.
h. Both Type 2D and Type 3D TDPs shall open in the appropriate software without regeneration errors or warnings.
22. Source Control Drawing (SOCD) Approval Request. Source control drawing approval requests (as referenced in MIL-STD-31000A and corresponding Appendix A) shall be prepared and submitted to the requiring office in Block 6 of this DD Form 1423-1 prior to the preparation or use of a source control drawing. Each potential source control item shall be approved by the Air Force System Engineer prior to inclusion of the source control drawing in the TDP. SOCD approval requests are used to ensure that only valid source qualification requirements are included in the TDP. Under Public Law, the Government will actively seek multiple sources for any item for which source qualification is a requirement. Air Force engineering will evaluate each request and notice will be promptly given regarding approval/disapproval. Requests shall be by letter and shall be prepared and submitted as follows:
a. Format - The Source Control Drawing Approval Request shall be in the contractor’s format.
b. Content - The request shall specify the following:
(1) Nomenclature and description of the item.
(2) The critical application(s) for which the item is to be used.
(3) Number of applications per end item.
(4) System performance requirements requiring source qualification.
(5) Procedures and criteria required to qualify a source.
(6) Sources of supply and manufacturers’ part numbers.
(7) Cost of the item involved.
(8) Estimated cost to qualify a source.
PREVIOUS EDITION MAY BE USED.
DD FORM 1423, FEB 2024
Page of
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoDM 5010.12 for detailed instructions.)
DD FORM 1423, FEB 2024
Page of
CONTRACT DATA REQUIREMENTS LIST
C. CATEGORY:
14. DISTRIBUTION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES Draft Final Reg Repro
16. REMARKS
14. DISTRIBUTION
15.TOTAL
Image of arrow pointing towards totals
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator).
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Name of preparer of CDRL.
Item H. Date CDRL was prepared and signature of preparer of CDRL.
Item I. Name of CDRL approval authority.
Item J. Date CDRL was approved and signature of CDRL approval authority.
Item 1. See DFARS Subpart 204.71 for proper numbering. To add or delete additional data items, point and click the plus or minus sign to the right of Block J.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref. DoDI 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.
Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government’s rights to use the data shall be governed by the pertinent provisions of the contract.
9.0.0.2.20120627.2.874785 DD Form 1423, "Contract Data Requirements List" delete continuation Show Attachment Bar
| CurrentPage: |
| PageCount: |
| Select Classification from drop-down list.: 1 |
| DI: |
| Click on this button to attach a file(s).: |
| A. CONTRACT LINE ITEM NUMBER: 0004 |
| exhibit: A-H |
| C. CATEGORY: Select for "TDP.": 0 |
| C. CATEGORY: Select for "TM.": 0 |
| C. CATEGORY: Select for "OTHER.": 1 |
| C. CATEGORY: Enter specification for "Other.": SESS |
| System: SOF/FW Sustainment Engineering Support |
| ContractNum: FD2060-23-33442 |
| Contractor: Mercer Engineering Research Center (MERC) |
| 1. DATA ITEM NUMBER: A-H006 |
| titleDataItem: Product Engineering Design Data and Associated Lists |
| subtitle: |
| 4. AUTHORITY (Data Acquisition Document Number): DI-SESS-81000F/T |
| contractRef: PWS Para 4.6.1, 4.7, 4.7.1 |
| reqOffice: AFLCMC/LZPEM |
| 7. DD 250 REQUIREMENT: DD |
| 8. APPROVAL CODE : A |
| 9. DISTRIBUTION STATEMENT REQUIRED: D |
| freq: QRTLY |
| asOfDate: 15 |
| dateFirstSub: ASREQ |
| dateSubseqSub: ASREQ |
| 16. REMARKS: |
1. Air Force drawings 9626025 rev G, 9579776 rev N and 9579777 rev B (CAGE 98752) are a part of this CDRL A copy of the drawings may be requested through the Procurement Contracting officer
2. METADATA SHALL BE IN ACCORDANCE WITH 9579776 PARAGRAPH 10 OPTION ONE
3. Please reference EDATS control number 2023-25 on all correspondence related to this effort.
Vendor Item Control Drawings shall be used to specify the requirements for purchased items when such items have been approved for use in the design and are used without alteration, selection or source qualification (testing of an item prior to procurement action to ensure that it satisfies the specified requirements). Reference paragraph 7.1 of DI-SESS-81000F.
BLK 4: DI-SESS-81000F is tailored as follows:
Requirements: (the below paragraph numbering corresponds with the numbering in the DID)
1. Reference Documents. Delete paragraph 1. in its entirety and replace with “1. Reference Documents. The documents apply as cited in the DD Form 1423-1 and continuation sheets. Unless otherwise noted, the latest revision of the ASME Standard at the time of solicitation shall apply.”
3. Format. Delete in its entirety and replace with “3. Format. Product Drawings/Models and Associated Lists shall be in the format as specified on this DD Form 1423-1 and continuation sheets, and shall meet the requirements of ASME Y14.1."
4. Content. Delete in its entirety and replace with “4. Content. Product Drawings/Models and Associated Lists shall conform to the requirements of ASME Y14.100-2017, Appendix B, sections B6 through B9.1 and Appendices C,D, E, and F in conjunction with ASME Y14.24-2012, ASME Y14.34, ASME Y14.35 and ASME Y14.41. They shall document directly or by reference the following (items a through q), as applicable:”
6. CAGE code. Delete “TDP Option Selection Work Sheet incorporated in the contract or purchase order.” and replace with “DD Form 1423-1 and continuation sheets.”
7. Selection of drawings. Delete “The TDP Option Selection Work Sheet incorporated in the contract or purchase order will specify whether the contractor or the Government is responsible for selecting the types of drawings and associated lists.” and replace with “The contractor shall comply with ASME Y14.24, Types and Applications of Engineering Drawings”.
BLK 7: Contractor shall submit a final DD Form 250 to DODAAC FA8509; via WAWF, sheriann.tilley@us.af.mil
BLK 8: The Government will approve/disapprove within thirty business days of receipt. Contractor will have fifteen days to incorporate any corrections before final approval.
| Click to add continuation field for Remarks: |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: AFLCMC/LZPEM |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: 285 Cochran Street |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: Robins AFB, GA |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: 31098-1669 |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: Paper Copy |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: Digital Data |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: (Classified) |
| 14. DISTRIBUTION - a. ADDRESSEE, new line: Digital |
| 15.TOTAL - Total draft copies is automatically calculated.: 1 |
| 15.TOTAL - Total draft copies is automatically calculated.: 1 |
| 15.TOTAL - Total final regular copies is automatically calculated.: 2 |
| 15.TOTAL - Total final reproducible copies is automatically calculated.: 1 |
| 15.TOTAL - Total final reproducible copies is automatically calculated.: 1 |
| 15.TOTAL - Total final reproducible copies is automatically calculated.: 2 |
| priceGrp: |
| estTotalPrice: |
| remarks: BLK 9: Distribution authorized to U.S. Government Agencies and their contractors (Critical Technology) (6 Jun 2023). Other request for this document shall be referred to AFLCMC/WIUAG. |
EXPORT CONTROL WARNING LABEL. All engineering data shall be marked with Export Control Warning Labels in accordance with DoD Instruction 5230.24, dated August 23, 2012 as follows:
“WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq.), as amended. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.”
DESTRUCTION NOTICE. Mark documents with one of the following:
a. For unclassified limited documents: “DESTRUCTION NOTICE. Destroy by any method that will prevent disclosure of contents or reconstruction of the document.”
b. For classified documents: “DESTRUCTION NOTICE. Follow the procedures in DoD 5220.22-M, National Industrial Security Program Operating Manual, Chapter 5, Section 7, or DoD 5200.1R, Information Security Program, Chapter 6.”
BLK 10: Revisions/changes to the final delivered data shall be furnished quarterly, commencing the first quarter after destination acceptance of the final reproducible data and continue until the contract is closed. Quarterly updates shall include an updated BOM, reference A.F. Drawing 9579776. Negative reports shall be submitted to AFLCMC/LZPEM.
BLK 11: Fifteen days before the end of the quarter.
BLOCKS 12 & 13:
1a. SAMPLE SUBMITTALS: As early as possible, but no later than 50% of TDP creation, the contractor shall submit four (4) representative samples of each digital data format of data for this project in accordance with Air Force drawing 9579776 (CAGE 98752), (Native, Neutral, HPGL, Metadata Spreadsheet, Gerber, Software/Memory Device Data, etc.).
1b. All data submittals shall contain a delivery letter and a shipping list. The letter shall contain at a minimum the contract number, delivery order, CLIN, and EDATS number (located on the bottom right corner of the DD Form 1423). The shipping list shall include as a minimum, the document number, revision level, and number of sheets/pages. The data delivered shall be in the same sequence as the shipping list. Shipments of data must be for a complete Technical Data Package (TDP) that accurately depicts the final product as defined in the tasking document (SOW, PWS, etc.). Shipping list shall specify whether the shipment is updates, final or make-up.
2. Within 90 days after successful government verification of the prototypes, a Bill of Materials (BOM) in accordance with Air Force drawing 9579776 (CAGE 98752) shall be delivered.
3. Within 90 days after successful government verification of the prototypes, one set of paper copies of all "final reproducible data" (reference Block 14 of the DD 1423-1) shall be delivered. A letter of transmittal shall accompany submittal. Paper copy submittal will be reviewed within 120 days after receipt of data, unless additional time is required, at which time the contractor will be notified. When the submittal does not meet the contractual requirements a discrepancy letter will be submitted through Government Contracting Officer with a suspense date for the contractor to resubmit the TDP with corrections incorporated.
a. Submittal of programming files, in accordance with Air Force drawing 9579776 (CAGE 98752), Software and memory Device Data is not required for this (paper) submission.
4. Within 60 days after approval of paper copy, one set of all “final reproducible digital data” to include Native, Neutral, HPGL, Metadata Spreadsheet, Gerber, Software/Memory Device Data, etc. (reference Block 14 of the DD 1423-1) shall be delivered to AFLCMC/LZPEM, 285 Cochran Street, ROBINS AFB GA. 31098-1669. If changes have been required to the BOM since delivery in paragraph 3 above, resubmittal shall be required. The final digital submittal will be reviewed within 60 days after receipt of data, unless additional time is required, at which time the contractor will be notified. In the event the submittal does not meet the contractual requirements, a discrepancy letter will be submitted through the Government Contracting Officer with a suspense date for the contractor to resubmit the final digital TDP with corrections incorporated.
SEE CONTINUATION SHEETS
| preparedBy: Sheriann Tilley, AFLCMC/WIUAG |
| J. SIGNATURE: H. SIGNED ON 20240430 |
| J. SIGNATURE: J. SIGNED ON 20240430 |
| J. SIGNATURE: |
| approvedBy: Jerrie Schack, AFLCMC/WIUWC |
| Click to add additional data items.: |
| Click to delete additional data items.: |